This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
Registration certificate
Not issued yet: the application is being processed by HRERA Panchkula
Project ID
RERA-PKL-1843-2025
Authority
HRERA Panchkula
Project type (as filed)
New
Project name
Navraj The Marq
Site address
Sector 20,
Sector
Sector 20
Tehsil / District
Faridabad / Faridabad
Layout plan approved
24 Oct 2024
Building plans approved
24 Oct 2024
Construction start (as filed)
1 Jan 2026
Completion (as filed)
31 Dec 2030
Application submitted
20 Nov 2025
Authority, hearings & orders
Current statusWithdrawn/Rejected
Initial scrutinyListed for hearing on 03-12-2025
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingExamination By AuthorityView order Proceedings
License no 128 of 2024 dated 24.10.2024 issued to set up mix land use colony
FAR permissible / proposed
3.62 / 3.62
Estimated project cost
₹ 1,246.41 Cr
Cost of land
₹ 90 Cr
Cost of construction
₹ 755 Cr
EDC, taxes, levies and other costs
₹ 401.41 Cr
How the land will be used
Use
Sq m
Share
Land Area To Be Used For Construction Of Apartments
8,790.02
47.6%
Construction Of Roads
3,416.02
18.5%
Parks And Playgrounds
2,770.66
15%
Green Belts
1,756.98
9.5%
Electricity Sub-Station
203
1.1%
Sewage And Solid Waste Treatment Facility
308.3
1.7%
Any Other
1,218.79
6.6%
Apartments 645 units · 2 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
17,497.29
-
101
Apartment/Shops/Other Buildings
11,249.52
-
526
Apartment/Shops/Other Buildings
336.56
3,623
18
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
Plots 1 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
18,463.78
22,082
198,742
1
External services
Service
Provided by
Approval taken
Roads
NHAI
No
Water Supply
HSVP
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HSVP
Yes
Storm Water Drainage
No
FOREST NOC
Forest Department
Yes
ZONING PLAN
Dtcp
Yes
AIRPORT NOC
Airport Authority Of India
Yes
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
250.00
YET TO BE PREPARED
2
Water Supply System
325.00
YET TO BE PREPARED
3
STORM WATER DRAINAGE
150.00
Yet To Be Prepared
4
ELECTRICITY SUPPLY SYSTEM
1550
YET TO BE PREPARED
5
Sewage Treatment & Garbage Disposal
325
YET TO BE PREPARED
6
STREET LIGHTING
125
Yet To Be Prepared
7
SECURITY AND FIRE FIGHTING
1200
YET TO BE PREPARED
8
Playgrounds And Parks
82
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
Yet To Be Prepared
10
SHOPPING AREA
0
YET TO BE PREPARED
11
Renewable Energy System
215.96
YET TO BE PREPARED
12
SCHOOL
0
Yet To Be Prepared
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
Any Other
0
YET TO BE PREPARED
15
PARKING
125.00
Yet To Be Prepared
16
STP
500.00
YET TO BE PREPARED
17
Undergraound Water Tank
325.00
YET TO BE PREPARED
18
RAIN WATER HARVESTING
125.00
Yet To Be Prepared
19
ELECTRICAL SUB STATION
2010.00
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
24-10-2024
(date)
6. Date of approval of Building Plans
24-10-2024
(date)
7. New projects:
i) Likely date of starting the construction work
01-01-2026
ii) Likely date of completing the project
31-12-2030
iii) Sizes of the plots to be offered in the project
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
18463.78
1
Total
1
iv. Type of apartments to be constructed in the project:
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
17497.288
101
2
Apartment/Shops/Other Buildings
11249.519
526
2
Apartment/Shops/Other Buildings
336.558
18
1
(vi) Quarterly schedule of development of whole/remaining part of the project:
(c) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
1544.51
2059.35
2574.18
1544.51
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
4537.29
4022.45
3119.88
3231.19
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
5797.60
5543.41
6428.62
6650.37
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
8008.88
5310.29
3505.64
3077.97
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
1303.86
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
230.00
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Security and Fire Fighting
120.00
120.00
120.00
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
25.00
Water Supply System
