Registration validHRERA Gurugram

Mrg Crown

by Mrg Group India Pvt. Ltd. · 9TH Floor, IREO Grand View Tower, Sector-58, Gurugram

RERA registration
GGM/706/438/2023/50
Registered on
29 Mar 2023
Valid till
15 Nov 2027
Project ID
RERA-GRG-1324-2023
Land area
3.8 acres
Apartments
436 in 19 towers
Plots
109
Completion (as filed)
30 Apr 2027
Estimated cost
₹ 474.97 Cr

RERA registration

Registration certificateGGM/706/438/2023/50, dated 29 Mar 2023
Registration valid till15 Nov 2027
Project IDRERA-GRG-1324-2023
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameMrg Crown
PromoterMrg Group India Pvt. Ltd.
Promoter’s registered office9TH Floor, IREO Grand View Tower, Sector-58, Gurugram-122102
CINU74999DL2018PTC331522
Site address9TH Floor, IREO Grand View Tower, Sector-58, Gurugram
SectorSector 58
Tehsil / DistrictGurgaon / Gurugram
Layout plan approved24 Nov 2022
Building plans approved22 Feb 2023
Construction start (as filed)1 May 2023
Completion (as filed)30 Apr 2027
Application submitted10 Mar 2023

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing fixed
Next hearingNot Required
  1. Application submitted online
  2. Hearing Examination By Authority
    Proceedings

    The matter is adjourned to 29.03.2023.

  3. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Ms. Prachi Singh (Planning Executive) briefed about the facts of the case.Ms. Anjana Gulati is present on behalf of the promoter.Approved as proposed.

  1. Registration granted GGM/706/438/2023/50
  2. Certificate uploaded RC Uploaded
  3. Registration valid till

Land, licence & cost

Land area of the project3.8 acres
Total licensed area8.169 acres
Licence192 of 2022
FAR permissible / proposed2.64 / 2.6
Estimated project cost₹ 474.97 Cr
Cost of land₹ 92.22 Cr
Cost of construction₹ 226.26 Cr
Infrastructure and other structures₹ 9.49 Cr
EDC, taxes, levies and other costs₹ 147 Cr

How the land will be used

UseSq mShare
Land Area To Be Used For Construction Of Apartments15,387.576100%

Apartments 436 units · 19 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings88.4995248
Apartment/Shops/Other Buildings89.639658
Apartment/Shops/Other Buildings89.639658
Apartment/Shops/Other Buildings88.1294876
Apartment/Shops/Other Buildings88.1294832
Apartment/Shops/Other Buildings82.5088872
Apartment/Shops/Other Buildings82.5088864
Apartment/Shops/Other Buildings83.5089924
Apartment/Shops/Other Buildings83.508998
Apartment/Shops/Other Buildings72.5478132
Apartment/Shops/Other Buildings72.5478164

Areas are as filed with HRERA.

Plots 109 plots

Plot size (sq m)Sq ydSq ftPlots
129.651551,3958
131.131571,41116
139.321671,50018
140.851681,5166
140.991691,51816
142.541701,5342
147.351761,58619
148.211771,59512
149.051781,6048
149.991791,6142
149.991791,6142

External services

ServiceProvided byApproval taken
RoadsALREADY CONNECTEDNo
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.29 CrYet To Be Prepared
Water Supply System₹ 1.14 CrYet To Be Prepared
Storm Water Drainage₹ 60.9 lakhYet To Be Prepared
Electricity Supply System₹ 68.6 lakhYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 91.4 lakhYet To Be Prepared
Street Lighting₹ 53.3 lakhYet To Be Prepared
Security And Fire Fighting₹ 19.1 lakhYet To Be Prepared
Playgrounds And Parks₹ 76.1 lakhYet To Be Prepared
Club House/Community Centre₹ 11.5 lakhYet To Be Prepared

Statutory approvals

ApprovalStatusDate
Change Of DeveloperAlready Been Obtained9 Mar 2023
LicenceAlready Been Obtained23 Nov 2022
Br-IIIAlready Been Obtained22 Feb 2023
LoiAlready Been Obtained28 Jun 2022
Lc IV & IV-AAlready Been Obtained23 Nov 2022

Specifications (as filed)

Flooring Details Of Various Parts Of HouseTiles / Marble / Granite / Laminated Wood
Wall Finishing DetailsObd/ Semi-Acrylic / Acrylic Emulsion / Tiles
Kitchen DetailsModular Kitchen Without Appliances, And SS Sink
Bathroom FittingsCp Fittings, Wash Basin, Wc With Accessories
Doors And Windos FramesUpvc / Al / Wood
Glass WorkClear / Frosted Glass
Conducting And Wiring DetailsPvc Conduits, Fr Wiring
Cupboard DetailsDesigner Wardrobes In Bedrooms
Water StorageOht
Lift DetailsStandard Make
External GlazingsUpvc / Aluminium
Windows/GlazingsUpvc / Aluminium
DoorsWooden Flush Door
Main DoorsWooden Flush Door
Internal DoorsWooden Flush Door
Air ConditioningVrv With High Wall Units In Living, Dining, Bedrooms
Electrical FittingsSwitch Box And Sockets. Home Automation In Select Areas As Per Design
Cng Pipe LineGas Pipe Line Provision Only
Provision Of Wifi And Broadband FacilityProvision Only
External Finishing/Colour SchemeExterior Grade Paint
Internal FinishingAcrylic Emulsion Paint

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Mrg Crown?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.