W4D, 204/5, Keshav Kunj, Cariappa Marg, Sainik Farms, New Delhi
CIN
U45400DL1990PLC042200
Site address
Sector 11 & 14
Sector
Sector 11
Tehsil / District
Nuh / Nuh
Layout plan approved
29 Aug 2017
Application submitted
5 Feb 2020
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Next hearingNot Required
Registration granted93 OF 2017
Application submitted online
Application received by HRERA Gurugram
Registration valid till
Land, licence & cost
Land area of the project
52.371 acres
Total licensed area
57.68 acres
Licence
19 of 2014
FAR permissible / proposed
0 / 0
Estimated project cost
₹ 273.46 Cr
Cost of land
₹ 153.64 Cr
Cost of construction
₹ 1.72 Cr
Infrastructure and other structures
₹ 10.63 Cr
EDC, taxes, levies and other costs
₹ 107.47 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
20.62
40.9%
Construction Of Roads
16.88
33.5%
Parks And Playgrounds
2.56
5.1%
Electricity Sub-Station
0.06
0.1%
Sewage And Solid Waste Treatment Facility
0.25
0.5%
Community
2
4%
Dispensary
1.25
2.5%
Cretche
0.2
0.4%
Religious
0.2
0.4%
Nursery
0.3
0.6%
High
5
9.9%
Commercial
1.07
2.1%
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
No
ELECTRICITY
No
Sewage Disposal
No
STORM WATER DRAINAGE
No
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
1299.61
Submitted To Town & Country Planning
2
WATER SUPPLY SYSTEM
313.96
SUBMITTED TO TOWN & COUNTRY PLANNING
3
Storm Water Drainage
370.52
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
0
Yet To Be Prepared
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
51.94
SUBMITTED TO TOWN & COUNTRY PLANNING
6
Street Lighting
221.30
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
0
Yet To Be Prepared
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
29-08-2017
(date)
6. Date of approval of Building Plans
Na
(date)
(i) Details of the plots/apartments in the project:
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type PLOT - C (TYPE II)
0
6
0
5
0
0
2
PLOT Type PLOT - D
0
36
0
34
2
0
3
PLOT Type PLOT - E
0
92
0
82
10
0
4
PLOT Type PLOT - F
0
54
0
54
0
0
5
PLOT Type PLOT - G
0
125
0
0
125
0
6
PLOT Type COMMERCIAL
4330.29
1
4330.29
1
0
0
7
PLOT Type COMMUNITY CENTRE
8094
1
8094
1
0
0
8
PLOT Type DISPENSARY
5058.75
1
5058.75
1
0
0
9
PLOT Type CRETCHE
809.40
1
809.4
1
0
0
10
PLOT Type RELIGIOUS BUILDING
809.40
1
809.4
1
0
0
11
PLOT Type NURSERY SCHOOL
1214.10
1
1214.1
1
0
0
12
PLOT Type HIGH SCHOOL
20235
1
20235
1
0
0
13
PLOT Type MILK BOOTH
12
1
12
1
0
0
Total
321
40562.94
183
137
0
(ii) Apartments/Shops/Other Buildings:-
(a) Status of construction activities in respect of sold/booked apartments.
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
(b) Time schedule of completion of already booked apartments:
Start Date
N/A
Earlier date of completion
N/A
Revised date of completion
N/A
(c) Time schedule for development of infrastructure:
Start Date
07-11-2015
Percentage completion Upto the
date of application
40
Projected date of completion
27-08-2022
(d) Provide further details in the proforma REP-I Part-C-X.
(e) Plan of action for completing the Project along with requisite infrastructure.
(iii) Status in respect of plotted colony:-
(a)
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
Plot
183
0
(b) Schedule for development of Infrastructure:
Start Date
07-11-2015
Percentage completion
40
Projected date of completion
27-08-2022
(c) Provide further details in the proforma REP-I Part-C-X.
