Ramprastha City - Sector 37C & 37D
by Ramprastha Estates Private Limited · Sector 37 C & D
- RERA registration
- Applied, not granted yet
- Applied on
- 2 Jan 2023
- Application status
- Rejected
- Project ID
- RERA-GRG-1254-2022
- Land area
- 105.402 acres
- Estimated cost
- ₹ 723.09 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-1254-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | Ongoing |
| Project name | Ramprastha City - Sector 37C & 37D |
| Promoter | Ramprastha Estates Private Limited |
| Promoter’s registered office | Plot No. 114, Sector- 44, Gurugram, Haryana |
| CIN | U70101HR2006PTC064788 |
| Site address | Sector 37 C & D |
| Sector | Sector 37 |
| Tehsil / District | Gurgaon / Gurugram |
| Application submitted | 2 Jan 2023 |
Authority, hearings & orders
- Application submitted online
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 30.01.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 13.02.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Sagar Gupta (AR) and Ms. Ruchi Mittal (AR) are present on behalf of the promoter. Today is 3rd hearing and deficiencies are yet to be removed. One last opportunity is given. The matter to come up on 13.03.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Sagar Gupta (AR), Ms. Ruchi Mittal (AR) and Sh. Nitin Kumar (AR) are present on behalf of the promoter. The AR of the promoter states that the requisite fee has already been deposited taking into account the zero period granted by Secretary TCP. The same shall be reconciled with the concerned staff within a period of ten days. The matter to come up on 27.03.2023.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 29.03.2023.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 29.03.2023 Ms. Prachi Singh, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Nikhil Jain, Sh. Sagar Gupta and Sh. Nitin Kumar are present on behalf of the promoter. Deficiencies have been conveyed to the applicant. The AR requests for a time of two weeks for submission of above deficit documents and deficit fee. The matter to come up on 10.04.2023.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 10.04.2023 Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Sagar Gupta and Sh. Nitin Kumar are present on behalf of the promoter. The AR of the promoter seeks time to comply with the observations and also to submit a detailed representation regarding the late fee imposed. The matter to come up on 01.05.2023.
-
Hearing
Objection View order
Proceedings
Due to administrative work, the matter is adjourned to 15.05.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Sagar Gupta (AR), Ms. Ruchi Mittal (AR) and Sh. Nitin Kumar (AR) are present on behalf of the promoter. The AR of the promoter requests for one month time for submission of the deficit documents. The matter to come up on 12.06.2023..
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Nitin Kumar (AR) is present on behalf of the promoter. The AR of the promoter requested for one month time to comply with the deficiencies and deficit fee should be dealt separately on file and penal proceedings be initiated for non-registration. The matter to come up on 21.08.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Nikhil Jain (Consultant) is present on behalf of the promoter who submits that the approval of revised plan has been obtained from DTCP and shall be filing its copy along with other deficit documents and seek 6 weeks time for their submission including deficit fee. Request is allowed as last opportunity. The applicant respondent is also required to submit consent of 2/3rd allottees for revision in the plans. The matter to come up on 09.10.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Nikhil Jain (Consultant) is present on behalf of the promoter but no authorization on behalf of the company is submitted. Further, a copy of the complaint received be also sent to the respondent for reply. The promoter to ensure submission of requisite deficit fee and remaining deficit documents within two weeks. Further, the promoter to ensure that only duly authorized representative is deputed for attending the meeting. The matter to come up on 20.11.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Shri Yash Sharma and Nikhil Jain (Consultant) present on behalf of the promoter and states that they are agreed to pay the requisite late fees along with the other deficiencies which is already conveyed through deficiency notice and seeks a short adjournment. The authority also directed the promoter to submit the reply in respect of the complaint submitted in the Authority as well as the copy of the same has been already given to the promoter. The matter to come upon 11.12.2023.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Mrs. Asha, Chartered Accountant briefed about the facts of the project. Sh. Yash Sharma (AR) and Sh. Nikhil Jain (AR) are present on behalf of the promoter. The AR requests for a time of four weeks for submission of above deficit documents and deficit fee. The matter to come up on 15.01.