0
97.50
97.50
130.00
Sewerage treatment & garbage disposal
97.50
97.50
97.50
32.50
Electricity Supply System
0
0
310.00
310.00
Storm Water Drainage
45.00
45.00
45.00
15.00
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Electrical sub station
402.00
Security and Fire Fighting
120.00
120.00
ELECTRICAL SUB STATION
402.00
402.00
UNDERGROUND WATER TANK
97.50
130.00
STP and WTP
150.00
Street Lighting
37.50
Rain Water Harvesting
37.50
50.00
Stp And Wtp
200.00
STREET LIGHTING
50.00
SECURITY AND FIRE FIGHTING
120.00
Security and fire fighting
120
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
50.00
50.00
75.00
50.00
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
465.00
465.00
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
41.00
41.00
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
ELECTRICAL SUB STATION
402.00
201.00
201.00
Security And Fire Fighting
120.00
120.00
60.00
60.00
PARKING
12.50
37.50
37.50
37.50
STREET LIGHTING
37.50
Stp And Wtp
150.00
UNDERGROUND WATER TANK
97.50
RAIN WATER HARVESTING
37.50
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
No
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
AXIS BANK , SHOP NO 78,79,56 GF, SPAZE CORPORATE PARKL, SECTOR 69, GURUGRAM
Bank Account number
923020062666491
IFSC code
UTIB0004762
MICR code
110211349
Branch code
4762
4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
Naveen Kumar
5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
YES
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - E
Details of the statutory approvals:
1. Annex copies of the following in Folder E:
i. Lay out Plan
No
ii. Demarcation Plan
No
iii. Zoning Plan
Yes
iv. Building Plan
No
Site Plan
Yes
Floor Plan
No
Apartment Plans
No
Elevation Section
No
Detail of Permissible FAR
No
Detail of covered area achieved FAR
No
2. Annex copies of the following in Folder E:
I. Roads And Pavement Plan
No
II. ELECTRICITY SUPPLY PLAN
No
III. WATER SUPPLY PLAN
No
IV. Sewerage And Garbage Disposal Plan
No
V. STROM WATER DRAINAGE
No
VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
No
Vii. Street Lighting Plan
No
VIII. PARKING PLAN
No
3. Statutory Approvals Status
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 128 OF 2024
Already Been Obtained
24-10-2024
II. FOREST NOC
Already Been Obtained
28-01-2025
III. SEWERAGE ASSURANCE
Already Been Obtained
20-01-2025
IV. ASSURANCES WATER SUPPLY
Already Been Obtained
20-01-2025
V. ASSURANCES TREATED STP WATER
Already Been Obtained
20-01-2025
VI. ASSUARNCES ELECTRICITY SUPPLY
Already Been Obtained
03-01-2025
VII. AIRPORT NOC
Already Been Obtained
15-01-2025
VIII. ROADS ASSURANCE
Applied For But Yet To Receive
NA
IX. ENVIORNMENT NOC
Applied For But Yet To Receive
NA
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.
Signature _____________
Seal _____________
Date _____________
Form Rep-I
Part - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.
Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)
(Annex a copy in Folder F)
Yes
3. Gist of the important provisions of the Draft Agreement
(Annex a copy in Folder F)
Gist Of Relevant Provisions Under The Mix Land Use Colony Buyer’S Agreement
CLAUSE NO. HEADING RELEVANCE
D Recitals Details of approved Zoning Plans
E Recitals Details of registered HARERA
H Recitals Description of the unit duly allotted to the Allottees
1.3 Terms The Total price of the duly allotted unit.
1.5 Payment Plan The Allottee agrees to pay as per the Payment plan as enclosed.
2.1 Mode of Payment The details of the Escrow RERA accounts.
5 Time is essence Timely payment by the Allottee is the essence of the contract.
6 Development of the Mix land use Colony Development shall be done as per the approved Zoning Plans/ Building plan.
7.1 Schedule for Possession of the Unit As per agreed terms and conditions on or before the time granted under the registration by the HARERA subject to force majeure.
9. Events of Defaults and consequences In case of failure in handing over the possession by the Promoter.
10. Conveyance deed & stamp duty charges Charges towards the registration and stamp duty at the time of Conveyance deed shall be paid by the Allottee.
