Silver County
by Ivory Buildtech Pvt. Ltd. · Village Wazirpur, Sector 95A, District Gurugram, Haryana
- RERA registration
- GGM/729/461/2023/73
- Registered on
- 3 Jul 2023
- Valid till
- 5 Jan 2028
- Project ID
- RERA-GRG-1286-2023
- Land area
- 5.025 acres
- Plots
- 89
- Completion (as filed)
- 5 Jan 2028
- Estimated cost
- ₹ 36.22 Cr
RERA registration
| Registration certificate | GGM/729/461/2023/73, dated 3 Jul 2023 |
|---|---|
| Registration valid till | 5 Jan 2028 |
| Project ID | RERA-GRG-1286-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Silver County |
| Promoter | Ivory Buildtech Pvt. Ltd. |
| Promoter’s registered office | 302, 3RD Floor, Indraprakash Building, 21 Barakhambar Road, New Delhi 110001 |
| CIN | U70100DL2011PTC219839 |
| Site address | Village Wazirpur, Sector 95A, District Gurugram, Haryana |
| Sector | Sector 95A |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 9 Jan 2023 |
| Construction start (as filed) | 15 Feb 2023 |
| Completion (as filed) | 5 Jan 2028 |
| Application submitted | 24 Apr 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter Diapatched
-
Hearing
Examination By Authority View order
Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Rishabh Jain is present on the behalf of the promoter. The AR of the promoter states that they are in the process of submitting the reply in the Authority and requests for a short adjournment of two weeks. The matter to come up on 29.05.2023.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated 29.05.2023 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Rishabh Jain, Advocate is present on the behalf of the promoter. The promoter has submitted the reply in the authority on 26.05.2023 which is yet to be scrutinized. The matter to come up on 12.06.2023 for further proceedings.
-
Hearing
Objection View order
Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Sachin Jain (AR) and Sh. Rishabh Jain (Advocate) are present on the behalf of the promoter. The AR of the promoter states that they have submitted the reply to remaining deficiencies on Friday, 09.06.2023. The concerned executive to examine the same. The matter to come up on 26.06.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Sachin Jain (AR) and Sh. Rishabh Jain (Advocate) are present on the behalf of the promoter. The AR of the promoter is advised to complete the deficiencies in two days. The matter to come up on 03.07.2023.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Proceedings dated 03.07.2023. Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Sachin Jain (AR) and Sh. Rishabh Jain (Advocate) are present on the behalf of the promoter. The AR is submitting the copy of land title search report, corrected allotment letter and BBA format along with corrected BG for submission of approved service plans and estimates (mistakenly mentioned as BG for submission of electric load availability) within three months from the date of registration. The concerned official has checked and confirmed. Approved as proposed.
- Registration granted GGM/729/461/2023/73
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 5.025 acres |
|---|---|
| Total licensed area | 5.025 acres |
| Licence | Licence Number 03 of 2023 Dated 06.01.2023 |
| FAR permissible / proposed | 1 / 1 |
| Estimated project cost | ₹ 36.22 Cr |
| Cost of land | ₹ 18.15 Cr |
| Infrastructure and other structures | ₹ 6.88 Cr |
| EDC, taxes, levies and other costs | ₹ 11.2 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 2.4949 | 49.6% |
| Construction Of Roads | 1.4557 | 29% |
| Parks And Playgrounds | 0.3769 | 7.5% |
| Area To Be Left For Transferring To The Government For Community Services | 0.5025 | 10% |
| Commercial | 0.195 | 3.9% |
Plots 89 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 100.98 | 121 | 1,087 | 36 |
| 102.92 | 123 | 1,108 | 4 |
| 105.87 | 127 | 1,140 | 22 |
| 107.42 | 128 | 1,156 | 1 |
| 112.87 | 135 | 1,215 | 1 |
| 133.87 | 160 | 1,441 | 12 |
| 138.72 | 166 | 1,493 | 1 |
| 141.83 | 170 | 1,527 | 4 |
| 143.73 | 172 | 1,547 | 1 |
| 144.11 | 172 | 1,551 | 1 |
| 150.00 | 179 | 1,615 | 1 |
| 150.00 | 179 | 1,615 | 4 |
| 150.00 | 179 | 1,615 | 1 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | No |
| Water Supply | HSVP | No |
| Electricity | UHBVNL | No |
| Sewage Disposal | HSVP | No |
| Storm Water Drainage | HSVP | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.14 Cr | As Per Project Report |
| Water Supply System | ₹ 1.51 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 56.44 lakh | As Per Project Report |
| Electricity Supply System | ₹ 1 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.08 Cr | As Per Project Report |
| Street Lighting | ₹ 19.28 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 4.19 lakh | As Per Project Report |
| Mtc Of Services | ₹ 1.35 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| 1. Licence No. 03 Of 2023 | Already Been Obtained | 6 Jan 2023 |
| Layout Plan | Already Been Obtained | 9 Jan 2023 |
| Zoning Plan | Already Been Obtained | 5 May 2023 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable Being Plotted Colony |
|---|---|
| Wall Finishing Details | Not Applicable Being Plotted Colony |
| Kitchen Details | Not Applicable Being Plotted Colony |
| Bathroom Fittings | Not Applicable Being Plotted Colony |
| Wood Work Etc | Not Applicable Being Plotted Colony |
| Doors And Windos Frames | Not Applicable Being Plotted Colony |
| Glass Work | Not Applicable Being Plotted Colony |
| Electric Fittings | Not Applicable Being Plotted Colony |
| Conducting And Wiring Details | Not Applicable Being Plotted Colony |
| Cupboard Details | Not Applicable Being Plotted Colony |
| Water Storage | Not Applicable Being Plotted Colony |
| Lift Details | Not Applicable Being Plotted Colony |
| External Glazings | Not Applicable Being Plotted Colony |
| Windows/Glazings | Not Applicable Being Plotted Colony |
| Doors | Not Applicable Being Plotted Colony |
| Main Doors | Not Applicable Being Plotted Colony |
| Internal Doors | Not Applicable Being Plotted Colony |
| Air Conditioning | Not Applicable Being Plotted Colony |
| Electrical Fittings | Not Applicable Being Plotted Colony |
| Cng Pipe Line | Not Applicable Being Plotted Colony |
| Provision Of Wifi And Broadband Facility | Not Applicable Being Plotted Colony |
| External Finishing/Colour Scheme | Not Applicable Being Plotted Colony |
| Internal Finishing | Not Applicable Being Plotted Colony |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.