Registration period overHRERA Panchkula

Sector 27,28,26,Part-I,II,III

by Estateofficer,HSVP Rohtak · Estate Officer, HSVP,Sector-3,Rohtak

RERA registration
HRERA-PKL-ROH-250-2021 Lapsed Project
Valid till
31 Dec 2024
Project ID
RERA-PKL-924-2021
Land area
300.555 acres
Plots
3,053
Completion (as filed)
31 Dec 2024
Estimated cost
₹ 141.61 Cr

RERA registration

Registration certificateHRERA-PKL-ROH-250-2021 Lapsed Project
Registration valid till31 Dec 2024
Project IDRERA-PKL-924-2021
AuthorityHRERA Panchkula
Project type (as filed)New
Project nameSector 27,28,26,Part-I,II,III
Promoterof the society/trust/authority
Site addressEstate Officer, HSVP,Sector-3,Rohtak
SectorSector 3
Tehsil / DistrictRohtak / Rohtak
Construction start (as filed)9 Aug 2019
Completion (as filed)31 Dec 2024
Application submitted5 Apr 2021

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyListed for hearing.
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Panchkula
  3. Hearing Examination By Authority View order
    Proceedings

    Adjourned to 24.05.2021.

  1. Hearing Adjournment View order
    Proceedings

    Adjourned to 05.07.2021.

  2. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Registration Certificate to be issued.

  3. Registration valid till

Land, licence & cost

Land area of the project300.555 acres
Total licensed area0 acres
LicenceDTP(R)1962/2017,dt.19.06.2017,DTP(R)1964/2017,Dt.19.06.2017,DTP(R)1987/2018,Dt.09.08.2018
FAR permissible / proposed1.98 / 2.64
Estimated project cost₹ 141.61 Cr
Cost of land₹ 0 Cr
Infrastructure and other structures₹ 141.61 Cr

How the land will be used

UseAcresShare
Plots To Be Sold125.64741.8%
Construction Of Roads141.37547%
Any Other33.53311.2%

Plots 3,053 plots

Plot size (sq m)Sq ydSq ftPlots
628,092.90751,1936,760,7293053

External services

ServiceProvided byApproval taken
RoadsHSVPNo
Water SupplyPUBLIC HEALTH ENGINEERING DEPARTMENTNo
ElectricityUHBVNLNo
Sewage DisposalPUBLIC HEALTH ENGINEERING DEPARTMENTNo
Storm Water DrainagePUBLIC HEALTH ENGINEERING DEPARTMENTNo

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 55.65 CrSubmitted To HUDA
Water Supply System₹ 21.49 CrSubmitted To HUDA
Storm Water Drainage₹ 18.7 CrSubmitted To HUDA
Electricity Supply System₹ 17.15 CrSubmitted To HUDA
Sewage Treatment & Garbage Disposal₹ 15.6 CrSubmitted To HUDA
Street Lighting₹ 9.53 lakhSubmitted To HUDA
Security And Fire Fighting₹ 17.3 lakhSubmitted To HUDA
Playgrounds And Parks₹ 1.81 CrSubmitted To HUDA
Club House/Community Centre₹ 5.5 CrSubmitted To HUDA
Shopping Area₹ 5.7 CrSubmitted To HUDA
School₹ 50 lakhSubmitted To HUDA
Hospital/Dispensary₹ 5 CrSubmitted To HUDA
Police Post₹ 1.5 CrSubmitted To HUDA

Statutory approvals

ApprovalStatusDate
Dtp(R)1987/2018, Dt. 09.08.2018Already Been Obtained9 Aug 2018

Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Sector 27,28,26,Part-I,II,III?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.