11. Maintenance of the said Project A separate Maintenance Agency shall be appointed by the Promoter to maintain the said project after the delivery of the units and the unit owners/allottees shall enter into a Maintenance agreement and cooperate with the Maintenance Agency.
17. Haryana Apartment Ownership Act Both, Developer as well as the Allottee shall be bound with the provisions of the said Act. Details of approvals are laid down therein.
29. Notices Any and all communication to be done via Notice between the parties at the addresses as provided therein.
32. Governing Law RERA act shall govern the Agreement.
33. Dispute resolution by Arbitration Disputes shall be amicable resolved, in case of failure, Arbitrator shall be appointed by the Managing Director of the Promoter to settle the dispute between the parties
33 Jurisdiction Courts of Faridabad shall have the jurisdiction for the disputes arising out of the Agreement.
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - G
Projects launched by the promoter in last five years: (No Projects)
I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - H
Specification Of Construction
Specification of apartments and other buildings including the following:
1
Flooring Details Of Various Parts Of House
IMPORTED MARBLE FLOORING,LAMINATED WOOD/ VITRIFIED TILE,CERAMIC TILES-KAJARIA OR EQUIVALENT
2
Wall Finishing Details
PLASTER WITH OIL BOUND DISTEMPER , PLASTIC EMULSION-ASIAN OR SIMILAR
3
Kitchen Details
IMPORTED MARBLE /VITRIFIED TILES, ON WALLS COMBINATION OF CERAMIC TILES AND PAINT FINISH, ON CEILING WE USE ACRYLIC EMULSION PAINT , GRANITE COUNTER TOP , , SINK MIXER OF PREMIUM BRAND AND STAINLESS STEEL SINK OF PREMIUM BRAND-HETTICH OR SIMILAR
4
Bathroom Fittings
CP FITTINGS OF PREMIUM BRANDS-KHOLER OR SIMILAR
5
Wood Work Etc
MODULAR KITCHEN – SOFT CLOSE SHUTTERS AND DRAWERS UNDER COUNTER ONLY-CENTURY LAMINATED FLUSHED DOOR OR SIMILAR
6
Doors And Windos Frames
VENEERED/ LAMINATED FLUSHED DOORS WITH WOODEN ARCHITRAVE & FRAME-TEAK WOOD OR SIMILAR
7
Glass Work
UPVC/ ALUMINUM WINDOWS/ GLAZING WITH APPROPRIATE GLASS-SAINT GOBAIN GLASS OR SIMILAR
8
Electric Fittings
GEYSERS & EXHAUST FAN (PROVISION ONLY) IN KITCHEN & TOILETS.
MODULAR SWITCHES & SOCKETS, FRLS (FIRE RESISTANT LOW SMOKE) COPPER WIRING OF BRANDED MAKE.-WIRING- POLYCAB OR EQUIVALENT
Switches- Norisys Or Equivalent
9
CONDUCTING AND WIRING DETAILS
Pvc Conduiting-Polycab Or Similar
10
CUPBOARD DETAILS
Modular Kitchen-
11
WATER STORAGE
Rcc Tank/ Panel Tanks-As Per HSVP
12
LIFT DETAILS
High Speed Elevator-Kone Or Similar
13
EXTERNAL GLAZINGS
Upvc/ Aluminum Windows/ Glazing-Finesta Or Similar
13.1
WINDOWS/GLAZINGS
Upvc/ Aluminum Windows/ Glazing With Appropriate Glass-Finesta Or Similar
14
DOORS
Veneered/ Laminated Flushed Doors With Wooden Architrave & Frame-Greenply Or Similar
14.1
MAIN DOORS
Veneered/ Laminated Flushed Doors With Wooden Architrave & Frame-Greenply
OR SIMILAR
14.2
Internal Doors
VENEERED/ LAMINATED FLUSHED DOORS WITH WOODEN ARCHITRAVE & FRAME-GREENPLY OR SIMILAR
15
Air Conditioning
VRV SYSTEM WITH HI-WALL UNITS OF ADEQUATE CAPACITY IN BEDROOMS & DRAWING/ DINING ROOM ONLY-MITSHUBISHI OR SIMILAR
