Ras RESIDENCY2
by Ras Developments Pvt Ltd · Sector-36 Karnal
- RERA registration
- Applied, not granted yet
- Applied on
- 12 Feb 2020
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-818-2020
- Land area
- 3.833 acres
- Estimated cost
- ₹ 83 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-818-2020 |
| Authority | HRERA Panchkula |
| Project type (as filed) | Ongoing |
| Project name | Ras RESIDENCY2 |
| Promoter | Ras Developments Pvt Ltd |
| Promoter’s registered office | 812& 812A 8TH Floor Chiranjiv Tower Nehru Place New Delhi |
| CIN | U74899DL2004PTC125080 |
| Site address | Sector-36 Karnal |
| Sector | Sector 36 |
| Tehsil / District | Karnal / Karnal |
| Application submitted | 12 Feb 2020 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 30.03.2020.
- Hearing Objection View order
-
Hearing
Adjournment View order
Proceedings
ADJOURNED TO 11.05.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 08.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 24.08.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 21.09.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 12.10.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.11.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 14.12.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 11.01.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 25.01.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 15.02.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 05.04.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 17.05.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 28.06.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 16.08.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 18.10.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 22.11.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 29.11.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 17.01.2022.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 31.01.2022.
-
Hearing
Withdrawn/Rejected View order
Proceedings
Withdrawn/Rejected
Land, licence & cost
| Land area of the project | 3.833 acres |
|---|---|
| Total licensed area | 3.833 acres |
| Licence | 112 OF 2011 |
| FAR permissible / proposed | 27146.26 / 175 |
| Estimated project cost | ₹ 83 Cr |
| Cost of land | ₹ 2.7 Cr |
| Cost of construction | ₹ 64.09 Cr |
| Infrastructure and other structures | ₹ 7.86 Cr |
| EDC, taxes, levies and other costs | ₹ 8.35 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 5,429 | 17.8% |
| Construction Of Roads | 3,250 | 10.7% |
| Parks And Playgrounds | 6,812 | 22.4% |
| Vehicle Parkings | 14,481 | 47.6% |
| Electricity Sub-Station | 120 | 0.4% |
| Sewage And Solid Waste Treatment Facility | 330 | 1.1% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | No |
| Water Supply | HUDA | No |
| Electricity | HUAD | No |
| Sewage Disposal | HUDA | No |
| Storm Water Drainage | HUDA | No |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Licence 112 Of 2011 | Already Been Obtained | 17 Dec 2011 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vitrified Tiles In Drawing Room& Bedrooms |
|---|---|
| Wall Finishing Details | Plaster With Paint |
| Kitchen Details | Ceramic Tiles On Wall |
| Bathroom Fittings | All Cp Fittings |
| Wood Work Etc | Imported Wood & Flush Door |
| Doors And Windos Frames | As Per Sanction Plan |
| Glass Work | As Per Sanction Plan |
| Electric Fittings | As Per Sanction Plan |
| Conducting And Wiring Details | Provided |
| Water Storage | As Per Service Estimate |
| Lift Details | Provided |
| Main Doors | Double Pattan (3.5 *5) |
| Internal Doors | Single Pattan (2.5*3.5) |
| Electrical Fittings | Provided |
| Provision Of Wifi And Broadband Facility | Provision Taken |
| External Finishing/Colour Scheme | Plaster With Paint |
| Internal Finishing | Plaster With Paint |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Ras RESIDENCY2?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.