by Ramakrishna Buildwell Pvt. Ltd. · Divine City, NH-1, 60TH Mile Stone, Sonepat Haryaha
RERA registration
Applied, not granted yet
Applied on
2 Dec 2020
Application status
In process
Project ID
RERA-PKL-885-2020
Land area
5 acres
Estimated cost
₹ 55.26 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
Registration certificate
Not issued yet: the application is being processed by HRERA Panchkula
Project ID
RERA-PKL-885-2020
Authority
HRERA Panchkula
Project type (as filed)
Ongoing
Project name
Presidia Heights
Promoter
Ramakrishna Buildwell Pvt. Ltd.
Promoter’s registered office
B-79, Second Floor, Wazirpur Indl. Area, Delhi - 110052
CIN
U45201DL2005PTC140802
Site address
Divine City, NH-1, 60TH Mile Stone, Sonepat Haryaha
Tehsil / District
Sonipat / Sonipat
Application submitted
2 Dec 2020
Authority, hearings & orders
Current statusStatus not given
Next hearingNot Required
Application submitted online
Land, licence & cost
Land area of the project
5 acres
Total licensed area
5 acres
Licence
60 OF 2007
FAR permissible / proposed
1.75 / 1.75
Estimated project cost
₹ 55.26 Cr
Cost of land
₹ 4.02 Cr
Cost of construction
₹ 40 Cr
Infrastructure and other structures
₹ 8 Cr
EDC, taxes, levies and other costs
₹ 3.24 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
1.26
25.2%
Construction Of Roads
1.51
30.2%
Pavements
0.71
14.2%
Parks And Playgrounds
0.5
10%
Green Belts
0.51
10.2%
Vehicle Parkings
0.21
4.2%
Electricity Sub-Station
0.05
1%
Club House
0.04
0.8%
Sewage And Solid Waste Treatment Facility
0.05
1%
Area To Be Left For Transferring To The Government For Community Services
0.16
3.2%
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
HUDA, Panchkula
Yes
ELECTRICITY
Uhbvn, Panchkula
Yes
SEWAGE DISPOSAL
No
STORM WATER DRAINAGE
HUDA, PANCHKULA
Yes
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
1124.54
Yet To Be Prepared
2
WATER SUPPLY SYSTEM
533.45
YET TO BE PREPARED
3
Storm Water Drainage
577.25
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
517.74
Yet To Be Prepared
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
347.44
YET TO BE PREPARED
6
Street Lighting
141.56
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
103.51
Yet To Be Prepared
8
PLAYGROUNDS AND PARKS
103.57
YET TO BE PREPARED
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
399.05
YET TO BE PREPARED
15
Boundary Wall
155.30
YET TO BE PREPARED
16
HARD LANDSCAPE
155.36
Yet To Be Prepared
17
PLANTATION
220.95
YET TO BE PREPARED
18
Play Equipment
44.17
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
NA
(date)
6. Date of approval of Building Plans
NA
(date)
(i) Details of the plots/apartments in the project:
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type
213300
216
46072800
81
135
4
Total
216
46072800
81
135
4
(ii) Apartments/Shops/Other Buildings:-
(a) Status of construction activities in respect of sold/booked apartments.
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
81
IN PROGRESS
(b) Time schedule of completion of already booked apartments:
Start Date
03-02-2007
Earlier date of completion
03-02-2019
Revised date of completion
01-12-2022
(c) Time schedule for development of infrastructure:
Start Date
03-02-2007
Percentage completion Upto the
date of application
45
Projected date of completion
01-12-2022
(d) Provide further details in the proforma REP-I Part-C-X.
(e) Plan of action for completing the Project along with requisite infrastructure.
(iii) Status in respect of plotted colony:-
(a)
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
(b) Schedule for development of Infrastructure:
Start Date
03-02-2007
Percentage completion
45
Projected date of completion
01-12-2022
(c) Provide further details in the proforma REP-I Part-C-X.
(d) Schedule of completing the project and handing over possession of the plots.
