Village Kakkar Majra & Bichpari, Tehsil Shehjadpur, District, Ambala
Tehsil / District
Shahzadpur St / Ambala
Layout plan approved
14 Aug 2025
Construction start (as filed)
1 Oct 2025
Completion (as filed)
13 Aug 2030
Application submitted
6 Nov 2025
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed for hearing on 26-11-2025
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
Registration valid till
Land, licence & cost
Land area of the project
17.2 acres
Total licensed area
17.2 acres
Licence
149 of 2025 dated 14.08.2025 valid upto 13.08.2030
FAR permissible / proposed
1.25 / 1.25
Estimated project cost
₹ 33.34 Cr
Cost of land
₹ 13.38 Cr
Infrastructure and other structures
₹ 19 Cr
EDC, taxes, levies and other costs
₹ 0.97 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
11.1261
64.7%
Construction Of Roads
5.9913
34.8%
Green Belts
0.0826
0.5%
Plots 113 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
244.56
292
2,632
3
244.78
293
2,635
9
245.01
293
2,637
1
245.23
293
2,640
3
259.92
311
2,798
4
270.91
324
2,916
15
301.37
360
3,244
2
302.61
362
3,257
1
321.18
384
3,457
2
326.90
391
3,519
1
388.57
465
4,183
3
414.53
496
4,462
2
430.44
515
4,633
1
437.14
523
4,705
2
439.96
526
4,736
1
455.07
544
4,898
1
464.34
555
4,998
1
464.48
556
5,000
1
464.52
556
5,000
48
471.75
564
5,078
1
566.72
678
6,100
1
566.93
678
6,102
9
568.44
680
6,119
1
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HWRA
No
Electricity
UHBVN/DHBVN
No
Sewage Disposal
HSPCB
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 1.5 Cr
Yet To Be Prepared
Water Supply System
₹ 2.5 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 2.32 Cr
Yet To Be Prepared
Electricity Supply System
₹ 2.45 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 2.4 Cr
Yet To Be Prepared
Street Lighting
₹ 40 lakh
Yet To Be Prepared
Playgrounds And Parks
₹ 1.7 Cr
Yet To Be Prepared
Site Related Expenses
₹ 2.9 Cr
Yet To Be Prepared
Land Filling
₹ 90 lakh
Yet To Be Prepared
Entrance Gate
₹ 65 lakh
Yet To Be Prepared
Boundary Wall
₹ 98 lakh
Yet To Be Prepared
Site Office Store
₹ 30 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
14 Aug 2025
Layout Plan
Already Been Obtained
14 Aug 2025
Zoning Plan
Already Been Obtained
31 Oct 2025
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Sigma Industrial Park, Kakkar Majra?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.