16
Electrical Fittings
SWITCHES AND OTHER SOCKETS-WIRING- POLYCAB OR EQUIVALENT
SWITCHES- NORISYS OR EQUIVALENT
17
CNG PIPE LINE
PROVISION FOR GAS PIPE LINE IN KITCHEN
18
PROVISION OF WIFI AND BROADBAND FACILITY
CONNECTIVITY PROVISION THROUGH SERVICE PROVIDER-BSNL OR SIMILAR
19
EXTERNAL FINISHING/COLOUR SCHEME
EXTERIOR GRADE PAINT FINISH-ASIAN OR SIMILAR
20
INTERNAL FINISHING
VITRIFIED TILES, PAINTS-ASIAN OR SIMILAR
Specification Unit Wise
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
Floor
IMPORTED MARBLE FLOORING-ITALIAN STONE OR SIMILAR
1 . 2
Walls
ACRYLIC EMULSION PAINT-ASIAN OR SIMILAR
1 . 3
Ceiling
ACRYLIC EMULSION PAINT-ASIAN OR SIMILAR
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
LAMINATED WOOD/ VITRIFIED TILE-ITALIAN STONE OR SIMILAR
2 . 2
WALLS
ACRYLIC EMULSION PAINT-ASIAN OR SIMILAR
2 . 3
CEILING
ACRYLIC EMULSION PAINT-ASIAN OR SIMILAR
2 . 4
MODULAR WARDROBES
NOT PROVING-CENTURY BOARD WITH GLASS SHUTTER
3 . Master Toilet
3 . 1
FLOOR
Vitrified Tiles-Kajaria Or Similar
3 . 2
WALLS
Ceramic/Vitrified Tiles Up To False Ceiling-Kajaria Or Similar
3 . 3
CEILING
Moisture Resistant Gypsum/Board False Ceiling-Asian Or Similar
3 . 4
COUNTERS
Granite/ Stone-Granite.
3 . 5
SANITARY WARE/CP FITTINGS
- Wooden Vanity With Granite/ Stone Counter
- WHITE SANITARY FIXTURES OF PREMIUM BRANDS
- CP FITTINGS OF PREMIUM BRANDS
Jaguar Or Similar
3 . 6
FITTING/FIXTURES
Cp Fitting-Jaguar Or Similar
4 . BED ROOMS
4 . 1
Floor
LAMINATED WOOD /VITRIFIED TILES-ITALIAN STONE OR SIMILAR
4 . 2
Walls
ACRYLIC EMULSION PAINT-ASIAN OR SIMILAR
4 . 3
Ceiling
ACRYLIC EMULSION PAINT-ASIAN OR SIMILAR
4 . 4
Wardrobes
NP-CENTURY BOARD WITH GLASS SHUTTER
5 . TOILET
5 . 1
FLOOR
VITRIFIED TILES-KAJARIA OR SIMILAR
5 . 2
WALLS
CERAMIC/VITRIFIED TILES UPTO FALSE CEILING-KAJARIA OR SIMILAR
5 . 3
CEILING
MOISTURE RESISTANT GYPSUM/BOARD FALSE CEILING-ASIAN OR SIMILAR
5 . 4
COUNTERS
GRANITE/ STONE
5 . 5
SANITARY WARE/CP FITTINGS
- WOODEN VANITY WITH GRANITE/ STONE COUNTER
- White Sanitary Fixtures Of Premium Brands
- CP FITTINGS OF PREMIUM BRANDS
JAGUAR OR SIMILAR
5 . 6
FIXTURES
CP FITTING-JAGUAR OR SIMILAR
6 . Kitchen
6 . 1
FLOOR
Imported Marble /Vitrified Tiles-Italian Stone Or Similar
6 . 2
WALLS
Combination Of Ceramic Tiles And Paint Finish-Kajaria Or Similar
6 . 3
CEILING
Acrylic Emulsion Paint-Asian Or Similar
6 . 4
COUNTERS
Granite Counter Top-Natural Granite Or Similar
6 . 5
FIXTURES
Sink Mixer Of Premium Brand-Kohlar Or Similar
6 . 6
KITCHEN APPLIANCES
Stainless Steel Sink Of Premium Brand
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
Floor
VITRIFIED TILES-KAJARIA OR SIMILAR
7 . 2
Walls & Ceiling
OIL BOUND DISTEMPER-ASIAN OR SIMILAR
7 . 3
Toilet
OIL BOUND DISTEMPER-KAJARIA OR SIMILAR
7 . 4
Balcony
TILE FLOORING-KAJARIA OR SIMILAR
8 . SIT-OUTS
8 . 1
FLOOR
VITRIFIED TILES-KAJARIA OR SIMILAR
8 . 2
WALLS & CEILING
EXTERIOR GRADE PAINT-ASIAN OR SIMILAR
8 . 3
RAILINGS
EXTERIOR GRADE PAINT-APOLLO OR SIMILAR
8 . 4
FIXTURES
MS/ SS RAILING WITH GLASS-APOLLO OR SIMILAR
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
List of Uploaded Documents
Sr. No.
