Maruti Kunj (Phase-1) 22.82833 Acre
by Gopal Hitech Infra Developers Pvt. Ltd. · Village Garhi Alawalpur Sector 24
- RERA registration
- Applied, not granted yet
- Applied on
- 8 Jan 2020
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-783-2019
- Land area
- 22.829 acres
- Plots
- 262
- Completion (as filed)
- 31 Dec 2022
- Estimated cost
- ₹ 32.85 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-783-2019 |
| Authority | HRERA Panchkula |
| Project type (as filed) | New |
| Project name | Maruti Kunj (Phase-1) 22.82833 Acre |
| Promoter | Gopal Hitech Infra Developers Pvt. Ltd. |
| Promoter’s registered office | Shop No. 212 Ansal Bhawan 16, Kasturba Gandhi Marg New Delhi-110001 |
| CIN | U70200DL2011PTC215686 |
| Site address | Village Garhi Alawalpur Sector 24 |
| Sector | Sector 24 |
| Tehsil / District | Dharuhera St / Rewari |
| Layout plan approved | 18 Dec 2018 |
| Building plans approved | 18 Dec 2018 |
| Construction start (as filed) | 1 Apr 2020 |
| Completion (as filed) | 31 Dec 2022 |
| Application submitted | 8 Jan 2020 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
Adjourned to 16.03.2020.
-
Hearing
Objection View order
Proceedings
Adjourned to 15.06.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 13.07.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 31.08.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 28.09.2020.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 12.10.2020.
-
Hearing
Sine Die View order
Proceedings
Sine Die
-
Hearing
Adjournment View order
Proceedings
Adjourned to 15.02.2021.
-
Hearing
Adjournment View order
Proceedings
Adjourned to 01.03.2021.
-
Hearing
Withdrawn/Rejected View order
Proceedings
Disposed off with the direction that the applicant shall file fresh application in place of the earlier application.
Land, licence & cost
| Land area of the project | 22.829 acres |
|---|---|
| Total licensed area | 22.829 acres |
| Licence | License No. 09 of 2018 dated 29.01.2018 which is valid upto 28.01.2023. |
| Estimated project cost | ₹ 32.85 Cr |
| Cost of land | ₹ 17.18 Cr |
| Infrastructure and other structures | ₹ 9.19 Cr |
| EDC, taxes, levies and other costs | ₹ 6.48 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 11.4946 | 50.4% |
| Construction Of Roads | 8.1872 | 35.9% |
| Parks And Playgrounds | 2.0386 | 8.9% |
| Community Site | 0.2 | 0.9% |
| Commercial | 0.9084 | 4% |
Plots 262 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 50.00 | 60 | 538 | 53 |
| 162.00 | 194 | 1,744 | 2 |
| 184.11 | 220 | 1,982 | 9 |
| 187.20 | 224 | 2,015 | 11 |
| 198.00 | 237 | 2,131 | 13 |
| 200.00 | 239 | 2,153 | 33 |
| 227.04 | 272 | 2,444 | 25 |
| 235.00 | 281 | 2,530 | 11 |
| 246.04 | 294 | 2,648 | 4 |
| 309.55 | 370 | 3,332 | 99 |
| 311.28 | 372 | 3,351 | 2 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | No |
| Water Supply | HSVP | No |
| Electricity | UHBVNL | No |
| Sewage Disposal | HSVP | No |
| Storm Water Drainage | HSVP | No |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.3 Cr | As Per Project Report |
| Water Supply System | ₹ 1.01 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 91.89 lakh | As Per Project Report |
| Electricity Supply System | ₹ 2.3 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.01 Cr | As Per Project Report |
| Street Lighting | ₹ 73.51 lakh | As Per Project Report |
| Playgrounds And Parks | ₹ 91.89 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No. 09 Of 2018 | Already Been Obtained | 29 Jan 2018 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Not Applicable Being Plotted Colony. |
|---|---|
| Wall Finishing Details | Not Applicable Being Plotted Colony. |
| Kitchen Details | Not Applicable Being Plotted Colony. |
| Bathroom Fittings | Not Applicable Being Plotted Colony. |
| Wood Work Etc | Not Applicable Being Plotted Colony. |
| Doors And Windos Frames | Not Applicable Being Plotted Colony. |
| Glass Work | Not Applicable Being Plotted Colony. |
| Electric Fittings | Not Applicable Being Plotted Colony. |
| Conducting And Wiring Details | Not Applicable Being Plotted Colony. |
| Cupboard Details | Not Applicable Being Plotted Colony. |
| Water Storage | Not Applicable Being Plotted Colony. |
| Lift Details | Not Applicable Being Plotted Colony. |
| External Glazings | Not Applicable Being Plotted Colony. |
| Windows/Glazings | Not Applicable Being Plotted Colony. |
| Doors | Not Applicable Being Plotted Colony. |
| Main Doors | Not Applicable Being Plotted Colony. |
| Internal Doors | Not Applicable Being Plotted Colony. |
| Air Conditioning | Not Applicable Being Plotted Colony. |
| Electrical Fittings | Not Applicable Being Plotted Colony. |
| Cng Pipe Line | Not Applicable Being Plotted Colony. |
| Provision Of Wifi And Broadband Facility | Not Applicable Being Plotted Colony. |
| External Finishing/Colour Scheme | Not Applicable Being Plotted Colony. |
| Internal Finishing | Not Applicable Being Plotted Colony. |
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Maruti Kunj (Phase-1) 22.82833 Acre?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.