Mahira Homes 88B
by Mahira Homes Private Limited · Vill - Harsaru Sector 88B
- RERA registration
- Applied, not granted yet
- Applied on
- 10 Apr 2023
- Application status
- Rejected
- Project ID
- RERA-GRG-1354-2023
- Land area
- 10.075 acres
- Apartments
- 1,462 in 13 towers
- Completion (as filed)
- 31 Dec 2027
- Estimated cost
- ₹ 290.35 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Gurugram |
|---|---|
| Project ID | RERA-GRG-1354-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Mahira Homes 88B |
| Promoter | Mahira Homes Private Limited |
| Promoter’s registered office | 301 3RD Floor Global Foyer Mall Sec 43 Golf Course Road Gurugram, 122009 |
| CIN | U70109HR2016PTC066406 |
| Site address | Vill - Harsaru Sector 88B |
| Sector | Sector 88B |
| Tehsil / District | Harsaru St / Gurugram |
| Construction start (as filed) | 5 Apr 2023 |
| Completion (as filed) | 31 Dec 2027 |
| Application submitted | 10 Apr 2023 |
Authority, hearings & orders
- Application submitted online
- Notice sent to the promoter BY Hand
-
Hearing
Examination By Authority View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Amit Singh (AR) is present on behalf of the promoter. The AR of the promoter stated that they have submitted a reply on 13.04.2023 which needs to be scrutinized. A copy of complaint has handed over to the AR of the promoter and DTCP has granted the additional license under Construction linked plan. The AR is directed to file reply within 2 days and the matter to come up on 24.04.2023.
-
Hearing
Adjournment View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. None is present on behalf of the promoter. A request for adjournment for one week has been received from the applicant. The matter to come up on 01.05.2023.
-
Hearing
Adjournment View order
Proceedings
Due to administrative work, the matter is adjourned to 15.05.2023.
-
Hearing
Adjournment View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. None is present on behalf of the promoter. The matter is adjourned to 29.05.2023.
-
Hearing
Adjournment View order
Proceedings
Proceedings dated 29.05.2023 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. None is present on behalf of the respondent and no reply has been filed for the complaint dated 24.4.2023 till now. As the promoter failed to submit the required approvals in the authority despite various opportunities. Hence, the authority decided to issue a show cause notice as to why the application for registration should not be rejected as provided under section 5 (1)(b) of the Real Estate (Regulation and Development) Act, 2016 and Rule-5 of Haryana Real Estate (Regulation and Development) Rules 2017. Matter to come up on 03.07.2023 for further proceedings.
-
Hearing
Objection View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Ravi Kumar (AR) along with Sh. Amit Kumar and Sh. Alakh Niranjan are present on behalf of the promoter. No reply has been submitted by the promoter against the show cause notice dated 01.06.2023 issued by the Authority. However, the promoter has submitted an application dated 19.06.2023 for withdrawal /surrender of RERA Registration NO. 51 of 2023 which was the original registration granted for 6.675 acres. The AR submits that the promoter does not wish to continue with the project and is requesting for withdrawal of the present application as well as surrender of the registration No. 51 of 2023. The AR further confirms that no 3rd party rights of any kind for sale, booking has been made in the above project and an affidavit to this effect shall also be submitted. It has been brought to the notice of the Authority that vide order dated 27.06.2023 of the DGTCP Haryana has passed an order for registration of FIR against the colonizer, its directors, associate companies, authorized signatory and the architect in the matter where building plans were submitted for the whole area of 10.075 acres to the GMDA under forged and fabricated signatures. Further, vide another show cause notice dated 27.06.2023, the DGTCP has taken cognizance of various complaints filed against the promoter and suspended license No. 9 of 2022 and license No. 61 of 2023 under section 3(3a) of the Act of 1975 with immediate effect and to explain as to why the mortgaged deed dated 19.07.2022 executed on the encumbered land may not be revoked and to explain as to how the title of the land of the aforementioned licenses be considered as ‘clear’ in accordance with section 3(2)(a) of the Act of 1975 in the light of the public notice dated 18.04.2023 issued by IHFL. It was decided that the matter be examined on file. The Matter to come up on 17.07.2023.
-
Hearing
Adjournment View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh, Ravi Kumar (AR) is present on behalf of the promoter. As the promoter has submitted the false information to the Authority pertaining to non-encumbrance on land and UDIN of CA certificate of non- default issued by CA has been withdrawn. Hence, the authority decided to issue a show cause notice under section 60 of the Act of 2016 for submitting false information before Authority. The matter to come up on 21.08.2023
-
Hearing
Adjournment View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. A show cause notice for submitting false information before the Authority punishable under section 60 of the Act of 2016 is being issued to the promoter. The matter to come up on 25.09.2023.