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. M. L. Sardana (Accountant) briefed about the facts of the project. None is present on behalf of the promoter. Despite grant of four weeks’ time as requested by the AR of the promoter on the last date of hearing, again a request vide email dated 15.01.2024 has been received today for grant of another four weeks for deposit of deficit fee and none has appeared on behalf of the promoter. The Authority observed that this is the 15th opportunity granted to the promoter to rectify the deficiencies. It is also noted that the promoter has already created 3rd party rights in the project sought to be registered and a large number of complaints have been received with respect to sale/alleged sale of plots in the project sought to be registered. Besides above there are a number of other deficiencies which have been conveyed to the promoter but not yet rectified and the same includes revision in the layout plan without prior consent of 2/3rd allottees in violation of section 14 of the Act of 2016. Therefore, the Authority decides to issue a show cause notice as to why the application for registration (made after a lapse of more than five years from the obligation under section 3 of the Act of 2016) be not rejected and further penal action under section 59 of the Act be not initiated. The matter to come up on 19.02.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Shri Yash Sharma and Nikhil Jain, ARs of the promoter are present. Despite 16 hearings, the promoter has been unable to rectify the deficiencies. The AR of the promoter company seeks one last opportunity to rectify the remaining deficiencies including the payment of late fees for the registration. The application for approval of demarcation/zoning plan is already submitted to DTCP and is under consideration of the field office for sending the report to DTCP. A show cause notice for rejection of the registration application is being issued separately. The matter to come up on 01.04.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Nikhil Jain (Advisor), Sh. Yash Sharma (AR) are present on behalf of the promoter. The AR states that the requisite deficit late fees have been deposited on 29.03.2024 and approval of revised demarcation/zoning plan is in advance stage with DTCP and seeks one more and last opportunity of two months within which the requisite documents shall be submitted. In view of the above, a final opportunity is granted to the promoter to submit the requisite documents including 2/3rd consent of the existing allottees and registered collaboration agreement. The promoter/director shall be present on the next date of hearing. The matter to come up on 10.06.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Yash Sharma (AR) and Sh. Nikhil Jain (AR) are present on behalf of the promoter. The AR states that a number of deficit documents have been submitted on 07.06.2024 which be examined by the office. Further, the AR seeks four weeks’ time for submission of approved zoning plan/demarcation plan which otherwise has been cleared by local field office and has been sent to DTCP office. The matter to come up on 22.07.2024.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned and to come up on 12.08.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Arvind Walia (AR) and Sh. Yash Sharma (AR) are present on behalf of the promoter. The AR of the promoter seeks six weeks’ time for submission of approved zoning plan/demarcation plan along with other observations and also to submit an undertaking stating that if the approved zoning/demarcation plan is not received within 6 weeks, the application is liable to be rejected. The matter to come up on 30.09.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Yash Sharma (AR) is present on behalf of the promoter and states that detailed reply to the deficiencies along with copy of approved zoning plan and demarcation plan has been submitted in the Authority on 27.09.2024. Further the requirement of obtaining 2/3rd consent is not applicable in view of the policy issued by ACS TCP Memo No… dated…. The addendum to the MOU incorporating the clause of irrevocability of the collaboration will be submitted in 10 days with the list of units earmarked. The matter to come up on 21.10.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Shri Yash Sharma and Nikhil Jain (Consultant) are present on behalf of the promoter. The addendum to the MOU incorporating the clause has been submitted by the promoter today. Further, the promoter stated that according to the policy issued by ACS TCP Memo No Misc-862/2023/7/1/2023-2TCP/11689-91 dated 24.04.2023 the consent is not required as per clause 3(iii) & 3(v) which is to be examined by the office vis-à-vis revision in the layout plan. A public notice in three newspapers (2 English and 1 Hindi) of vide circulation shall be issued with respect to revision in the layout plan for inviting objections, if any within a period of two weeks. All the issues need to be examined on file for decision of the authority. The matter to come up on 11.11.2024.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned and to come up on 02.12.2024.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Nikhil Jain (AR) and Sh. Laxmikant Saini (CA) are present on behalf of the promoter. The promoter has been asked to submit 2/3rd consent of the allottees in view of the changes in the earlier approved layout plan. The authorization on behalf of the landowner/collaboration company singing be submitted and copy of loan sanction letter and NOC. The copy of objections received shall also be supplied to the respondents and reply to the same be submitted within 2 weeks. Further, the promoter is directed to remove the pending deficiencies as already conveyed and also mentioned at serial no. 21 (Remarks). The matter to come up on 20.01.2025.
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned and to come up on 03.03.2025.
-
Hearing
Adjournment View order
Proceedings
Ms. Deepika, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. None is present on behalf of the promoter and a request seeking four weeks’ adjournment has been received for submission of the requisite 2/3rd consent of the existing allottees in respect of the changes in the earlier approved layout plan. The matter to come up on 21.04.2025.
