Notice sent to the promoterBy Hand And Through Mail
HearingExamination By AuthorityView order Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. No reply has been submitted by the promoter company till 06.09.2023 against the deficiencies conveyed by the authority through notice dated 06.09.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Yogender Hooda, Partner of the company is present on behalf of the promoter. Approved subject to submission of signed copy of zoning plan and an undertaking to abide by condition of HSIIDC pertaining to allotment of the site and the same will also be incorporated in the Registration Certificate. The promoter shall submit the BG/DD amounting to Rs 25 lakhs as a security amount to submit the Fire Scheme approval within 3 months The registration certificate shall be issued after the submission of above.
Registration grantedGGM/749/481/2023/93
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Licence
Promoter was allotted the Group housing site Area Admeasuring 4000 Sqmts at Gh-36, Sector-1, Industrial Model Township, Mansar, District Gurugram, Ref no. HSIIDC C and H 2022 5813 DATED 05/09/2022 for Development of Residential Group housing from Haryana State Industrial and Infrastructure Development Corporation Ltd
FAR permissible / proposed
175 / 174.96
Estimated project cost
₹ 59.84 Cr
Cost of land
₹ 17.37 Cr
Cost of construction
₹ 23.82 Cr
Infrastructure and other structures
₹ 5.9 Cr
EDC, taxes, levies and other costs
₹ 12.75 Cr
How the land will be used
Use
Area (as filed)
Share
Land Area To Be Used For Construction Of Apartments
624.821
15.6%
Construction Of Roads
1,521.465
38%
Green Belts
600
15%
Vehicle Parkings
1,233.829
30.8%
Convenient
19.885
0.5%
Apartments 60 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
94.00
1,012
36
Apartment/Shops/Other Buildings
95.00
1,023
24
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
HSIIDC
Yes
Water Supply
HSIIDC
Yes
Electricity
DHBAN
Yes
Sewage Disposal
HSIIDC
Yes
Storm Water Drainage
HSIIDC
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 35 lakh
As Per Project Report
Water Supply System
₹ 45 lakh
As Per Project Report
Storm Water Drainage
₹ 35 lakh
As Per Project Report
Electricity Supply System
₹ 1.25 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 43 lakh
As Per Project Report
Street Lighting
₹ 19 lakh
As Per Project Report
Security And Fire Fighting
₹ 47 lakh
As Per Project Report
Playgrounds And Parks
₹ 11 lakh
As Per Project Report
Renewable Energy System
₹ 29 lakh
As Per Project Report
Parking
₹ 29 lakh
As Per Project Report
Stp
₹ 41 lakh
As Per Project Report
Under Ground Tank
₹ 45 lakh
As Per Project Report
Rain Water Harvesting
₹ 4 lakh
As Per Project Report
Electrical Sub Station
₹ 85 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Building Plan Approval (Memo No. Hsiidc/Ipd/Imt/M/2023/744
Already Been Obtained
8 Aug 2023
Noc From Airport Authority (Si/Rhq/Nr/ATS/Loc/2023/469/2099-2102
Already Been Obtained
13 Jul 2023
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitrified Tile, Laminate Wooden
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Ompee Tower?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.