-
Hearing
Rejected View order
Proceedings
Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. None is present on behalf of the promoter. The application for registration of additional area of 3.4 acres is hereby rejected and the earlier registration certificate i.e., 51 of 2023 issued for 6.675 acres is hereby kept in abeyance and no advertisement, sale, purchase in respect of same shall be made by the promoter. Further regarding action for submission of false information for registration of the project at the time of registration, the DTCP is already seized of the matter and proceedings for above false documents shall be finalized after the requisite action is taken by DTCP. A public notice for abeyance of the existing registration and of rejection of additional area applied be also issued in the newspapers for information of general public to not make any sale or purchase in any manner in respect of above project. Detailed order will follow.
Land, licence & cost
| Land area of the project | 10.075 acres |
|---|---|
| Total licensed area | 10.075 acres |
| Licence | 09 of 2022 dated 31.01.2022 and 61 of 2023 dated 27.03.2023 |
| FAR permissible / proposed | 998516.924 / 9.672 |
| Estimated project cost | ₹ 290.35 Cr |
| Cost of land | ₹ 80.97 Cr |
| Cost of construction | ₹ 159.42 Cr |
| Infrastructure and other structures | ₹ 107.1 Cr |
| EDC, taxes, levies and other costs | ₹ 11.51 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 1,462 | 100% |
Apartments 1,462 units · 13 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 92,861.45 | - | 1462 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | No | WATER SUPPLY |
| No | ELECTRICITY | No |
| Sewage Disposal | No | STORM WATER DRAINAGE |
| No | 4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report: | Sr. No. |
| Name of the facility | Estimated cost (In Lakhs)(Within the project area only) | Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C) |
| 1 | INTERNAL ROADS AND PAVEMENTS | 437.72 |
| Yet To Be Prepared | 2 | WATER SUPPLY SYSTEM |
| 247.53 | YET TO BE PREPARED | 3 |
| Storm Water Drainage | 84.52 | YET TO BE PREPARED |
| 4 | ELECTRICITY SUPPLY SYSTEM | 48.30 |
| Yet To Be Prepared | 5 | SEWAGE TREATMENT & GARBAGE DISPOSAL |
| 398.48 | YET TO BE PREPARED | 6 |
| Street Lighting | 58.35 | YET TO BE PREPARED |
| 7 | SECURITY AND FIRE FIGHTING | 33.21 |
| Yet To Be Prepared | 8 | PLAYGROUNDS AND PARKS |
| 42.50 | YET TO BE PREPARED | 9 |
| Club House/Community Centre | 20.81 | YET TO BE PREPARED |
| 10 | SHOPPING AREA | 20.81 |
| Yet To Be Prepared | 11 | RENEWABLE ENERGY SYSTEM |
| 48.30 | YET TO BE PREPARED | 12 |
| School | 0 | YET TO BE PREPARED |
| 13 | HOSPITAL/DISPENSARY | 0 |
| Yet To Be Prepared | 14 | ANY OTHER |
| 86.48 | YET TO BE PREPARED | 15 |
| Electrical Sub Station | 128.30 | YET TO BE PREPARED |
| 16 | RAIN WATER HARVESTING | 67.92 |
| Yet To Be Prepared | 17 | PARKING |
| 13.58 | YET TO BE PREPARED | 5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed. |
| Na | (date) | 6. Date of approval of Building Plans |
| Na | (date) | 7. New projects: |
| i) Likely date of starting the construction work | 05-04-2023 | ii) Likely date of completing the project |
| 31-12-2027 | iii) Sizes of the plots to be offered in the project | Sr. No |
| Plot Area(In Square Meter) | Number of plots in the project | 1 |
| 0 | 0 | Total |
| 0 | iv. Type of apartments to be constructed in the project: | Type |
| Carpet area(In Square Meter) | Number of apartments | Number of towers |
| Apartment/Shops/Other Buildings | 92861.45 | 1462 |
| 13 | (vi) Quarterly schedule of development of whole/remaining part of the project: | (c) Apartments/Shops/Other Buildings |
| Expenditure incurred till the date of application (In Lakhs) | Particulars | Expenditure |
| Expenditure to be made in each quarter (In Lakhs) | Particulars | Expenditure to be made in each quarter ( |
| ) | Apr-June | July-Sep |
| Oct-Dec | Jan-Mar | (d) Infrastructure |
| Expenditure incurred till the date of application (In Lakhs) | Particulars | Expenditure |
| Expenditure to be made in each quarter (In Lakhs) | Particulars | Expenditure to be made in each quarter ( |
