Signature Global City 63A (1)
by Signatureglobal (India) Limited · Village Kadarpur Sector 63
- RERA registration
- GGM/581/313/2022/56
- Registered on
- 27 Jun 2022
- Valid till
- 26 Feb 2027
- Project ID
- RERA-GRG-1063-2022
- Land area
- 5.013 acres
- Apartments
- 205 in 20 towers
- Completion (as filed)
- 28 Feb 2025
- Estimated cost
- ₹ 192.68 Cr
RERA registration
| Registration certificate | GGM/581/313/2022/56, dated 27 Jun 2022 |
|---|---|
| Registration valid till | 26 Feb 2027 |
| Project ID | RERA-GRG-1063-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Signature Global City 63A (1) |
| Promoter | Signatureglobal (India) Limited |
| Promoter’s registered office | 13TH Floor, Dr. Gopal Das Bhawan, 28 Barakhamba Road, Connaught Place, New Delhi Central Delhi Dl 110001 In |
| CIN | U70100DL2000PLC104787 |
| Site address | Village Kadarpur Sector 63 |
| Sector | Sector 63 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 20 Dec 2021 |
| Building plans approved | 5 May 2022 |
| Construction start (as filed) | 1 Apr 2022 |
| Completion (as filed) | 28 Feb 2025 |
| Application submitted | 2 May 2022 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter Notice dispatched to the AR
-
Hearing
Examination By Authority
Proceedings
the matter is adjourned to 25.05.2022
-
Hearing
Adjournment
Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Ajay Kumar (Asst. Manager) is present on behalf of the promoter. The promoter submitted the reply to the deficiency notice in the Authority on 19.05.2022. after the scrutiny of the reply, there are still deficiencies pending in the application. Further, a loan of Rs. 95 crore has been availed by the promoter against the security of land and receivables arising from sold and unsold inventory of the project. Accordingly, the promoter shall submit undertaking issued by the bank regarding the rights and interests of allottees as per section 11(4)(h) of the Act. The AR of the promoter is directed to submit the deficit documents as listed below in the Authority before the next date of hearing. 1. The annexures in the online DPI are not uploaded as well as the correction needs to be done in the online(A-H). 2. Copy of approved service estimates and plans along with a sanction letter from DTCP, Haryana needs to be submitted. 3. Cost of land needs to be clarified. An annexure in support of the same needs to be provided. 4. Escrow agreement executed with bank needs to be submitted. 5. Form REP-II needs to be corrected. 6. Escrow agreement with the bank needs to be provided. 7. CA Certificate for default in repayment of govt. dues needs to be submitted, certificate must be issued by chartered accountant and it is not prior to six months from the date of application. 8. Bank undertaking as per section 11(4)(h) of the Real Estate (Regulation and Development), 2016 needs to be submitted. Some of the deficiencies have been attended which need to be scrutinised by the office. Left out deficiencies as mentioned out of the above if pending be attended by the promoter before next date of hearing. The Authority has viewed it seriously that QPRs and annual audit reports of various projects by the promoter or its associated companies have not been regularly submitted. The promoter may reconcile the reports if submitted in the Authority and balance reports be completed within a week both in online and offline mode. The Authority reserves its right to initiate penal proceedings against the promoter for violation of section 4 and section 11(1) of the Act. The matter to come up on 30.05.2022.
-
Hearing
Objection
Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Ajay Kumar (Asst. Manager) and Sh. Anurag Srivastava are present on behalf of the promoter. A certificate from the concerned branch regarding submission of the annual audit report of project accounts in respect of projects registered till 31.03.2021 and QPRs of the projects of the promoter till last quarter is to be submitted. Bank undertaking as per section 11(4)(h) of the Real Estate (Regulation and Development), 2016 needs to be submitted. The matter to come up on 06.06.2022 for compliance.
-
Hearing
Adjournment
Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Ajay Kumar (Asstt Manager) and Sh. Anurag Srivastava are present on behalf of the promoter. Apart from rectification of the above deficiencies the promoter is advised to submit a certificate from the concerned branch regarding submission of the annual audit report of project accounts in respect of projects registered till 31.03.2021 and QPRs of the projects of the promoter till last quarter is to be submitted. Bank undertaking as per section 11(4)(h) of the Real Estate (Regulation and Development), 2016 needs to be submitted. The matter to come up on 13.06.2022.
-
Hearing
Adjournment
Proceedings
The Coram is incomplete. The matter is adjourned to 27.06.2022.
