HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Approved for Registration
Registration valid till
Land, licence & cost
Land area of the project
34.931 acres
Total licensed area
1,034.594 acres
Licence
16 of 2018, 11 of 2021 and 64 of 2022
Estimated project cost
₹ 74.25 Cr
Cost of land
₹ 32.73 Cr
Infrastructure and other structures
₹ 40.77 Cr
EDC, taxes, levies and other costs
₹ 0.75 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
16.82
48.2%
Construction Of Roads
15.371
44%
Parks And Playgrounds
2.74
7.8%
Plots 540 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
58.86
70
634
5
61.79
74
665
37
90.45
108
974
1
92.94
111
1,000
10
109.00
130
1,173
2
109.32
131
1,177
91
109.41
131
1,178
5
109.48
131
1,178
72
109.73
131
1,181
1
109.80
131
1,182
1
110.29
132
1,187
2
120.59
144
1,298
2
123.46
148
1,329
2
129.13
154
1,390
44
129.96
155
1,399
62
130.03
156
1,400
24
131.12
157
1,411
2
133.46
160
1,437
2
133.64
160
1,438
4
144.09
172
1,551
5
144.40
173
1,554
2
149.90
179
1,614
2
149.92
179
1,614
9
149.94
179
1,614
21
150.00
179
1,615
131
1,560.30
1,866
16,795
1
External services
Service
Provided by
Approval taken
Roads
PWD
Yes
Water Supply
DTCP, HARYANA
Yes
Electricity
UHBVN
Yes
Sewage Disposal
DTCP, HARYANA
Yes
Storm Water Drainage
DTCP, HARYANA
Yes
Layout Plan
DTCP,HARYANA
Yes
License For Project
DTCP,HARYANA
Yes
Zoning Plan
DTCP,HARYANA
Yes
Service Plan Estimate
DTCP,HARYANA
Yes
Enviromental Clearance
MOEF
Yes
Cte Permission
HARYANA STATE POLLUTION CONTROL BOARD
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 11.75 Cr
As Per Project Report
Water Supply System
₹ 2.84 Cr
As Per Project Report
Storm Water Drainage
₹ 4.46 Cr
As Per Project Report
Electricity Supply System
₹ 12.97 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 2.3 Cr
As Per Project Report
Street Lighting
₹ 79.8 lakh
As Per Project Report
Security And Fire Fighting
₹ 30 lakh
As Per Project Report
Playgrounds And Parks
₹ 2.57 Cr
As Per Project Report
Horticulture
₹ 92.21 lakh
As Per Project Report
Pmc Consultancy Gate Community Facility Contingency Etc
₹ 1.86 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Layout Plan
Already Been Obtained
24 May 2022
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Met City Pocket C & D?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.