Registration validHRERA GurugramOC / CC on record

M3M Capital

by Union Buildmart Private Limited · Sector -113, Gurugram Manesar Urban Complex, Gurugram, Haryana.

RERA registration
GGM/531/263/2022/06
Registered on
2 Feb 2022
Valid till
29 Jun 2027
Project ID
RERA-GRG-1006-2022
Land area
4.856 acres
Apartments
644 in 1 tower
Completion (as filed)
30 Jun 2026
Estimated cost
₹ 599.66 Cr

RERA registration

Registration certificateGGM/531/263/2022/06, dated 2 Feb 2022
Registration valid till29 Jun 2027
Project IDRERA-GRG-1006-2022
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameM3M Capital
PromoterUnion Buildmart Private Limited
Promoter’s registered officeUnit No. Sb/C/5L/Office/008, M3M Urbana Sector-67 Gurugram Manesar Urban Complex, Gurugram, Gurgaon, Hr 122102 In
CINU70100HR2012PTC089615
Site addressSector -113, Gurugram Manesar Urban Complex, Gurugram, Haryana.
SectorSector 113
Tehsil / DistrictGurgaon / Gurugram
Layout plan approved18 Jan 2022
Building plans approved18 Jan 2022
Construction start (as filed)18 Jan 2022
Completion (as filed)30 Jun 2026
Application submitted20 Jan 2022

Authority, hearings & orders

Current statusExtension Certificate Uploaded
Initial scrutinyfirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter Dispatched to AR by hand
  1. Hearing Examination By Authority
    Proceedings

    The matter is adjourned to 02.02.2022

  2. Hearing Approved And Ready For Certificate Issuing Process
    Proceedings

    Proceedings dated 02.02.2022 Sh. Vineet Maheshwari (Legal Head), Sh. Abhijeet Singh (COO) and Sh. Parijat Pandey (Deputy Manager, Strategy) is present on behalf of the promoter. The promoter has submitted the reply on 31.01.2022 with reference to deficiency notice conveyed to the promoter vide notice no. HARERA/GGM/RPIN/426 dated 24.01.2022. the reply of the promoter was scrutinized and the deficiencies which still needs to be rectified by the promoter are correction in online DPI, correction in REP-I (A-H), allottees related documents, revalidation of AAI NOC, approved fire scheme NOC and approved service estimates and plans. However, the promoter has applied for these approvals in the concerned department and final approval is awaited. The authority decides to grant the registration subject to the submission of bank guarantee/cheque of Rs. 25 lakhs on account of approved fire scheme and 25 lakhs on account of approved service plans and estimates within seven days from the grant of registration. This bank guarantee shall be forfeited in case the approved fire scheme and approved service plans and estimates are not submitted within three months from the date of grant of registration.

  3. Registration granted GGM/531/263/2022/06
  1. Registration valid till

Land, licence & cost

Land area of the project4.856 acres
Total licensed area15.031 acres
Licence106 of 2021 dated 16.12.2021
FAR permissible / proposed64033.087 / 1.25
Estimated project cost₹ 599.66 Cr
Cost of land₹ 122.74 Cr
Cost of construction₹ 247.8 Cr
Infrastructure and other structures₹ 22.66 Cr
EDC, taxes, levies and other costs₹ 206.46 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments0.66713.7%
Construction Of Roads1.26226%
Parks And Playgrounds2.24846.3%
Open0.67914%

Apartments 644 units · 1 tower

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings11,147.61-136
Apartment/Shops/Other Buildings11,819.48-136
Apartment/Shops/Other Buildings11,718.03-144
Apartment/Shops/Other Buildings11,718.03-144
Apartment/Shops/Other Buildings6,830.42-84

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsGMDA-CONNECTEDYes
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.05 CrSubmitted To Town & Country Planning
Water Supply System₹ 3 CrSubmitted To Town & Country Planning
Storm Water Drainage₹ 1.1 CrSubmitted To Town & Country Planning
Electricity Supply System₹ 48.38 lakhAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 1.4 CrSubmitted To Town & Country Planning
Street Lighting₹ 57.68 lakhSubmitted To Town & Country Planning
Security And Fire Fighting₹ 6.46 CrAs Per Project Report
Playgrounds And Parks₹ 8.36 lakhSubmitted To Town & Country Planning
Renewable Energy System₹ 49.48 lakhAs Per Project Report
Parking₹ 11.98 lakhAs Per Project Report
Stp₹ 48.38 lakhAs Per Project Report
Underground Tank₹ 41.94 lakhAs Per Project Report
Rain Water Harvesting₹ 6.05 lakhAs Per Project Report
Electrical Sub Station₹ 5.36 CrAs Per Project Report
Boundary Wall₹ 55.86 lakhAs Per Project Report

Statutory approvals

ApprovalStatusDate
LicenceAlready Been Obtained16 Dec 2021
Building Plan ApprovalAlready Been Obtained18 Jan 2022
Forest NocAlready Been Obtained7 Aug 2018
Aravali NocAlready Been Obtained27 Aug 2018

Specifications (as filed)

Flooring Details Of Various Parts Of HouseVitrified Tiles/Laminated Wooden Floor/Ceramic Tile
Wall Finishing DetailsPlaster With Obd
Doors And Windos FramesExternal Aluminium With Glass

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about M3M Capital?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.