Land Area To Be Used For Construction Of Apartments
16,643
45.4%
Construction Of Roads
3,324
9.1%
Pavements
7,312
20%
Parks And Playgrounds
2,519
6.9%
Green Belts
608
1.7%
Vehicle Parkings
6,135
16.7%
Sewage And Solid Waste Treatment Facility
70
0.2%
Any Other
38
0.1%
Apartments 595 units · 6 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
35,677.13
-
595
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
HUDA, GURUGRAM
Yes
Water Supply
GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY
Yes
Electricity
DAKSHIN HARYANA BIJLI VITRAN NIGAM
Yes
Sewage Disposal
GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY
Yes
Storm Water Drainage
GURUGRAM METROPOLITAN DEVELOPMENT AUTHORITY
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 36.58 lakh
As Per Project Report
Water Supply System
₹ 87.52 lakh
As Per Project Report
Storm Water Drainage
₹ 22.26 lakh
As Per Project Report
Electricity Supply System
₹ 10.91 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 60.91 lakh
As Per Project Report
Street Lighting
₹ 9.46 lakh
As Per Project Report
Security And Fire Fighting
₹ 12.24 lakh
As Per Project Report
Any Other
₹ 40.08 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Assurance For Stp Treated Water
Already Been Obtained
28 Dec 2018
Aravali Noc
Already Been Obtained
21 Feb 2019
Letter Of Intent
Already Been Obtained
26 Oct 2018
Demarcation Plan
Already Been Obtained
19 Dec 2018
License
Already Been Obtained
6 Dec 2018
Zoning Plan
Already Been Obtained
7 Dec 2018
Height Clearance
Already Been Obtained
6 Mar 2019
Assurance Of Drinking Water Supply
Already Been Obtained
17 Dec 2018
Environmental Clearance
Applied For But Yet To Receive
19 Mar 2019
Specifications (as filed)
Flooring Details Of Various Parts Of House
Ceramic/ Vitrified Tiles
Wall Finishing Details
Gypsum Plaster
Kitchen Details
Ceramic Tiles, Paint, Green Marble, Sink
Bathroom Fittings
Part Ceramic Tiles, Part Paint, False Ceiling
Wood Work Etc
Doors
Doors And Windos Frames
Balcony Doors, Windows- Aluminium Framing With Glass
Glass Work
Windows & Balcony Doors
Electric Fittings
Not Provided
Conducting And Wiring Details
Anchor/Kalinga Or Equivalent
Cupboard Details
Not Provided
Water Storage
Common Overhead Tank On Terrace Of Each Towers
Lift Details
12-13 Passengers With Ard
External Glazings
Not Provided
Windows/Glazings
Aluminum Windows With Glass
Doors
Wooden Flush Doors
Main Doors
Wooden Flush Doors
Internal Doors
Wooden Flush Doors
Air Conditioning
Not Provided
Electrical Fittings
Led Lights In Common Area
Cng Pipe Line
Not Provided
Provision Of Wifi And Broadband Facility
Not Provided
External Finishing/Colour Scheme
Exterior Paint
Internal Finishing
Paint
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Rof Aalayas Phase II?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.