Document Description
Date of Document Upload
View Document
1
COPY OF LICENSE ALONG WITH SCHEDULE OF LAND
18-10-2025
View Document
2
Zoning Plan
06-11-2025
View Document
3
SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN
20-11-2025
View Document
4
A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS
20-11-2025
View Document
5
In Case Of Plotted Colony, The Latest Layout Plan
20-11-2025
View Document
6
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT
20-11-2025
View Document
7
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.
20-11-2025
View Document
8
Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record
20-11-2025
View Document
9
DEMARCATION PLAN
17-11-2025
View Document
10
NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT
20-11-2025
View Document
11
In Case Of Group Housing/ Commercial Sites, A Copy Of The Approved Site Plan
20-11-2025
View Document
12
CASH FLOW STATEMENT OF THE PROPOSED PROJECT
20-11-2025
View Document
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.5 Cr
Yet To Be Prepared
Water Supply System
₹ 3.25 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 1.5 Cr
Yet To Be Prepared
Electricity Supply System
₹ 15.5 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 3.25 Cr
Yet To Be Prepared
Street Lighting
₹ 1.25 Cr
Yet To Be Prepared
Security And Fire Fighting
₹ 12 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 82 lakh
Yet To Be Prepared
Renewable Energy System
₹ 2.16 Cr
Yet To Be Prepared
Parking
₹ 1.25 Cr
Yet To Be Prepared
Stp
₹ 5 Cr
Yet To Be Prepared
Undergraound Water Tank
₹ 3.25 Cr
Yet To Be Prepared
Rain Water Harvesting
₹ 1.25 Cr
Yet To Be Prepared
Electrical Sub Station
₹ 20.1 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
License No. 128 Of 2024
Already Been Obtained
24 Oct 2024
Forest Noc
Already Been Obtained
28 Jan 2025
Sewerage Assurance
Already Been Obtained
20 Jan 2025
Assurances Water Supply
Already Been Obtained
20 Jan 2025
Assurances Treated Stp Water
Already Been Obtained
20 Jan 2025
Assuarnces Electricity Supply
Already Been Obtained
3 Jan 2025
Airport Noc
Already Been Obtained
15 Jan 2025
Roads Assurance
Applied For But Yet To Receive
Enviornment Noc
Applied For But Yet To Receive
Specifications (as filed)
Flooring Details Of Various Parts Of House
Imported Marble Flooring,Laminated Wood/ Vitrified Tile,Ceramic Tiles-Kajaria Or Equivalent
Wall Finishing Details
Plaster With Oil Bound Distemper , Plastic Emulsion-Asian Or Similar
Kitchen Details
Imported Marble /Vitrified Tiles, On Walls Combination Of Ceramic Tiles And Paint Finish, On Ceiling We Use Acrylic Emulsion Paint , Granite Counter Top , , Sink Mixer Of Premium Brand And Stainless Steel Sink Of Premium Brand-Hettich Or Similar
Bathroom Fittings
Cp Fittings Of Premium Brands-Kholer Or Similar
Wood Work Etc
Modular Kitchen – Soft Close Shutters And Drawers Under Counter Only-Century Laminated Flushed Door Or Similar
Doors And Windos Frames
Veneered/ Laminated Flushed Doors With Wooden Architrave & Frame-Teak Wood Or Similar
Glass Work
Upvc/ Aluminum Windows/ Glazing With Appropriate Glass-Saint Gobain Glass Or Similar
Electric Fittings
Geysers & Exhaust Fan (Provision Only) In Kitchen & Toilets.
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Navraj The Marq?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.