| ) | Apr-June | July-Sep |
| Oct-Dec | Jan-Mar | It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
| Form Rep-I | Part - D | Accounts related information: |
| 1. Annex copy of the balance sheet of last 3 years | Yes | 2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D. |
| Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form. | No | 3. Bank account to which the deposits received from apartment buyers will be credited |
| Bank and Branch address | HDFC BANK LTD, 101 AND 101-A, QUTUB PLAZA, DLF PHASE-1, GURUGRAM-122002 | Bank Account number |
| 50200069990267 | IFSC code | HDFC0002853 |
| MICR code | 110211311 | Branch code |
| 2853 | 4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority) | SIKANDAR SINGH & SACHIN SHARMA |
| 5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details) | I hereby declare that the above information and particulars are based on record and are true to the | best of my knowledge and belief and nothing has been concealed. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
| Form Rep-I | Part - E | Details of the statutory approvals: |
| 1. Annex copies of the following in Folder E: | i. Lay out Plan | No |
| ii. Demarcation Plan | No | iii. Zoning Plan |
| No | iv. Building Plan | No |
| Site Plan | No | Floor Plan |
| No | Apartment Plans | No |
| Elevation Section | No | Detail of Permissible FAR |
| No | Detail of covered area achieved FAR | No |
| 2. Annex copies of the following in Folder E: | I. ROADS AND PAVEMENT PLAN | No |
| II. Electricity Supply Plan | No | III. WATER SUPPLY PLAN |
| No | IV. SEWERAGE AND GARBAGE DISPOSAL PLAN | No |
| V. Strom Water Drainage | No | VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY |
| No | VII. STREET LIGHTING PLAN | No |
| Viii. Parking Plan | No | 3. Statutory Approvals Status |
| Statutory Approvals | Statutory Approvals Status | Date |
| I. Dtcp | APPLIED FOR BUT YET TO RECEIVE | 05-04-2023 |
| It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees. | Signature _____________ | Seal _____________ |
| Date _____________ | FORM REP-I | Part - F |
| 1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers. | (Annex a copy in Folder F) | Yes |
| 2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules) | (Annex a copy in Folder F) | Yes |
| 3. Gist of the important provisions of the Draft Agreement | (Annex a copy in Folder F) | I hereby declare that the above information and particulars are based on record and are true to the |
| best of my knowledge and belief and nothing has been concealed. | Signature of the Applicant / Authorised Representative | Stamp _____________ |
| Date _____________ | FORM REP-I | Part - G |
| Projects launched by the promoter in last five years: (No Projects) | I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed. | Signature of the Applicant / Authorised Representative |
| Stamp _____________ | Date _____________ | FORM REP-I |
| Part - H | SPECIFICATION OF CONSTRUCTION | Specification of apartments and other buildings including the following: |
| 1 | FLOORING DETAILS OF VARIOUS PARTS OF HOUSE | VETRIFIED |
| Tile | SOMANI / | AGL / |
| Equivalen | T | RS 28 PER |
| Sqft + Gst | 2 | WALL FINISHING DETAILS |
| Vetrified | TILE | SOMANI / |
| Agl / | EQUIVALEN | T |
| Rs 28 Per | SQFT + GST | 3 |
| Kitchen Details | GLAZED | TILE |
| Somani / | AGL / | EQUIVALEN |
| T | RS 28 PER | SQFT + GST |
| 4 | BATHROOM FITTINGS | CERAMIC |
| Somani / | AGL / | EQUIVALEN |
| T | RS 22 PER | SQFT + GST |
| 5 | WOOD WORK ETC | NAWINDOW |
| Flush | DOOR | BHUTAN |
| Tuff / | TIMBER | LAND |
| Rs. 95 Per | SQFT + GST | 6 |
| Doors And Windos Frames | WINDOW | FLUSH |
| Door | BHUTAN | TUFF / |
| Timber | LAND | RS. 95 PER |
| Sqft + Gst | 7 | GLASS WORK |
| Na | 8 | ELECTRIC FITTINGS |
| Na | 9 | CONDUCTING AND WIRING DETAILS |
| Na | 10 | CUPBOARD DETAILS |
| Na | 11 | WATER STORAGE |
| Na | 12 | LIFT DETAILS |
| Na | 13 | EXTERNAL GLAZINGS |
| Na | 13.1 | WINDOWS/GLAZINGS |
| Na | 14 | DOORS |
| Na | 14.1 | MAIN DOORS |
| Na | 14.2 | INTERNAL DOORS |
| Na | 15 | AIR CONDITIONING |
| Na | 16 | ELECTRICAL FITTINGS |
| Na | 17 | CNG PIPE LINE |
| Na | 18 | PROVISION OF WIFI AND BROADBAND FACILITY |
