HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Anish Dham (AR), Sh. Nitin Gupta (AR) and Sh. Kabir Kapoor (AR) are present on behalf of the promoter. The Landowners Sh. Ishwar Singh, Sh. Shribhagwan, Sh. Rajkumar and Authorized representative of M/s Gurgaon One Reality Pvt. Ltd. are present. The landowners’ present in person states that they are well versed with the allocation of the plots of their share as submitted by the promoter in the Authority. The Authorized Representative of the promoter submits that an application dated 25.05.2026 has been submitted in the Authority seeking registration of the project namely “Privana Enclave”. The license no 219 of 2023 dated 25.10.2023 valid upto 24.10.2028 was issued by DTCP in favour of M/s DLF Limited and others in collaboration with M/s DLF Limited for the development of residential colony under NILP over an area admeasuring 116.2962 acres. Further, the phasing plan has been approved and the project is to be developed in 10 phases. Now, the promoter has applied for registration of Phase VII under Section 4 of the Act, 2016 for a residential plotted colony having an area admeasuring 4.662 acres. The AR further submits that presently, Approved service plans and estimates, Road access permission and Re-alignment of Powerline have not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit: i. Approved Service Plans and Estimates within 6 months from the date of grant of registration Certificate. ii. Road access permission within 6 months from the date of grant of registration Certificate. iii. Power line Shifting NOC after the re-alignment of powerline. Further, he undertakes to submit a Demand Draft/Bank Guarantee amounting to Rs. 25 lakhs as a security deposit for timely compliance with the above requirement at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approval within the stipulated time frames, the security amount shall be liable to be forfeited by the Authority. The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approvals as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit a Demand Draft/Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amount for timely submission of the following approvals: a. Approved Service Plans and Estimates: within 6 months from the date of grant of registration Certificate. In the event of non-submission of any of the above approval within the prescribed time frames, the security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. The Authority further observed that three plots no SR/05 to SR/07 to be kept on hold till HT Line is re-aligned as per the approved layout plan. A condition to the same shall be incorporated in the Registration Certificate. The AR of the promoter is further directed to submit the road access permission within 6 months from the date of grant of registration Certificate and Powerline Shifting NOC after the Re-alignment of powerline. Approved as proposed subject to rectification of deficiencies mentioned above at S. No 33. The registration Certificate shall be issued after submission of remaining deficiencies mentioned at S. No 33 including correction in A-H form, Online DPI and submission of a BG/DD of Rs. 25 lakhs for submission of Approved Service plan and Estimates within the timeframe mentioned above.
Registration grantedGGM/1079/811/2026/51
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
4.662 acres
Total licensed area
116.296 acres
Licence
DTCP 219 of 2023 25.10.2023 valid upto 24.10.2028
FAR permissible / proposed
2.62 / 0.017
Estimated project cost
₹ 56.63 Cr
Cost of land
₹ 27.44 Cr
Infrastructure and other structures
₹ 18.65 Cr
EDC, taxes, levies and other costs
₹ 10.54 Cr
How the land will be used
Use
Sq m
Share
Plots To Be Sold
10,932.8
57.9%
Construction Of Roads
6,031.615
32%
Parks And Playgrounds
1,902
10.1%
Plots 41 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
204.00
244
2,196
14
211.14
253
2,273
1
215.83
258
2,323
1
277.42
332
2,986
1
286.00
342
3,078
14
299.00
358
3,218
6
306.80
367
3,302
1
415.61
497
4,474
1
426.00
509
4,585
2
External services
Service
Provided by
Approval taken
Roads
GMDA
No
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.8 Cr
As Per Project Report
Water Supply System
₹ 93.24 lakh
As Per Project Report
Storm Water Drainage
₹ 1.12 Cr
As Per Project Report
Electricity Supply System
₹ 4.66 Cr
As Per Project Report
Street Lighting
₹ 1.49 Cr
As Per Project Report
Playgrounds And Parks
₹ 1.49 Cr
As Per Project Report
Any Other
₹ 2.61 Cr
As Per Project Report
Earth Works
₹ 1.31 Cr
As Per Project Report
Rwh
₹ 93.24 lakh
As Per Project Report
Sewer Line
₹ 1.31 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
25 Oct 2023
Water Assurance
Already Been Obtained
6 Oct 2023
Storm Assurance
Already Been Obtained
11 Oct 2023
Sewerage Assurance
Already Been Obtained
10 Oct 2023
Electric Assurance
Already Been Obtained
10 Jan 2024
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Privana Enclave?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.