-
Hearing
Approved And Ready For Certificate Issuing Process
Proceedings
Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Anurag Srivastava (Manager Legal) is present on behalf of the promoter. The AR seeks two days’ time for submission of the requisite BG for submission of service plan and estimates within three months. Further during last hearing the promoter was required to submit certificate from concerned branch for submission of QPRs and annual audit reports. The AR submits that the compliance of 4(2)(l)(D) has been made and for submission of QPRs of four projects is pending and has sought 2 weeks’ time for their submission during the separate hearing today. The AR clarifies that the QPR for which hard copy has been submitted in the Authority has also been uploaded online except for one QPR which could not be uploaded due to some technical glitch. The office to confirm the status of uploading of QPRs on website and to put up for grant of registration after receipt of BG as well as uploading of filed QPR except in respect of four projects wherein two weeks’ time has been separately allowed.
- Registration granted GGM/581/313/2022/56
- Registration valid till
Land, licence & cost
| Land area of the project | 5.013 acres |
|---|---|
| Total licensed area | 5.013 acres |
| Licence | 110 of 2021 dated 17.12.2021 |
| FAR permissible / proposed | 2.64 / 2.47 |
| Estimated project cost | ₹ 192.68 Cr |
| Cost of land | ₹ 29.05 Cr |
| Cost of construction | ₹ 87 Cr |
| Infrastructure and other structures | ₹ 5.34 Cr |
| EDC, taxes, levies and other costs | ₹ 71.29 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 1.234 | 32.7% |
| Pavements | 1.198 | 31.8% |
| Green Belts | 0.469 | 12.4% |
| Electricity Sub-Station | 0.06 | 1.6% |
| Sewage And Solid Waste Treatment Facility | 0.11 | 2.9% |
| Area To Be Left For Transferring To The Government For Community Services | 0.501 | 13.3% |
| Area Under Commercial Units | 0.201 | 5.3% |
Apartments 205 units · 20 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 88.25 | 950 | 52 |
| Apartment/Shops/Other Buildings | 71.92 | 774 | 80 |
| Apartment/Shops/Other Buildings | 54.23 | 584 | 16 |
| Apartment/Shops/Other Buildings | 723.42 | 7,787 | 57 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | ALREADY CONNECTED | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | NA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.85 Cr | Submitted To HUDA |
| Water Supply System | ₹ 1.13 Cr | Submitted To HUDA |
| Storm Water Drainage | ₹ 37.56 lakh | Submitted To HUDA |
| Sewage Treatment & Garbage Disposal | ₹ 60.19 lakh | Submitted To HUDA |
| Street Lighting | ₹ 7.69 lakh | Submitted To HUDA |
| Playgrounds And Parks | ₹ 10.57 lakh | Submitted To HUDA |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| 110 Of 2021 | Already Been Obtained | 17 Dec 2021 |
| Zoining Plan Memo No. 8147 | Already Been Obtained | 1 Feb 2022 |
| Electrical Load CH40/Dgr-26B | Already Been Obtained | 14 Jan 2022 |
| Water Supply Memo No: Ee(Proj)/GMDA/2022/44 | Already Been Obtained | 13 Jan 2022 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Marble / Stone I Tiles I Anti-Skid Tiles / Laminated I Equivalent |
|---|---|
| Wall Finishing Details | Tiles I Acrylic Emulsion I Equivalent /Obd |
| Kitchen Details | Tiles / Acrylic Emulsion / Equivalent |
| Bathroom Fittings | Standard Sanitary & Cp Fittings |
| Wood Work Etc | Hard Wood |
| Doors And Windos Frames | Wooden / Equivalent Door Frames, Anodised / Powder Coated Frames For Windows/ Upvc |
| Glass Work | Single Glass For Windows |
| Electric Fittings | Led For Only The Common Areas, Isi Marked |
| Conducting And Wiring Details | Pvc Conduits And Frls Wiring, Isi Marked |
| Water Storage | Overhead Tanks / Pvc |
| Lift Details | 1 Lift / Plot |
| External Glazings | Windows Single Glazed |
| Windows/Glazings | Upvc / Aluminium |
| Doors | Flush Doors |
| Main Doors | Laminated And Painted Flush Door With All Hardware |
| Internal Doors | Laminated And Painted Flush Doors |
| Air Conditioning | Isi Marked |
| Electrical Fittings | Isi Marked For Only The Common Areas |
| External Finishing/Colour Scheme | External Texture Paint |
| Internal Finishing | Obd / Tiles Equivalent |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.