Village Gangar And Shamgarh, Sector-16, Nilokheri-Tarori, Karnal, Haryana
Sector
Sector 16
Tehsil / District
Nilokheri / Karnal
Layout plan approved
20 Jun 2024
Construction start (as filed)
1 Aug 2024
Completion (as filed)
18 Jun 2029
Application submitted
13 Aug 2024
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed For First Hearing On 11.09.2024.
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS.
Registration valid till
Land, licence & cost
Land area of the project
20.6 acres
Total licensed area
20.6 acres
Licence
68 of 2024
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 82.16 Cr
Cost of land
₹ 57.49 Cr
Infrastructure and other structures
₹ 22.06 Cr
EDC, taxes, levies and other costs
₹ 2.62 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
12.55
60.9%
Construction Of Roads
3.605
17.5%
Parks And Playgrounds
1.553
7.5%
Area To Be Left For Transferring To The Government For Community Services
2.071
10.1%
Any Other
0.821
4%
Plots 369 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
104.72
125
1,127
28
105.77
127
1,139
2
109.89
131
1,183
14
111.01
133
1,195
1
116.83
140
1,258
5
118.10
141
1,271
8
123.21
147
1,326
4
123.24
147
1,327
16
123.95
148
1,334
4
131.25
157
1,413
14
132.94
159
1,431
36
134.40
161
1,447
2
135.00
161
1,453
28
142.92
171
1,538
2
143.45
172
1,544
4
147.00
176
1,582
26
147.14
176
1,584
30
149.18
178
1,606
2
149.45
179
1,609
11
149.81
179
1,613
18
149.83
179
1,613
1
150.00
179
1,615
113
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
UHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.59 Cr
Yet To Be Prepared
Water Supply System
₹ 1.66 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 1.86 Cr
Yet To Be Prepared
Electricity Supply System
₹ 3.49 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 2.27 Cr
Yet To Be Prepared
Street Lighting
₹ 71.23 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 1.4 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 1.56 Cr
Yet To Be Prepared
Club House/Community Centre
₹ 2.51 Cr
Yet To Be Prepared
Shopping Area
₹ 4 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License No 68 Of 2024
Already Been Obtained
19 Jun 2024
Demarcation Cum Zoning
Already Been Obtained
12 Aug 2024
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Ops Divine Greens?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.