-
Hearing
Rejected View order
Proceedings
Ms. Deepika, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Laxmi Kant (CA) is present on behalf of the promoter and requests for an adjournment of hearing. The Authority observes that the application under Section 4 for registration of the project titled “Ramprastha City – Sector 37C & 37D”, situated at Sector 37C & 37D, Gurugram, was submitted by the promoter on 02.01.2023 which is more than two years ago. The deficiencies in the application were duly conveyed to the promoter and despite 26 opportunities and lapse of more than two years and personal hearing before the Authority, the promoter has failed to submit the requisite documents/compliances. A show-cause notice for rejection of the application for registration of the real estate residential plotted colony project titled “Ramprastha City – Sector 37C & 37D” was issued to the promoter on 23.02.2024. The promoter was granted multiple opportunities of hearing thereafter. However, the deficiencies have still not been addressed by the promoter. The application has been pending before the Authority for more than two years, and the promoter has not complied with the pending deficiencies already conveyed. In view of the above, the application submitted by the promoter under Section 4 for project registration is hereby rejected, with liberty to submit a fresh application once all the requisite documents, including the applicable fee, are available. Additionally, the promoter is restrained from creating any further third-party rights in the project. The processing fee is forfeited, and the balance fee will be adjusted when the promoter submits a fresh application. The proceedings initiated against the promoter for violation of Section 3(1) of the Act, 2016 under suo moto case no. RERA-GRG-4794-2023 shall continue separately.
Land, licence & cost
| Land area of the project | 105.402 acres |
|---|---|
| Total licensed area | 105.402 acres |
| Licence | 128 of 2012(Expiry 27.12.2025) |
| Estimated project cost | ₹ 723.09 Cr |
| Cost of land | ₹ 93.17 Cr |
| Infrastructure and other structures | ₹ 122.2 Cr |
| EDC, taxes, levies and other costs | ₹ 507.72 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 50.91 | 48.3% |
| Construction Of Roads | 33.291 | 31.6% |
| Parks And Playgrounds | 8.652 | 8.2% |
| Electricity Sub-Station | 0.127 | 0.1% |
| Sewage And Solid Waste Treatment Facility | 0.303 | 0.3% |
| Any Other | 2.2444 | 2.1% |
| Commercial | 2.025 | 1.9% |
| Community | 7.8496 | 7.4% |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | No |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 25.34 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 13.79 Cr | Yet To Be Prepared |
| Storm Water Drainage | ₹ 10.2 Cr | Yet To Be Prepared |
| Electricity Supply System | ₹ 22 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 14.44 Cr | Yet To Be Prepared |
| Street Lighting | ₹ 1.48 Cr | Yet To Be Prepared |
| Club House/Community Centre | ₹ 21.69 Cr | Yet To Be Prepared |
| Any Other | ₹ 13.26 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Forest Noc | Already Been Obtained | 15 Dec 2022 |
| Water Supply Assurance | Already Been Obtained | 29 Nov 2022 |
| Sewage Disposal Assurance | Already Been Obtained | 24 Nov 2022 |
| Storm Water Drainage Assurance | Already Been Obtained | 29 Nov 2022 |
| License | Already Been Obtained | 19 Oct 2022 |
| Service Plan Estimates Approval | Yet To File For Approval |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable |
|---|---|
| Wall Finishing Details | Not Applicable |
| Kitchen Details | Not Applicable |
| Bathroom Fittings | Not Applicable |
| Wood Work Etc | Not Applicable |
| Doors And Windos Frames | Not Applicable |
| Glass Work | Not Applicable |
| Electric Fittings | Not Applicable |
| Conducting And Wiring Details | Not Applicable |
| Cupboard Details | Not Applicable |
| Water Storage | Not Applicable |
| Lift Details | Not Applicable |
| External Glazings | Not Applicable |
| Windows/Glazings | Not Applicable |
| Doors | Not Applicable |
| Main Doors | Not Applicable |
| Internal Doors | Not Applicable |
| Air Conditioning | Not Applicable |
| Electrical Fittings | Not Applicable |
| Cng Pipe Line | Not Applicable |
| Provision Of Wifi And Broadband Facility | Not Applicable |
| External Finishing/Colour Scheme | Not Applicable |
| Internal Finishing | Not Applicable |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Ramprastha City - Sector 37C & 37D?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.