Palm Meadows
by Gurugram Land And Finance Private Limited · Sector-78, Village-Naurangpur, Tehsil-Manesar, District-Gurugram, Haryana
- RERA registration
- GGM/742/474/2023/86
- Registered on
- 21 Aug 2023
- Valid till
- 13 Mar 2028
- Project ID
- RERA-GRG-1367-2023
- Land area
- 5.019 acres
- Plots
- 95
- Completion (as filed)
- 2 Jul 2028
- Estimated cost
- ₹ 28.13 Cr
RERA registration
| Registration certificate | GGM/742/474/2023/86, dated 21 Aug 2023 |
|---|---|
| Registration valid till | 13 Mar 2028 |
| Project ID | RERA-GRG-1367-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Palm Meadows |
| Promoter | Gurugram Land And Finance Private Limited |
| Promoter’s registered office | Unit No. 811 And 812, Emaar The Palm Square, Sector-66, Golf Course Extension Road, Gurugram, Haryana 122001 |
| CIN | U70109HR2022PTC103264 |
| Site address | Sector-78, Village-Naurangpur, Tehsil-Manesar, District-Gurugram, Haryana |
| Sector | Sector 78 |
| Tehsil / District | Manesar / Gurugram |
| Layout plan approved | 15 Mar 2023 |
| Construction start (as filed) | 3 Jul 2023 |
| Completion (as filed) | 2 Jul 2028 |
| Application submitted | 27 May 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter Dispatched Online
-
Hearing
Examination By Authority View order
Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Ankit Singh (AR) is present on the behalf of the promoter. The AR of the promoter requests three weeks’ time to submit the deficiencies in the Authority. The matter to come up on 24.07.2023
-
Hearing
Adjournment View order
Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Pawan Kumar (AR) is present on the behalf of the promoter. The AR of the promoter is directed to rectify the remaining deficiencies which have already been conveyed before the next date of hearing. The matter to come up on 07.08.2023.
-
Hearing
Adjournment View order
Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Pawan Kumar is present on the behalf of the promoter. The AR submits that requisite clarification with respect to allocation of plots of the land owner along with other clarification has been submitted on 04.08.2023 which require to be scrutinised by the office. The matter to come up on 21.08.2023.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Pawan Kumar (AR) is present on behalf of the promoter. Approved as proposed and RC shall be issued after rectification of details in the project report and other minor deficiencies. The AR has submitted the list of plots which are in share of land owner as well as collaborator and duly signed by both the parties which shall also be annexed with the RC for general information.
- Registration granted GGM/742/474/2023/86
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 5.019 acres |
|---|---|
| Total licensed area | 5.019 acres |
| Licence | 52 of 2023 dated 15-03-2023 Granted by TCP, Haryana |
| FAR permissible / proposed | 1 / 1 |
| Estimated project cost | ₹ 28.13 Cr |
| Cost of land | ₹ 10.28 Cr |
| Infrastructure and other structures | ₹ 7.9 Cr |
| EDC, taxes, levies and other costs | ₹ 9.95 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 2.863 | 57% |
| Construction Of Roads | 1.0767 | 21.5% |
| Parks And Playgrounds | 0.3765 | 7.5% |
| Area To Be Left For Transferring To The Government For Community Services | 0.5019 | 10% |
| Commercial | 0.2007 | 4% |
Plots 95 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 97.03 | 116 | 1,044 | 2 |
| 109.39 | 131 | 1,177 | 6 |
| 110.02 | 132 | 1,184 | 9 |
| 115.52 | 138 | 1,243 | 1 |
| 116.53 | 139 | 1,254 | 5 |
| 124.44 | 149 | 1,339 | 60 |
| 125.59 | 150 | 1,352 | 6 |
| 133.11 | 159 | 1,433 | 3 |
| 142.75 | 171 | 1,537 | 3 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA - ALREADY CONNECTED FROM 60 M WIDE ROAD | No |
| Water Supply | GMDA | No |
| Electricity | DHBVN | No |
| Sewage Disposal | GMDA | No |
| Storm Water Drainage | GMDA | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.04 Cr | As Per Project Report |
| Water Supply System | ₹ 1.42 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 54.97 lakh | As Per Project Report |
| Electricity Supply System | ₹ 55 lakh | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 91.67 lakh | As Per Project Report |
| Street Lighting | ₹ 19.26 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 2.5 lakh | As Per Project Report |
| Boundary Wall Gate And Guard Room | ₹ 50 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 14 Mar 2023 |
| Layout Plan | Already Been Obtained | 15 Mar 2023 |
| Zoning Plan | Already Been Obtained | 12 May 2023 |
| Forest Noc | Already Been Obtained | 6 Jan 2023 |
| Service Plan And Estimate Approval | Already Been Obtained | 28 Jul 2023 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Palm Meadows?