4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
0
Yet To Be Prepared
2
WATER SUPPLY SYSTEM
0
YET TO BE PREPARED
3
Storm Water Drainage
0
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
0
Yet To Be Prepared
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
YET TO BE PREPARED
6
Street Lighting
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
Yet To Be Prepared
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
Na
(date)
6. Date of approval of Building Plans
Na
(date)
(i) Details of the plots/apartments in the project:
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type GF
2723
104
283192
0
0
0
2
APARTMENT/SHOPS/OTHER BUILDINGS Type FF
1992.37
85
169351.45
0
0
0
3
APARTMENT/SHOPS/OTHER BUILDINGS Type SF
824.63
39
32160.57
0
0
0
4
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-3
1148.12
35
40184.2
0
0
0
5
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-4
1148.12
35
40184.2
0
0
0
6
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-5
783.49
15
11752.35
0
0
0
7
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-6
601.65
16
9626.4
0
0
0
8
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-7
665.15
22
14633.3
0
0
0
9
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-8
665.15
22
14633.3
0
0
0
10
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-9
665.15
22
14633.3
0
0
0
11
APARTMENT/SHOPS/OTHER BUILDINGS Type SA-10
667.59
20
13351.8
0
0
0
Total
415
643702.87
0
0
0
(ii) Apartments/Shops/Other Buildings:-
(a) Status of construction activities in respect of sold/booked apartments.
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
GF
0
100%
(b) Time schedule of completion of already booked apartments:
Start Date
01-11-2014
Earlier date of completion
20-12-2020
Revised date of completion
20-12-2020
(c) Time schedule for development of infrastructure:
Start Date
01-11-2014
Percentage completion Upto the
date of application
100
Projected date of completion
20-12-2020
(d) Provide further details in the proforma REP-I Part-C-X.
Attached
(e) Plan of action for completing the Project along with requisite infrastructure.
ATTACHED
(iii) Status in respect of plotted colony:-
(a)
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
(b) Schedule for development of Infrastructure:
Start Date
01-11-2014
Percentage completion
100
Projected date of completion
20-12-2020
(c) Provide further details in the proforma REP-I Part-C-X.
ATTACHED
(d) Schedule of completing the project and handing over possession of the plots.
Attached
(iv) Vehicle parkings details of the project-
a) Underground parking
329
b) Stilt parking
0
c) Covered parking
0
d) Open parking
61
e) Independent garages
0
(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
14649.53
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - C-X
1.Financial information:
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
400
0
ii. No. of Flats/ Apartments booked
0
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
0 Lakhs
0
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
00
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
0
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
0
vii. Amount invested in the project upto the date of application
0 Lakhs
0
Land cost (If any)
5238 Lakhs
0
Apartments
0 Lakhs
00
Infrastructure
0 Lakhs
0
EDC/ Taxes Etc.
0 Lakhs
0
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
0
(a) In respect of existing allottees
0 Lakhs
00
(b) In respect of rest of the project
0 Lakhs
0
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
0
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
0
2.Additional information:
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. Internal Roads And Pavements
0
0
II. Water Supply System
0
0
III. Storm Water Drainage
0
0
IV. Electricity Supply System
0
0
V. Sewage Treatment & Garbage Disposal
0
0
Vi. Club House/Community Centre
0
0
Vii. School
0
0
Viii. Any Other
0
0
Ix. Solid Waste Collection & Mgmt System
0
0
X. Clubhouse
0
0
Xi. Neighbourhood Shopping
0
0
Xii. Green Areas,Parks,Playgrounds Etc.
0
0
Xiii. Covered Parking
0
0
Xiv. Open Parking
0
0
Xv. Garages
0
0
Xvi. Security System
0
0
Xvii. Other Facilities As Per Project Report
0
0
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
No
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
Oriental Bank Of Commerce, Shop No. 08, Vipul Square, B- Block, Sushant Lok-I, Gurugram-122002
Bank Account number
11521132000179
IFSC code
ORBC0101152
MICR code
110022134
Branch code
101152
Statutory approvals
Approval
Status
Date
Dtcp License
Already Been Obtained
4 May 2017
Approval From Forest Department Haryana Under Land Preservation Act
Already Been Obtained
17 Jun 2013
Ultimate Power Load Requirement
Already Been Obtained
9 May 2017
Noc From Civil Aviation
Already Been Obtained
29 Jan 2015
Noc/ Approval From Fire Deptt
Already Been Obtained
12 Apr 2017
Noc For Non Applicability Of Aravali Notification Of 1992
Already Been Obtained
17 Oct 2013
Noc From HUDA Regarding Non Usage Of Ground Water For Construction
Already Been Obtained
9 May 2013
Assurance From HUDA Regarding Wter Supply For Drinking
Already Been Obtained
11 Dec 2013
Layout Of Electrical Installation - Single Lime Diagram
Already Been Obtained
22 Oct 2013
Noc From Deptt Of Minning And Geology
Already Been Obtained
4 Apr 2014
Noc From Wildlife Ofiicer, Gurugram
Already Been Obtained
10 Sep 2015
Environment Clearance Moefe&cc;, Goi
Already Been Obtained
28 Feb 2014
Consent To Establish- Haryana Pollution Control Board
Already Been Obtained
16 Jun 2014
Dpc Certificate
Already Been Obtained
29 Apr 2015
Change Of Name From Everlike Buildcon Pvt Ltd To Silverglades Infrastructure Pvt Ltd By Dtcp, Haryana
Already Been Obtained
9 Jan 2017
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Merchant Plaza?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.