Village Badshapur And Maidawas, Sector-65, Gurugram
Sector
Sector 65
Tehsil / District
Badshahpur St / Gurugram
Construction start (as filed)
15 Nov 2017
Completion (as filed)
30 Jun 2024
Application submitted
12 Feb 2020
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Next hearingNot Required
Registration granted01 OF 2017
Application submitted online
Application received by HRERA Gurugram
Registration valid till
Land, licence & cost
Land area of the project
14.413 acres
Total licensed area
14.413 acres
Licence
15 of 2017 dated 2.05.2017
FAR permissible / proposed
205888.046 / 353
Estimated project cost
₹ 2,706.46 Cr
Cost of land
₹ 745.4 Cr
Cost of construction
₹ 661.56 Cr
Infrastructure and other structures
₹ 176.5 Cr
EDC, taxes, levies and other costs
₹ 1,123 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
7.202
50%
Construction Of Roads
2.787
19.3%
Pavements
1.23
8.5%
Parks And Playgrounds
1.535
10.7%
Vehicle Parkings
0.008
0.1%
Area To Be Left For Transferring To The Government For Community Services
0.018
0.1%
Any Other
1.6185
11.2%
Rain
0.014
0.1%
Apartments 2,399 units · 9 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
150,491.00
-
2399
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
HSVP/ GMDA
No
Water Supply
HSVP / GMDA
Yes
Electricity
DHBVNL
Yes
Sewage Disposal
HSVP/GMDA
No
Storm Water Drainage
HSVP/GMDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 12.88 Cr
As Per Project Report
Water Supply System
₹ 26.41 Cr
As Per Project Report
Storm Water Drainage
₹ 65 lakh
As Per Project Report
Electricity Supply System
₹ 27.35 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 44 lakh
As Per Project Report
Security And Fire Fighting
₹ 26.3 Cr
As Per Project Report
Playgrounds And Parks
₹ 1.71 Cr
As Per Project Report
Club House/Community Centre
₹ 15.41 Cr
As Per Project Report
Renewable Energy System
₹ 1.08 Cr
As Per Project Report
Any Other
₹ 27.25 Cr
As Per Project Report
Underground Water Tank
₹ 1.12 Cr
As Per Project Report
Electrical Sub Station
₹ 34.5 Cr
As Per Project Report
Rain Water Harvesting
₹ 39 lakh
As Per Project Report
Stp
₹ 1.03 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Licence
Already Been Obtained
2 May 2017
Zoning Plan
Already Been Obtained
2 May 2017
Building Plan
Already Been Obtained
8 Feb 2018
Service Plan Estimates
Already Been Obtained
11 Mar 2019
Aravali
Already Been Obtained
12 Dec 2014
Forest
Already Been Obtained
30 Jul 2010
Electricity
Already Been Obtained
3 May 2017
Noc For Height Clearance
Already Been Obtained
31 Oct 2014
Harera Registration No.
Already Been Obtained
14 Jun 2017
Specifications (as filed)
Flooring Details Of Various Parts Of House
Rcc Slab/Tile
Wall Finishing Details
Painted/White Wash Masonry Wall/Partition
Bathroom Fittings
Standard Chinaware, Cp Fittings, With/ Without Wash Basin Counter
Doors And Windos Frames
Powder Coated Aluminium Frame/Wooden Frame
Glass Work
Glass Thickness Varies From 5 To 12MM
Electric Fittings
Public Areas & Toilets To Be Provided With Led Light Fixtures.
Conducting And Wiring Details
Is Approved Conduits & Wires
Water Storage
Rcc Tank
Lift Details
Schindler / Thyssenkrupp / Fujitec / Kone
External Glazings
Powder Coated Aluminium Glazing With Glass Of 5-12 Mm Thick Glass
Windows/Glazings
Powder Coated Aluminium Glazing With Glass Of 5-12 Mm Thick Glass
Doors
Aluminium Doors / Glass Doors
Main Doors
Aluminium Doors / Glass Doors
Internal Doors
Ms/Aluminium/Wooden
Air Conditioning
Chilled Water Ac System Upto Tap Off For Multiplex/Cinema & Food Court. Provision For Water Cooled Dx System Up To Tap Off Inside The Shop. Air Cooled Dx Split Ac System For Residential Block
Electrical Fittings
Provision Of Wire / Cable Up To Distribution Board Isi /Bis Approved
Provision Of Wifi And Broadband Facility
Provision Of Ont Box Only
External Finishing/Colour Scheme
Paint/Glass/Acp
Internal Finishing
Antiskid Tiles/Ips On Floor, Paint/White Wash Finish On Wall & Ceiling In Public Areas
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Mixed Land Use Colony For 14.4125 Acres?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.