RERA registration
Registration certificateHRERA-PKL-PNP-789-2025
Registration valid till31 Mar 2030
Project IDRERA-PKL-1601-2024
AuthorityHRERA Panchkula
Project type (as filed)New
Project nameRalith Retreat
PromoterRalith Realty Pvt. Ltd.
Promoter’s registered officeB-903 Npsc Society Plot No 5 Sector 2 Dwarka South West Delhi 110075
CINU45309DL2022PTC400328
Site addressVillage Azizulapur, Sector-19A, Panipat, Haryana
SectorSector 19A
Tehsil / DistrictPanipat / Panipat
Layout plan approved28 Nov 2024
Construction start (as filed)1 Dec 2025
Completion (as filed)31 Mar 2030
Application submitted3 Oct 2025
Authority, hearings & orders
Current status Approved And Certificate Uploaded
Initial scrutiny Listed for hearing on 29.10.2025.
Next hearing Not Required
3 Oct 2025
Application submitted online
8 Oct 2025
Application received by HRERA Panchkula
29 Oct 2025
Hearing
Approved And Ready For Certificate Issuing Process View order Proceedings APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
31 Mar 2030
Registration valid till
Land, licence & cost
Land area of the project21.369 acres
Total licensed area21.369 acres
Licence166 0f 2024 Dated 28.11.2024 Valid upto 27.11.2029
Estimated project cost₹ 137.64 Cr
Cost of land₹ 71.2 Cr
Infrastructure and other structures₹ 21.42 Cr
EDC, taxes, levies and other costs₹ 45.02 Cr
How the land will be used
Use Acres Share
Plots To Be Sold9.9563 46.6% Construction Of Roads3.8274 17.9% Pavements3.5884 16.8% Parks And Playgrounds2.0713 9.7% Sewage And Solid Waste Treatment Facility0.4568 2.1% Any Other0.0838 0.4% Commercial0.84 3.9% Underground0.0583 0.3% Community0.2017 0.9% Ud0.2849 1.3%
Plots 143 plots
Plot size (sq m) Sq yd Sq ft Plots
571.56684 6,152 2 761.25910 8,194 5 1,471.601,760 15,840 5 4,672.005,588 50,289 16 5,972.407,143 64,286 28 7,155.758,558 77,024 47 17,586.8021,034 189,303 40
External services
Service Provided by Approval taken
RoadsHSVP-PWD Yes Water SupplyHSVP Yes ElectricityUHBVN Yes Sewage DisposalHSVP Yes Storm Water DrainageHSVP Yes
Facilities in the service plan
Facility Estimated cost Status
Internal Roads And Pavements₹ 5.75 Cr As Per Project Report Water Supply System₹ 2.44 Cr As Per Project Report Storm Water Drainage₹ 2.07 Cr As Per Project Report Electricity Supply System₹ 3.38 Cr As Per Project Report Sewage Treatment & Garbage Disposal₹ 1.79 Cr As Per Project Report Street Lighting₹ 78.78 lakh As Per Project Report Security And Fire Fighting₹ 24.67 lakh As Per Project Report Playgrounds And Parks₹ 20.27 lakh As Per Project Report Renewable Energy System₹ 14.76 lakh As Per Project Report Any Other₹ 2.04 Cr As Per Project Report Stp₹ 64.56 lakh As Per Project Report Ugt₹ 28.82 lakh As Per Project Report Rwhp₹ 24.81 lakh As Per Project Report Electric Sub Station₹ 1.37 Cr As Per Project Report
Statutory approvals
Approval Status Date
LoiAlready Been Obtained 12 Aug 2024
LicenseAlready Been Obtained 28 Nov 2024
Site PlanAlready Been Obtained 28 Nov 2024
Water AssuranceAlready Been Obtained 2 Jan 2025
Sewer AssuranceAlready Been Obtained 2 Jan 2025
Storm Water AssuranceAlready Been Obtained 2 Jan 2025
Access PermissionAlready Been Obtained 16 Aug 2024
Forest NocAlready Been Obtained 6 May 2025
Electrical AssuranceAlready Been Obtained 23 Jan 2025
Specifications (as filed)
Flooring Details Of Various Parts Of HouseNot Applicable Being A Plotted Colony Wall Finishing DetailsNot Applicable Being A Plotted Colony Kitchen DetailsNot Applicable Being A Plotted Colony Bathroom FittingsNot Applicable Being A Plotted Colony Wood Work EtcNot Applicable Being A Plotted Colony Doors And Windos FramesNot Applicable Being A Plotted Colony Glass WorkNot Applicable Being A Plotted Colony Electric FittingsNot Applicable Being A Plotted Colony Conducting And Wiring DetailsNot Applicable Being A Plotted Colony Cupboard DetailsNot Applicable Being A Plotted Colony Water StorageNot Applicable Being A Plotted Colony Lift DetailsNot Applicable Being A Plotted Colony External GlazingsNot Applicable Being A Plotted Colony Windows/GlazingsNot Applicable Being A Plotted Colony DoorsNot Applicable Being A Plotted Colony Main DoorsNot Applicable Being A Plotted Colony Internal DoorsNot Applicable Being A Plotted Colony Air ConditioningNot Applicable Being A Plotted Colony Electrical FittingsNot Applicable Being A Plotted Colony Cng Pipe LineNot Applicable Being A Plotted Colony Provision Of Wifi And Broadband FacilityNot Applicable Being A Plotted Colony External Finishing/Colour SchemeNot Applicable Being A Plotted Colony Internal FinishingNot Applicable Being A Plotted Colony
Source: HRERA Panchkula, Form REP-I , read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.