LapsedHRERA GurugramInterim Rera

Monsoon Breeze Phase -I Ablm Towers

by Umang Realtech Pvt. Ltd · Village Naurangpur ,Sector 78, Gurugram

RERA registration
121 OF 2017
Registered on
28 Aug 2017
Valid till
5 Mar 2019
Project ID
RERA-GRG-1580-2024
Land area
12.514 acres
Estimated cost
₹ 90 Cr

RERA registration

Registration certificate121 OF 2017, dated 28 Aug 2017
Registration valid till5 Mar 2019
Project IDRERA-GRG-1580-2024
AuthorityHRERA Gurugram (Interim Rera)
Project type (as filed)Ongoing
Project nameMonsoon Breeze Phase -I Ablm Towers
PromoterUmang Realtech Private Limited
Promoter’s registered officeD- 64, 2ND Floor Defence Colony New Delhi New Delhi Dl 110024
CINU45400DL2007PTC163070
Site addressSector 78, District Gurugram, Haryana
SectorSector 78
Tehsil / DistrictGurgaon / Gurugram
Building plans approved9 Dec 2011
Application submitted29 Mar 2024

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted 121 OF 2017
  2. Registration valid till
  3. Application submitted online

Land, licence & cost

Land area of the project12.514 acres
Total licensed area12.514 acres
Licence38 of 2008 Dated 02.03.2008
FAR permissible / proposed0 / 0
Estimated project cost₹ 90 Cr
Cost of land₹ 29 Cr
Cost of construction₹ 45 Cr
Infrastructure and other structures₹ 3.35 Cr
EDC, taxes, levies and other costs₹ 12.65 Cr

How the land will be used

UseAcresShare
Plots To Be Sold12.514100%

External services

ServiceProvided byApproval taken
RoadsHSVPYes
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 7.67 lakhAs Per Project Report
Water Supply System₹ 1.49 CrAs Per Project Report
Electricity Supply System₹ 1.47 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 2.25 lakhAs Per Project Report
Security And Fire Fighting₹ 25.81 lakhAs Per Project Report

Statutory approvals

ApprovalStatusDate
Fire Fighting SchemeAlready Been Obtained27 Jul 2009
Building PlanAlready Been Obtained9 Dec 2011
Service Plan EstimateAlready Been Obtained17 May 2012
Zoning PlanAlready Been Obtained16 Jun 2008
Environmental Clearance For ConstructionAlready Been Obtained21 Jan 2010
Environmental Clearance For Proposed ExpansionAlready Been Obtained21 Feb 2014

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tiles
Wall Finishing DetailsOil Bound Distemper
Kitchen DetailsGranite Counter, Ceramic Tiles Upto 2 Ft Above Counter And Rest Obd
Bathroom FittingsCp Fitting & China Ware
Wood Work EtcSemi Modular Kitchen Below Counter Only
Doors And Windos FramesPainted Hard Wood Door Frames With Flush Door Shutters
Glass WorkUpvc With Toughned Glass
Electric FittingsNot Providing
Conducting And Wiring DetailsCopper Wiring In Recessed Pvc Conduit
Cupboard DetailsNot Providing
Water StorageUnder Ground&over; Head Tanks
Lift DetailsPassenger & Service Lifts In Each Tower
External GlazingsUpvc
Windows/GlazingsUpvc
DoorsDecorative Laminated Flush Doors
Main DoorsDecorative Laminated Flush Doors
Internal DoorsPainted Flush Doors
Air ConditioningNot Providing
Electrical FittingsNot Providing
Cng Pipe LineNot Providing
Provision Of Wifi And Broadband FacilityNot Providing
External Finishing/Colour SchemeTexture Paint With Pleasant Shades
Internal FinishingOil Bound Distemper

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Monsoon Breeze Phase -I Ablm Towers?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.