(iv) Vehicle parkings details of the project-
a) Underground parking
0
b) Stilt parking
108
c) Covered parking
877
d) Open parking
257
e) Independent garages
0
(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
2928.51
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
805.34
Water Supply System
292.85
Sewerage treatment & garbage disposal
183.03
Electricity Supply System
366.06
Storm Water Drainage
329.46
Parks and Playgrounds
73.21
Clubhouse/community centres
0
Shopping area
0
Other
292.85
Boundary Wall
109.82
Fire Fighting
73.21
Hard Landscape
109.82
Plantation
183.03
Play Equipments
36.61
Street Lighting
73.21
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - C-X
1.Financial information:
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
90
ii. No. of Flats/ Apartments booked
81
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
2743.55 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
2743.55 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
3633.79 Lakhs
Land cost (If any)
360 Lakhs
Apartments
1365 Lakhs
Infrastructure
1215 Lakhs
EDC/ Taxes Etc.
693.79 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
2000 Lakhs
(a) In respect of existing allottees
2000 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
2.Additional information:
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
1124.54
805.34
II. WATER SUPPLY SYSTEM
533.45
292.85
III. STORM WATER DRAINAGE
577.25
329.46
IV. ELECTRICITY SUPPLY SYSTEM
517.74
366.06
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
347.44
183.03
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
399.05
292.85
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
103.57
73.21
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
820.85
585.70
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
Yes
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
CENTRAL BANK OF INDIA, GT ROAD, PANIPAT, HARYANA
Bank Account number
3634982315
IFSC code
CBIN0280382
MICR code
132016002
Branch code
00382
4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
YES
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - E
Details of the statutory approvals:
1. Annex copies of the following in Folder E:
i. Lay out Plan
Yes
ii. Demarcation Plan
Yes
iii. Zoning Plan
Yes
iv. Building Plan
No
Site Plan
Yes
Floor Plan
Yes
Apartment Plans
Yes
Elevation Section
Yes
Detail of Permissible FAR
Yes
Detail of covered area achieved FAR
Yes
2. Annex copies of the following in Folder E:
I. Roads And Pavement Plan
No
II. ELECTRICITY SUPPLY PLAN
No
III. WATER SUPPLY PLAN
No
IV. Sewerage And Garbage Disposal Plan
No
V. STROM WATER DRAINAGE
No
VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
No
Vii. Street Lighting Plan
No
VIII. PARKING PLAN
No
3. Statutory Approvals Status
Statutory Approvals
Statutory Approvals Status
Date
I. DIRECTORATE OF TOWN & COUNTRY PLANNING
Applied For But Yet To Receive
03-02-2007
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.
Signature _____________
Seal _____________
Date _____________
Form Rep-I
Part - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.
Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)
(Annex a copy in Folder F)
Yes
3. Gist of the important provisions of the Draft Agreement
(Annex a copy in Folder F)
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - G
Projects launched by the promoter in last five years: (No Projects)
I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - H
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
Floor Tile
2
WALL FINISHING DETAILS
Putti With Paint
3
KITCHEN DETAILS
Semi Finished
4
BATHROOM FITTINGS
Semi Finished With Fitting
5
WOOD WORK ETC
Semi Finished
6
DOORS AND WINDOS FRAMES
Yes
7
GLASS WORK
As Per Requirement Of Customer
8
ELECTRIC FITTINGS
Yes
9
CONDUCTING AND WIRING DETAILS
Yes
10
CUPBOARD DETAILS
Yes
11
WATER STORAGE
Yes
12
LIFT DETAILS
Yes
13
EXTERNAL GLAZINGS
No
13.1
WINDOWS/GLAZINGS
