Land, licence & cost
Land area of the project
8.526 acres
Total licensed area
8.526 acres
Licence
123 of 2019 dated 17.09.2019
FAR permissible / proposed
0 / 0
Estimated project cost
₹ 147.76 Cr
Cost of land
₹ 59.49 Cr
Infrastructure and other structures
₹ 10.16 Cr
EDC, taxes, levies and other costs
₹ 78.11 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
2.984
35%
Construction Of Roads
2.8928
33.9%
Parks And Playgrounds
1.8573
21.8%
Vehicle Parkings
0.5977
7%
Electricity Sub-Station
0.1092
1.3%
Sewage And Solid Waste Treatment Facility
0.004
0%
Any Other
0.036
0.4%
Rain
0.0277
0.3%
Utility
0.0173
0.2%
Plots 105 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
48.17
58
518
6
84.61
101
911
11
95.70
114
1,030
4
96.00
115
1,033
19
108.00
129
1,163
34
108.12
129
1,164
1
120.00
144
1,292
19
159.16
190
1,713
2
180.38
216
1,942
2
201.60
241
2,170
2
223.44
267
2,405
2
347.62
416
3,742
2
365.22
437
3,931
1
External services
Service
Provided by
Approval taken
Roads
GMDA/ HSVP
No
Water Supply
GMDA/ HSVP
No
Electricity
DHBVN
No
Sewage Disposal
GMDA/ HSVP
No
Storm Water Drainage
GMDA/ HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 91.49 lakh
Yet To Be Prepared
Water Supply System
₹ 17.46 lakh
Yet To Be Prepared
Storm Water Drainage
₹ 20.65 lakh
Yet To Be Prepared
Electricity Supply System
₹ 59.21 lakh
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 15.47 lakh
Yet To Be Prepared
Street Lighting
₹ 4.42 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 4.93 lakh
Yet To Be Prepared
Playgrounds And Parks
₹ 60.62 lakh
Yet To Be Prepared
Parking
₹ 11.66 lakh
Yet To Be Prepared
Rain Water Harvesting
₹ 19.97 lakh
Yet To Be Prepared
Electrical Sub Station
₹ 81.58 lakh
Yet To Be Prepared
Overhead Establishments Running And Maintenance
₹ 39.82 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
Licence
Already Been Obtained
17 Sep 2019
Forest Noc
Already Been Obtained
7 Aug 2018
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about M3M 113 Market?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.