Sapphire 84
by Ameya Commercial Projects Pvt. Ltd. · Sector - 84, Rev Estate Of Of Village Hayatpur, Gurugram, Haryana
- RERA registration
- GGM/830/562/2024/57
- Registered on
- 3 Jun 2024
- Valid till
- 30 Nov 2028
- Project ID
- RERA-GRG-1464-2023
- Land area
- 2.55 acres
- Apartments
- 451 in 2 towers
- Completion (as filed)
- 30 Nov 2028
- Estimated cost
- ₹ 123.85 Cr
RERA registration
| Registration certificate | GGM/830/562/2024/57, dated 3 Jun 2024 |
|---|---|
| Registration valid till | 30 Nov 2028 |
| Project ID | RERA-GRG-1464-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Sapphire 84 |
| Promoter | Ameya Commercial Projects Pvt. Ltd. |
| Promoter’s registered office | Ameya One, Golf Course Road, DLF City Phase V, Gurugram. Haryana. 122002 |
| CIN | U70200DL2009PTC195340 |
| Site address | Sector - 84, Rev Estate Of Of Village Hayatpur, Gurugram, Haryana |
| Sector | Sector 84 |
| Tehsil / District | Gurgaon / Gurugram |
| Layout plan approved | 28 Mar 2024 |
| Building plans approved | 28 Mar 2024 |
| Construction start (as filed) | 1 Dec 2023 |
| Completion (as filed) | 30 Nov 2028 |
| Application submitted | 25 Oct 2023 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter Deficiency notice
-
Hearing
Examination By Authority View order
Proceedings
Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority through notice dated 16.11.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Akshit Gupta (AR) is present on behalf of the promoter and states that approval of revised building plans has been obtained from DTCP and approved plans are being submitted today and seeks two weeks’ time for submission of remaining deficit documents. Further the AR states that no 3rd party rights or any booking in respect of project has been made and hence no consent of allottees is required and a public notice to this effect shall also be issued in two prominent newspapers one Hindi and one English inviting inviting objections if any. The matter to come up on 22.04.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Akshat Gupta (AR) is present on behalf of the promoter. The AR of the promoter seeks a short adjournment to rectify the deficiencies. The director/CEO/Project-Incharge of the promoter company is directed to be present along with the authorized representative of the landowner companies along with board resolution on the next date of hearing. The matter to come up on 13.05.2024.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the project. Sh. Akshat Gupta (AR) is present on behalf of the promoter. Sh. Saurabh Rana (AR) is present on behalf of SA Infracon Pvt Ltd and Ramprastha Housing Pvt Ltd (Landowners). The AR of the promoter states that reply to the deficiencies stand submitted on 09.05.2024 and the license of the project has been renewed and copy of the same is being submitted today along with other deficit documents. The office to examine the replies submitted by the promoter on 09.05.2024 and being submitted today. The matter to come up on 20.05.2024.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Sh. Sumeet, Engineering Officer and Ms. Suruchi Pandey, Chartered Accountant briefed about the facts of the project. Sh. Akshat Gupta, Saurabh Rana and Mrityunjay Kumar, Authorized representatives are present on behalf of the promoter. The AR of the promoter states that fire scheme approval has been received and copy alongwith the plans is submitted today. Further, the road access permission has been applied and shall be submitted within four months of grant of registration of project and if the same is not submitted within stipulated period, the necessary action may be initiated. Further the necessary corrections in financial documents shall also be made within 2 days. Approved as proposed subject to rectification/reconciliation of the financial statements made in the form A-H and DPI along with documents.
- Registration granted GGM/830/562/2024/57
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 2.55 acres |
|---|---|
| Total licensed area | 2.55 acres |
| Licence | Licence No 44 of 2019 granted by Department of Town and Country Planning |
| FAR permissible / proposed | 1.84 / 1.83 |
| Estimated project cost | ₹ 123.85 Cr |
| Cost of land | ₹ 0.15 Cr |
| Cost of construction | ₹ 82.11 Cr |
| Infrastructure and other structures | ₹ 5.39 Cr |
| EDC, taxes, levies and other costs | ₹ 36.2 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 1.4137 | 55.4% |
| Land Area To Be Used For Construction Of Apartments | 0.9363 | 36.7% |
| Watersupply | 0.04 | 1.6% |
| Stormwaterdrainage | 0.09 | 3.5% |
| Sewage | 0.06 | 2.4% |
| Streetlight | 0.01 | 0.4% |
Apartments 451 units · 2 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 119,583.58 | - | 451 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | NHAI | No |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 77.83 lakh | As Per Project Report |
| Water Supply System | ₹ 3.33 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 23.52 lakh | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 41.87 lakh | As Per Project Report |
| Street Lighting | ₹ 3.91 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 3.96 lakh | As Per Project Report |
| Mtc Charges | ₹ 55.19 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 5 Mar 2019 |
| Zoning | Already Been Obtained | 6 Mar 2019 |
| Revised Building Plans | Already Been Obtained | 28 Mar 2024 |
| Ec | Already Been Obtained | 6 Sep 2019 |
| Service Plan Estimates | Already Been Obtained | 9 May 2024 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Imported Marble / Vetrified Tile |
|---|---|
| Wall Finishing Details | Plastic Emulsion |
| Kitchen Details | Tiles |
| Bathroom Fittings | Steel |
| Wood Work Etc | Wood And Plyboard |
| Doors And Windos Frames | Wood And Plyboard |
| Glass Work | 6MM Toughened Glass |
| Electric Fittings | Philips Or Equivalent |
| Conducting And Wiring Details | Philips Or Equivalent |
| Cupboard Details | N/A |
| Water Storage | Oht/ Ugt |
| Lift Details | Johnson Control Or Equivalent |
| External Glazings | Paint |
| Windows/Glazings | Paint |
| Doors | Paint |
| Main Doors | Paint |
| Internal Doors | Paint |
| Air Conditioning | 1 To 1.5 Ton Voltas Or Equivalent |
| Electrical Fittings | Philips Or Equivalent |
| Cng Pipe Line | N/A |
| Provision Of Wifi And Broadband Facility | N/A |
| External Finishing/Colour Scheme | Paint |
| Internal Finishing | Paint |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.