No
14
DOORS
Yes
14.1
MAIN DOORS
Yes
14.2
INTERNAL DOORS
Yes
15
AIR CONDITIONING
No
16
ELECTRICAL FITTINGS
Yes
17
CNG PIPE LINE
No
18
PROVISION OF WIFI AND BROADBAND FACILITY
No
19
EXTERNAL FINISHING/COLOUR SCHEME
Yes
20
INTERNAL FINISHING
Yes
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
YES
1 . 2
WALLS
YES
1 . 3
CEILING
YES
2 . Master Bedroom/Dressroom
2 . 1
FLOOR
Yes
2 . 2
WALLS
Yes
2 . 3
CEILING
Yes
2 . 4
MODULAR WARDROBES
Yes
3 . MASTER TOILET
3 . 1
Floor
YES
3 . 2
Walls
YES
3 . 3
Ceiling
YES
3 . 4
Counters
YES
3 . 5
Sanitary Ware/Cp Fittings
YES
3 . 6
Fitting/Fixtures
YES
4 . BED ROOMS
4 . 1
FLOOR
YES
4 . 2
WALLS
YES
4 . 3
CEILING
YES
4 . 4
WARDROBES
YES
5 . Toilet
5 . 1
FLOOR
Yes
5 . 2
WALLS
Yes
5 . 3
CEILING
No
5 . 4
COUNTERS
No
5 . 5
SANITARY WARE/CP FITTINGS
Yes
5 . 6
FIXTURES
Yes
6 . KITCHEN
6 . 1
Floor
YES
6 . 2
Walls
YES
6 . 3
Ceiling
YES
6 . 4
Counters
NO
6 . 5
Fixtures
YES
6 . 6
Kitchen Appliances
NO
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NO
7 . 2
WALLS & CEILING
NO
7 . 3
TOILET
NO
7 . 4
BALCONY
NO
8 . Sit-Outs
8 . 1
FLOOR
No
8 . 2
WALLS & CEILING
No
8 . 3
RAILINGS
No
8 . 4
FIXTURES
No
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
List of Uploaded Documents
Sr. No.
Document Description
Date of Document Upload
View Document
1
Service Plans Showing The Services On The Layout Plan
02-12-2020
View Document
2
IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN
02-12-2020
View Document
3
IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN
02-12-2020
View Document
4
Certificate From A Chartered Accountant Certifying That The Informstion Provided By The Applicant In Form Rep-1-C-X Is Correct As Per The Books Of Accounts/ Balance Sheet Of The Applicant
02-12-2020
View Document
5
DEMARCATION PLAN
02-12-2020
View Document
6
COPY OF LICENSE ALONG WITH SCHEDULE OF LAND
02-12-2020
View Document
7
Declaration Supported By Affidavit Duly Signed By The Promoter To Be Enclosed.
02-12-2020
View Document
8
ZONING PLAN
02-12-2020
View Document
9
NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT
02-12-2020
View Document
10
Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record
02-12-2020
View Document
11
CASH FLOW STATEMENT OF THE PROPOSED PROJECT
02-12-2020
View Document
12
A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS
02-12-2020
View Document
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 11.25 Cr
Yet To Be Prepared
Water Supply System
₹ 5.33 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 5.77 Cr
Yet To Be Prepared
Electricity Supply System
₹ 5.18 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 3.47 Cr
Yet To Be Prepared
Street Lighting
₹ 1.42 Cr
Yet To Be Prepared
Security And Fire Fighting
₹ 1.04 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 1.04 Cr
Yet To Be Prepared
Any Other
₹ 3.99 Cr
Yet To Be Prepared
Boundary Wall
₹ 1.55 Cr
Yet To Be Prepared
Hard Landscape
₹ 1.55 Cr
Yet To Be Prepared
Plantation
₹ 2.21 Cr
Yet To Be Prepared
Play Equipment
₹ 44.17 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
Directorate Of Town & Country Planning
Applied For But Yet To Receive
3 Feb 2007
Specifications (as filed)
Flooring Details Of Various Parts Of House
Floor Tile
Wall Finishing Details
Putti With Paint
Kitchen Details
Semi Finished
Bathroom Fittings
Semi Finished With Fitting
Wood Work Etc
Semi Finished
Doors And Windos Frames
Yes
Glass Work
As Per Requirement Of Customer
Electric Fittings
Yes
Conducting And Wiring Details
Yes
Cupboard Details
Yes
Water Storage
Yes
Lift Details
Yes
External Glazings
No
Windows/Glazings
No
Doors
Yes
Main Doors
Yes
Internal Doors
Yes
Air Conditioning
No
Electrical Fittings
Yes
Cng Pipe Line
No
Provision Of Wifi And Broadband Facility
No
External Finishing/Colour Scheme
Yes
Internal Finishing
Yes
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Presidia Heights?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.