Block A Sushant Lok- III, Sector-57 Gurugram Manesar Urban Complex
Sector
Sector 57
Tehsil / District
Wazirabad St / Gurugram
Layout plan approved
1 Dec 2022
Building plans approved
1 Dec 2022
Construction start (as filed)
1 Dec 2022
Completion (as filed)
31 Aug 2026
Application submitted
2 Dec 2022
Authority, hearings & orders
Current statusExtension Certificate Uploaded
Initial scrutinyFirst hearing fixed
Next hearingNot Required
Application submitted online
Notice sent to the promoterDeficiency notice
HearingExamination By AuthorityView order Proceedings
The matter to come up on 23.12.2022
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Sumeet, Engineer Executive Cum Planning Coordinator and Ms. Asha Chartered Accountant briefed about the facts of the case. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR), Sh. Bharat Vigmal(AR) and Sh. Ayush Gupta (AR) are present on behalf of the promoter. Approved as proposed.
Registration grantedGGM/651/383/2022/126
Registration valid till
Land, licence & cost
Land area of the project
3.16 acres
Total licensed area
3.16 acres
Licence
10 to 16 of 1996 dated 16.02.1996, 3 to 5 and 8 of 1999 dated 4.01.1999, 2 to 4 of 2000 dated 6.02.2000, 102 to 114 of 2004 dated 27.07.2004
FAR permissible / proposed
3.67 / 3.66
Estimated project cost
₹ 561.01 Cr
Cost of land
₹ 140.71 Cr
Cost of construction
₹ 237.03 Cr
Infrastructure and other structures
₹ 28.08 Cr
EDC, taxes, levies and other costs
₹ 155.18 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
1.8923
59.9%
Construction Of Roads
0.7631
24.1%
Any Other
0.5046
16%
Apartments 858 units
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
31,415.28
-
858
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
GMDA
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 3.32 Cr
As Per Project Report
Water Supply System
₹ 1.05 Cr
As Per Project Report
Storm Water Drainage
₹ 20.5 lakh
As Per Project Report
Electricity Supply System
₹ 2 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 45 lakh
As Per Project Report
Street Lighting
₹ 15 lakh
As Per Project Report
Security And Fire Fighting
₹ 1.72 Cr
As Per Project Report
Construction Of Circulation Road And Boundary Wall
₹ 9.46 lakh
As Per Project Report
Electrical Sub Station
₹ 2.87 Cr
As Per Project Report
Rain Water Harvesting
₹ 26 lakh
As Per Project Report
Electrification To Site
₹ 14.35 Cr
As Per Project Report
Stp
₹ 96 lakh
As Per Project Report
Parking
₹ 10.25 lakh
As Per Project Report
Water Tank
₹ 55 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Loi
Already Been Obtained
20 Dec 2021
Noc For Height Clearance
Already Been Obtained
29 Nov 2021
Environment Clearance
Already Been Obtained
25 Mar 2022
Building Plan Approval
Already Been Obtained
1 Dec 2022
Specifications (as filed)
Flooring Details Of Various Parts Of House
Bare R.c.c Slab,
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about M3M PARAGON57?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.