6TH Floor, M3M Tee Point, North Block, Sector- 65,Gurugram
CIN
U70109HR2006PTC056114
Site address
Sector 114, Gurugram
Sector
Sector 114
Tehsil / District
Gurgaon / Gurugram
Layout plan approved
20 Feb 2023
Building plans approved
11 May 2023
Construction start (as filed)
1 Mar 2023
Completion (as filed)
30 Apr 2025
Application submitted
28 Mar 2023
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing fixed
Next hearingNot Required
Application submitted online
Notice sent to the promoter1ST Deficiency Notice
HearingExamination By AuthorityView order Proceedings
Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. The AR of the promoter has requested the Authority for 30 days times for submission of approved Architectural control sheet alongwith other deficiencies. The Authority allowed the time with the liberty to request for early hearing in case the approval from DTCP received before 30 days. The matter to come up on 15.05.2023.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. The AR of the promoter states that a reply has been submitted on 12.05.2023 in which the approval of architectural control sheet alongwith the plans has been attached. The architectural control sheet has been approved vide memo no. ZP-1745/JD(RD)/2023/14122 dated 11.05.2023. Further, for submission of approved service plan and estimates, a cheque no. 000804 dated 28.03.2023 amounting Rs 25 Lakhs as a security amount has been submitted and request for refund of amount of Rs 25 lakhs which was submitted vide cheque no. 000807 dated 28.03.2023 on account of submission of approved architectural control sheet. The Authority decided to grant the registration certificate subject to submission of approved service plan and estimates within 3 months and further subject to corrections in Online (A-H) form prior to issuance of registration certificate. The Authority further decides to refund the amount of Rs 25 lakhs which was submitted on account of approved architectural control sheet as the approval has already been submitted.
Registration grantedGGM/718/450/2023/62
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
2.481 acres
Total licensed area
2.481 acres
Licence
36 of 2023 dated 20.02.2023
FAR permissible / proposed
1.5 / 1.5
Estimated project cost
₹ 46.91 Cr
Cost of land
₹ 8.34 Cr
Infrastructure and other structures
₹ 16.74 Cr
EDC, taxes, levies and other costs
₹ 21.83 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
0.8684
35%
Construction Of Roads
1.002
40.4%
Green Belts
0.5586
22.5%
Electricity Sub-Station
0.017
0.7%
Stp
0.025
1%
Underground
0.011
0.4%
Plots 44 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
60.00
72
646
4
67.07
80
722
6
78.00
93
840
19
85.70
102
922
1
90.00
108
969
10
90.87
109
978
1
97.44
117
1,049
1
107.70
129
1,159
1
108.31
130
1,166
1
External services
Service
Provided by
Approval taken
Roads
GMDA-CONNECTED
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 6.12 Cr
As Per Project Report
Water Supply System
₹ 41.68 lakh
As Per Project Report
Storm Water Drainage
₹ 55.33 lakh
As Per Project Report
Electricity Supply System
₹ 91.72 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 32.46 lakh
As Per Project Report
Street Lighting
₹ 26.58 lakh
As Per Project Report
Security And Fire Fighting
₹ 6.64 lakh
As Per Project Report
Playgrounds And Parks
₹ 18 lakh
As Per Project Report
Any Other
₹ 1.25 Cr
As Per Project Report
Boundary Wall
₹ 61.44 lakh
As Per Project Report
Electrical Substation
₹ 79.48 lakh
As Per Project Report
Electrification Till Site
₹ 4.51 Cr
As Per Project Report
Underground Tank
₹ 18.61 lakh
As Per Project Report
Stp
₹ 33.07 lakh
As Per Project Report
Rain Water Harvesting
₹ 21.69 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Forest Noc
Already Been Obtained
28 Sep 2022
License
Already Been Obtained
20 Feb 2023
Aravalli Noc
Already Been Obtained
3 Feb 2023
Standard Design Approval
Already Been Obtained
11 May 2023
Layout Plan
Already Been Obtained
20 Feb 2023
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about M3M Xpressway 114?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.