Registration period overHRERA GurugramInterim ReraOC / CC on record

Samsara Part II

by Achaleswar Infrastructure Pvt. Ltd · Sector-60, Wazirabad , Gurugram

RERA registration
197 OF 2017
Registered on
15 Sep 2017
Valid till
31 Mar 2022
Project ID
RERA-GRG-617-2020
Apartments
21
Plots
7
Completion (as filed)
31 Mar 2022
Estimated cost
₹ 34 Cr

RERA registration

Registration certificate197 OF 2017, dated 15 Sep 2017
Registration valid till31 Mar 2022
Project IDRERA-GRG-617-2020
AuthorityHRERA Gurugram (Interim Rera)
Project type (as filed)New
Project nameSamsara Part II
PromoterAchaleshwar Infrastructure Pvt Ltd
Promoter’s registered officeAdani House, Plot No. 83, Sector 32, Institutional Area, Gurugram - 122001
CINU70102MH2013PTC250897
Site addressSector-60
SectorSector 60
Tehsil / DistrictWazirabad St / Gurugram
Layout plan approved12 Jun 2017
Building plans approved16 Oct 2018
Construction start (as filed)15 Sep 2017
Completion (as filed)31 Mar 2022
Application submitted11 Feb 2020

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted 197 OF 2017
  2. Application submitted online
  3. Registration valid till
  1. Application received by HRERA Gurugram

Land, licence & cost

LicenceLicense NO. 64 of 2010
FAR permissible / proposed1.98 / 1.98
Estimated project cost₹ 34 Cr
Cost of land₹ 7.3 Cr
Cost of construction₹ 15.5 Cr
EDC, taxes, levies and other costs₹ 11.2 Cr

How the land will be used

UseArea (as filed)Share
Residential Floors On Plots1,540100%

Apartments 21 units

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings112.881,2153
Apartment/Shops/Other Buildings112.971,2163
Apartment/Shops/Other Buildings114.271,23015

Areas are as filed with HRERA.

Plots 7 plots

Plot size (sq m)Sq ydSq ftPlots
1,540.001,84216,5767

External services

ServiceProvided byApproval taken
RoadsCOLONIZERNo
Water SupplyCOLONIZERNo
ElectricityCOLONIZERNo
Sewage DisposalCOLONIZERNo
Storm Water DrainageCOLONIZERNo

Statutory approvals

ApprovalStatusDate
Occupation CertificateAlready Been Obtained9 Sep 2019

Specifications (as filed)

Flooring Details Of Various Parts Of HouseImported Marble/ Laminated Flooring/ Vitrified Tiles/ Ceramic Tile
Wall Finishing DetailsAcrylic Emulsion Paint
Kitchen DetailsModular Kitchen
Bathroom FittingsJaquar Or Equivalent
Doors And Windos FramesUpvc Windows
Glass WorkToughned Glass Upvc
Lift Details6 Passengers Lift
External GlazingsToughened Glass
Windows/GlazingsUpvc Windows
DoorsVeeneered/Laminated Flush Door
Main DoorsVeenered Flush Door
Internal DoorsVeeneered/Laminated Flush Door
Air ConditioningVrv Air Conditioning In Living, Dining And All Bed Rooms
Cng Pipe LineProvision Only
External Finishing/Colour SchemeExterior Grade Paint

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Samsara Part II?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.