Registration validHRERA Gurugram

M3M Crown Phase 1

by Metro Education & Welfare Private Limited · Sector-111

RERA registration
GGM/687/419/2023/31
Registered on
2 Feb 2023
Valid till
31 Jan 2028
Project ID
RERA-GRG-1262-2023
Land area
15.994 acres
Apartments
1,332 in 11 towers
Completion (as filed)
31 Jan 2028
Estimated cost
₹ 2,306.75 Cr

RERA registration

Registration certificateGGM/687/419/2023/31, dated 2 Feb 2023
Registration valid till31 Jan 2028
Project IDRERA-GRG-1262-2023
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameM3M Crown Phase 1
PromoterMetro Education & Welfare Private Limited
Promoter’s registered office6TH Floor, M3M Tee Point North Block, Sector-65, Gurugram
CINU70100HR2010PTC086524
Site addressSector-111
SectorSector 111
Tehsil / DistrictGurgaon / Gurugram
Layout plan approved25 Jan 2023
Building plans approved25 Jan 2023
Construction start (as filed)25 Jan 2023
Completion (as filed)31 Jan 2028
Application submitted25 Jan 2023

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing fixed
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter By Hand
  1. Hearing Examination By Authority View order
    Proceedings

    The matter is adjourned to 02.02.2023.

  2. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AS) and Sh. Bharat Vigmal (AS) are present on behalf of the promoter. Approved as proposed.

  3. Registration granted GGM/687/419/2023/31
  1. Certificate uploaded RC Uploaded
  2. Registration valid till

Land, licence & cost

Land area of the project15.994 acres
Total licensed area11.602 acres
LicenceLicense No. 213 of 2022 dated 27-Dec-22 valid upto 26-Dec-27
FAR permissible / proposed3.6 / 2.92
Estimated project cost₹ 2,306.75 Cr
Cost of land₹ 792.47 Cr
Cost of construction₹ 984 Cr
Infrastructure and other structures₹ 71.46 Cr
EDC, taxes, levies and other costs₹ 458.83 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments6.6957.6%
Construction Of Roads2.8424.4%
Parks And Playgrounds2.0918%

Apartments 1,332 units · 11 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings145,041.19-1332

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsGMDANo
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 3.38 CrAs Per Project Report
Water Supply System₹ 72 lakhAs Per Project Report
Storm Water Drainage₹ 1.25 CrAs Per Project Report
Electricity Supply System₹ 5.9 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 2.5 CrAs Per Project Report
Street Lighting₹ 76 lakhAs Per Project Report
Security And Fire Fighting₹ 1.92 CrAs Per Project Report
Any Other₹ 6.97 CrAs Per Project Report
Stp₹ 2.63 CrAs Per Project Report
Parking₹ 52.59 lakhAs Per Project Report
Rain Water Harvesting₹ 1.25 CrAs Per Project Report
Electric Sub Station₹ 6.22 CrAs Per Project Report
Underground Water Tank₹ 1.35 CrAs Per Project Report
Boundary Wall₹ 2.37 CrAs Per Project Report
Switching Station₹ 7.03 CrAs Per Project Report
Hardscape And Softscape₹ 25.39 CrAs Per Project Report
Main Entrance₹ 1.29 CrAs Per Project Report
Boundary Wall₹ 2.37 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
LicenseAlready Been Obtained27 Dec 2022
Environment ClearanceAlready Been Obtained10 May 2021
Forest NocAlready Been Obtained7 Aug 2018
Aravali NocAlready Been Obtained27 Aug 2018

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tiles/Laminatedwooden Floor/Ceramic Tile
Wall Finishing DetailsPlaster With Obd
Doors And Windos FramesExternal Aluminium With Glassinternal – Wooden
Glass WorkOnly External Door/Window
Electric FittingsAs Per Approved Make
Conducting And Wiring DetailsAs Per Approved Make
Water StorageAs Per Norms
Lift DetailsLifts As Per Building Plans
External GlazingsGlass With Aluminium Framingsliding
Windows/GlazingsGlass With Aluminium Framingsliding
Main DoorsHard Wood Door Frame Withflush Door /Laminate
Internal DoorsHard Wood Door Frame Withflush Door /Laminate
Electrical FittingsAs Per Approved Make
Cng Pipe LineService Provider
External Finishing/Colour SchemeWater Proof Paint

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about M3M Crown Phase 1?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.