HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Approved for registration.
Registration valid till
Land, licence & cost
Land area of the project
86.537 acres
Total licensed area
126.96 acres
Licence
Drawing No DTP(RE)652/2020 dated 06.05.2022/29.09.2020
FAR permissible / proposed
2.64 / 2.64
Estimated project cost
₹ 18.35 Cr
Cost of land
₹ 60 Cr
Infrastructure and other structures
₹ 18.35 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
38.49
44.5%
Construction Of Roads
24.34
28.1%
Parks And Playgrounds
4.587
5.3%
Green Belts
3.4
3.9%
Electricity Sub-Station
1.72
2%
Area To Be Left For Transferring To The Government For Community Services
10.228
11.8%
Any Other
3.772
4.4%
Plots 494 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
494.00
591
5,317
494
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
No
ELECTRICITY
No
Sewage Disposal
No
STORM WATER DRAINAGE
No
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
656.74
Submitted To HUDA
2
WATER SUPPLY SYSTEM
246.20
SUBMITTED TO HUDA
3
Storm Water Drainage
143.50
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
82.51
Submitted To HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
123.91
SUBMITTED TO HUDA
6
Street Lighting
42.50
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
0
Yet To Be Prepared
8
PLAYGROUNDS AND PARKS
540.00
SUBMITTED TO HUDA
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
21-06-2022
(date)
6. Date of approval of Building Plans
21-06-2022
(date)
7. New projects:
i) Likely date of starting the construction work
01-09-2022
ii) Likely date of completing the project
31-03-2024
iii) Sizes of the plots to be offered in the project
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
494
494
2
0
0
3
0
0
4
0
0
5
0
0
Total
494
iv. Type of apartments to be constructed in the project:
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
(vi) Quarterly schedule of development of whole/remaining part of the project:
(c) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
149.00
Water Supply System
0
0
0
45.30
Sewerage treatment & garbage disposal
0
0
0
27.30
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
34.13
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
128.00
130.00
248.74
0
Water Supply System
55.30
50.30
95.30
0
Sewerage treatment & garbage disposal
25.23
24.30
47.25
0
Electricity Supply System
0
42.50
82.51
0
Storm Water Drainage
30.13
25.13
54.11
0
Parks and Playgrounds
0
215.00
325.00
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
Pnbmanimajra
Bank Account number
1183005900001699
IFSC code
PUNB0118300
MICR code
Na
Branch code
PUNB0118300
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 6.57 Cr
Submitted To HUDA
Water Supply System
₹ 2.46 Cr
Submitted To HUDA
Storm Water Drainage
₹ 1.44 Cr
Submitted To HUDA
Electricity Supply System
₹ 82.51 lakh
Submitted To HUDA
Sewage Treatment & Garbage Disposal
₹ 1.24 Cr
Submitted To HUDA
Street Lighting
₹ 42.5 lakh
Submitted To HUDA
Playgrounds And Parks
₹ 5.4 Cr
Submitted To HUDA
Statutory approvals
Approval
Status
Date
1
Already Been Obtained
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Sector-7, HSVP, Rewari.?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.