(d) Schedule of completing the project and handing over possession of the plots.
(iv) Vehicle parkings details of the project-
a) Underground parking
0
b) Stilt parking
0
c) Covered parking
0
d) Open parking
0
e) Independent garages
0
(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
23576
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - C-X
1.Financial information:
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
321
ii. No. of Flats/ Apartments booked
183
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
32640.16 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
29103.20 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
3536.86 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
2214.36 Lakhs
vii. Amount invested in the project upto the date of application
23576 Lakhs
Land cost (If any)
15363 Lakhs
Apartments
786 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
7425 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
3770 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
10300 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
8800 Lakhs
2.Additional information:
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
0
0
II. WATER SUPPLY SYSTEM
0
0
III. STORM WATER DRAINAGE
0
0
IV. ELECTRICITY SUPPLY SYSTEM
0
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
0
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
Yes
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
AXIS BANK LTD, CROSS POINT, PHASE-IV, GURUGAON
Bank Account number
914020004162298
IFSC code
UTIB0000131
MICR code
110211019
Branch code
000131
4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
Navin M. Raheja
5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - E
Details of the statutory approvals:
1. Annex copies of the following in Folder E:
i. Lay out Plan
Yes
ii. Demarcation Plan
Yes
iii. Zoning Plan
Yes
iv. Building Plan
No
Site Plan
Yes
Floor Plan
No
Apartment Plans
No
Elevation Section
No
Detail of Permissible FAR
No
Detail of covered area achieved FAR
No
2. Annex copies of the following in Folder E:
I. ROADS AND PAVEMENT PLAN
Yes
II. Electricity Supply Plan
No
III. WATER SUPPLY PLAN
Yes
IV. SEWERAGE AND GARBAGE DISPOSAL PLAN
Yes
V. Strom Water Drainage
Yes
VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
No
VII. STREET LIGHTING PLAN
No
Viii. Parking Plan
No
3. Statutory Approvals Status
Statutory Approvals
Statutory Approvals Status
Date
I. Environment Clearance
ALREADY BEEN OBTAINED
15-10-2013
II. License No. 19 Of 2014
ALREADY BEEN OBTAINED
11-06-2014
III. Water Connection Permission
ALREADY BEEN OBTAINED
09-12-2016
IV. Sewerage Connection Permission
ALREADY BEEN OBTAINED
09-12-2016
V. Applicability Of Forest Laws
ALREADY BEEN OBTAINED
17-07-2014
Vi. DHBVN Power Assurance
ALREADY BEEN OBTAINED
10-03-2016
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.
Signature _____________
Seal _____________
Date _____________
FORM REP-I
Part - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.
(Annex a copy in Folder F)
Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)
(Annex a copy in Folder F)
Yes
3. Gist of the important provisions of the Draft Agreement
(Annex a copy in Folder F)
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - G
Projects launched by the promoter in last five years:
3. The number of plots/ apartments booked/sold to the allottees:
(a) Apartments
92
(b) Plots
0
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 13 Cr
Submitted To Town & Country Planning
Water Supply System
₹ 3.14 Cr
Submitted To Town & Country Planning
Storm Water Drainage
₹ 3.71 Cr
Submitted To Town & Country Planning
Sewage Treatment & Garbage Disposal
₹ 51.94 lakh
Submitted To Town & Country Planning
Street Lighting
₹ 2.21 Cr
Submitted To Town & Country Planning
Statutory approvals
Approval
Status
Date
Environment Clearance
Already Been Obtained
15 Oct 2013
License No. 19 Of 2014
Already Been Obtained
11 Jun 2014
Water Connection Permission
Already Been Obtained
9 Dec 2016
Sewerage Connection Permission
Already Been Obtained
9 Dec 2016
Applicability Of Forest Laws
Already Been Obtained
17 Jul 2014
DHBVN Power Assurance
Already Been Obtained
10 Mar 2016
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Plotted Colony (Raheja Aranya Phase - II)?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.