| Na | 19 | EXTERNAL FINISHING/COLOUR SCHEME |
| Na | 20 | INTERNAL FINISHING |
| Na | SPECIFICATION UNIT WISE | 1 . LIVING/DINING/FOYER/FAMILY LOUNGE |
| 1 . 1 | FLOOR | NA |
| 1 . 2 | WALLS | NA |
| 1 . 3 | CEILING | NA |
| 2 . Master Bedroom/Dressroom | 2 . 1 | FLOOR |
| Na | 2 . 2 | WALLS |
| Na | 2 . 3 | CEILING |
| Na | 2 . 4 | MODULAR WARDROBES |
| Na | 3 . MASTER TOILET | 3 . 1 |
| Floor | NA | 3 . 2 |
| Walls | NA | 3 . 3 |
| Ceiling | NA | 3 . 4 |
| Counters | NA | 3 . 5 |
| Sanitary Ware/Cp Fittings | NA | 3 . 6 |
| Fitting/Fixtures | NA | 4 . BED ROOMS |
| 4 . 1 | FLOOR | NA |
| 4 . 2 | WALLS | NA |
| 4 . 3 | CEILING | NA |
| 4 . 4 | WARDROBES | NA |
| 5 . Toilet | 5 . 1 | FLOOR |
| Na | 5 . 2 | WALLS |
| Na | 5 . 3 | CEILING |
| Na | 5 . 4 | COUNTERS |
| Na | 5 . 5 | SANITARY WARE/CP FITTINGS |
| Na | 5 . 6 | FIXTURES |
| Na | 6 . KITCHEN | 6 . 1 |
| Floor | NA | 6 . 2 |
| Walls | NA | 6 . 3 |
| Ceiling | NA | 6 . 4 |
| Counters | NA | 6 . 5 |
| Fixtures | NA | 6 . 6 |
| Kitchen Appliances | NA | 7 . UTILITY ROOMS/UTILITY BALCONY/TOILET |
| 7 . 1 | FLOOR | NA |
| 7 . 2 | WALLS & CEILING | NA |
| 7 . 3 | TOILET | NA |
| 7 . 4 | BALCONY | NA |
| 8 . Sit-Outs | 8 . 1 | FLOOR |
| Na | 8 . 2 | WALLS & CEILING |
| Na | 8 . 3 | RAILINGS |
| Na | 8 . 4 | FIXTURES |
| Na | I hereby declare that the above information and particulars are based on record and are true to the | best of my knowledge and belief and nothing has been concealed. |
| Signature of the Applicant / Authorised Representative | Stamp _____________ | Date _____________ |
| List of Uploaded Documents | Sr. No. | Document Description |
| Date of Document Upload | View Document | 1 |
| In Case Of Plotted Colony, The Latest Layout Plan | 07-04-2023 | View Document |
| 2 | SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN | 07-04-2023 |
| View Document | 3 | A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS |
| 07-04-2023 | View Document | 4 |
| Zoning Plan | 07-04-2023 | View Document |
| 5 | DEMARCATION PLAN | 07-04-2023 |
| View Document | 6 | COPY OF LICENSE ALONG WITH SCHEDULE OF LAND |
| 07-04-2023 | View Document | 7 |
| Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record | 07-04-2023 | View Document |
| 8 | CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT | 07-04-2023 |
| View Document | 9 | NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT |
| 07-04-2023 | View Document | 10 |
| Declaration Supported By Affidavit Duly Signed By The Promoter To Be Enclosed. | 07-04-2023 | View Document |
| 11 | IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN | 07-04-2023 |
| View Document | 12 | CASH FLOW STATEMENT OF THE PROPOSED PROJECT |
| 07-04-2023 | View Document | I hereby declare that the above information and particulars are based on record and are true to the |
| best of my knowledge and belief and nothing has been concealed. | Signature of the Applicant / Authorised Representative | Stamp _____________ |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 4.38 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 2.48 Cr | Yet To Be Prepared |
| Storm Water Drainage | ₹ 84.52 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 48.3 lakh | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 3.98 Cr | Yet To Be Prepared |
| Street Lighting | ₹ 58.35 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 33.21 lakh | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 42.5 lakh | Yet To Be Prepared |
| Club House/Community Centre | ₹ 20.81 lakh | Yet To Be Prepared |
| Shopping Area | ₹ 20.81 lakh | Yet To Be Prepared |
| Renewable Energy System | ₹ 48.3 lakh | Yet To Be Prepared |
| Any Other | ₹ 86.48 lakh | Yet To Be Prepared |
| Electrical Sub Station | ₹ 1.28 Cr | Yet To Be Prepared |
| Rain Water Harvesting | ₹ 67.92 lakh | Yet To Be Prepared |
| Parking | ₹ 13.58 lakh | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Dtcp | Applied For But Yet To Receive | 5 Apr 2023 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Vetrified |
|---|
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Mahira Homes 88B?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.