Unit NO.101,Groundfloor,Tower-A,Signaturetower South City-1,Gurugram, Haryana-122001
CIN
L70100DL2000PLC104787
Site address
Village - Faizalpur Jharsa, Sector-71, Gurugram, Haryana
Sector
Sector 71
Tehsil / District
Badshahpur St / Gurugram
Building plans approved
21 May 2025
Construction start (as filed)
1 Jun 2025
Completion (as filed)
31 May 2031
Application submitted
20 May 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
Application received by HRERA Gurugram
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Deepika, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Vineet Maheshwari (AR), Sh. Siddhartha Kapoor (AR), Sh. Vedant Batra (AR) and Sh. Ravinder (AR) are present on behalf of the promoter. Meanwhile, the project site was visited on 04.06.2025 by the concerned Planning Executive (PE), and it was observed that the proposed Group Housing Colony is well connected with a 24-meter-wide road. Approved as proposed subject to submission of deficit late fees which otherwise is leviable from the erstwhile licensee i.e. M/s Vipul Ltd. For the license granted by the DTCP in the year 2010. A confirmation from DTCP shall be obtained if any building plan prior to above transfer of license in favor of applicant promoter has been sanctioned or not and thereafter the matter shall be examined in terms of the advice of AG and HREAT orders. Other deficiencies shall also be rectified and DD/BG of Rs. 25 lakhs shall be submitted for submission of fire NOC within four months. The approved SPE shall be submitted within two months as BG of Rs 5,75,00,000/- has already been submitted to DTCP for release of approved SPE which otherwise has been technically approved by CE, HSVP.
Registration grantedGGM/955/687/2025/58
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
8.12 acres
Total licensed area
22.5 acres
Licence
09 of 2010 Dated 23.01.2010 Renewed up to 22.01.2030
FAR permissible / proposed
3.15 / 3.15
Estimated project cost
₹ 2,228.13 Cr
Cost of land
₹ 487.14 Cr
Cost of construction
₹ 1,293.74 Cr
Infrastructure and other structures
₹ 15.97 Cr
EDC, taxes, levies and other costs
₹ 431.28 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
0.9857
12.1%
Construction Of Roads
2.3167
28.5%
Parks And Playgrounds
3.711
45.7%
Vehicle Parkings
0.1638
2%
Club House
0.254
3.1%
Area To Be Left For Transferring To The Government For Community Services
0.5
6.2%
Any Other
0.1081
1.3%
Commercial
0.0807
1%
Apartments 837 units · 3 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
167.83
1,807
70
Apartment/Shops/Other Buildings
118.52
1,276
280
Apartment/Shops/Other Buildings
108.52
1,168
420
Apartment/Shops/Other Buildings
29.24
315
2
Apartment/Shops/Other Buildings
219.50
2,363
22
Apartment/Shops/Other Buildings
18.64
201
43
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
GMDA (CONNECTED)
No
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
No
Storm Water Drainage
GMDA (OWN ARRANGEMENT)
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 3 Cr
Submitted To Town & Country Planning
Water Supply System
₹ 5.16 Cr
Submitted To Town & Country Planning
Storm Water Drainage
₹ 1.5 Cr
Submitted To Town & Country Planning
Sewage Treatment & Garbage Disposal
₹ 2.42 Cr
Yet To Be Prepared
Street Lighting
₹ 31.16 lakh
Submitted To Town & Country Planning
Playgrounds And Parks
₹ 26.66 lakh
Submitted To Town & Country Planning
Ms Charges
₹ 3.31 Cr
Submitted To Town & Country Planning
Statutory approvals
Approval
Status
Date
Transfer Of License
Already Been Obtained
29 Apr 2024
Environmental Clearance
Already Been Obtained
3 Jan 2025
Airport Height Clearance
Already Been Obtained
9 Mar 2024
Power Assurance
Already Been Obtained
23 May 2024
Sewerage Assurance
Already Been Obtained
26 Apr 2024
Stp Assurance
Already Been Obtained
26 Apr 2024
Water Assurance
Already Been Obtained
26 Apr 2024
Br-III
Already Been Obtained
21 May 2025
Specifications (as filed)
Flooring Details Of Various Parts Of House
Marble/Vitrified Tiles/ Porcelein Tiles
Wall Finishing Details
Acrylic Emulsion Paint/Obd
Kitchen Details
Marble/Vitrified Tiles/ Porcelein Tiles
Bathroom Fittings
As Per Indian Standard/ Hindware/ Parryware Equivalent
Doors And Windos Frames
Aluminum Frames With Toughened Glass
Glass Work
Toughened Glass
Electric Fittings
Isi Marked
Conducting And Wiring Details
Isi Marked
Lift Details
4 No Of Flates & 4 Lifts
External Glazings
Aluminum Frames With Toughened Glass
Windows/Glazings
Aluminum Frames With Toughened Glass
Doors
Flush Panel Door
Main Doors
Flush Panel Door
Internal Doors
Flush Panel Door
Air Conditioning
Isi Marked
Electrical Fittings
Isi Marked
External Finishing/Colour Scheme
External Grid Paint/ Texture Paint
Internal Finishing
Acrylic Emulsion Paint
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Signatureglobal Cloverdale Spr?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.