Registration validHRERA Gurugram

Lushlands

by Adani Infrastructure And Developers Private Limited · Village Gwal Pahari, Sector 02, Gurugram

RERA registration
GGM/837/569/2024/64
Registered on
14 Jun 2024
Valid till
31 Mar 2029
Project ID
RERA-GRG-1526-2024
Land area
8.349 acres
Estimated cost
₹ 906.08 Cr

RERA registration

Registration certificateGGM/837/569/2024/64, dated 14 Jun 2024
Registration valid till31 Mar 2029
Project IDRERA-GRG-1526-2024
AuthorityHRERA Gurugram
Project type (as filed)Ongoing
Project nameLushlands
PromoterAdani Infrastructure And Developers Private Limited
Promoter’s registered officePlot No. 83, Adani House, Sector 32, Gurugram(Hr)- 122001
CINU45201GJ2006PTC066449
Site addressVillage Gwal Pahari, Sector 02, Gurugram
SectorSector 02
Tehsil / DistrictWazirabad St / Gurugram
Layout plan approved16 May 2024
Building plans approved16 May 2024
Application submitted24 Jan 2024

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Hearing Examination By Authority View order
    Proceedings

    Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. The application submitted by the promoter has been scrutinized by the concerned official, but the deficiency notice has not been dispatched till date. Therefore, in view of the same the matter is adjourned, and the concerned official is directed to dispatch the notice. The next date of hearing will be conveyed after submission of reply of deficiencies.

  1. Notice sent to the promoter By Email
  2. Hearing Adjournment View order
    Proceedings

    Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case.Sh. Rajesh Jain (General Manager), Sh. Dheeraj Garg (Dy. Manager) and Sh. Praveen Kumar (AR) are present on behalf of the promoter. The AR states that phasing of the project is under approval with DTCP and sanctioned copy will be submitted within one week as the present application is only in respect of Phase-I. Further, the project has been awarded through NCLT and consent of 23 unique allottees out of 30 unique allottees have been obtained and submitted in the Authority and one week public notice to be published in two newspapers (1 Hindi and 1 English) for inviting objections, if any.The matter to come up on 10.06.2024.

  3. Hearing Approved And Ready For Certificate Issuing Process View order
    Proceedings

    Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Rajesh Jain (AR), Sh. Dheeraj Garg (AR) and Sh. Praveen Kumar (AR) are present on behalf of the promoter. The AR of the promoter stated that the approved service plan and estimates, Phasing letter from DTCP alongwith the other deficiencies has been submitted on 07.06.2024. A public notice w.r.t the revision in building plans in respect to the project for inviting objections, if any has been published on 04.06.2024 in Hindustan Times (Hindi) and Hindustan (Hindi).  No objection has been received regarding revision in the building plans in the project namely “Lushlands” till date. It is noticed that the project was already registered vide Registration No. 230 of 2017 dated 19.09.2017 (Monde-De-Provence, Phase-1, Tower B & D) and 266 of 2017 dated 09.10.2017 (Monde-De-Provence, Phase-II, Tower C). The CIRP proceeding u/s 7 of IBC was commenced against the erstwhile promoter of the project and a resolution plan was submitted by the AIDPL. The member of CoC had approved the resolution plan submitted by AIDPL and finally, the resolution plan was approved by Hon’ble NCLT, Delhi on 30.05.2022 and AIDPL was declared as successful bidder and project was assigned to it. The promoter has obtained the Change of Developer from DTCP, Haryana vide memo no. LC-2604-Vol-II/JE(RK)/2024/14388-94 dated 15.05.2024. The late fee be recalculated from 01.06.2022 as the promoter i.e., Adani Infrastructure and Developers Pvt. Ltd. got project through NCLT on 30.05.2022 and has applied for registration on 25.01.2024 and the excess fee, if any be returned. Approved as proposed subject to submission of BG /DD of Rs 25 lakhs for submission of Fire scheme approval within 3 months from the grant of registration and office to examine the reply dated 07.06.2024 and ensure necessary correction in form A to H and DPI.    

  1. Registration granted GGM/837/569/2024/64
  2. Certificate uploaded RC Uploaded
  3. Registration valid till

Land, licence & cost

Land area of the project8.349 acres
Total licensed area12.356 acres
Licence98 of 2011
FAR permissible / proposed1.75 / 1.75
Estimated project cost₹ 906.08 Cr
Cost of land₹ 46.6 Cr
Cost of construction₹ 608.73 Cr
Infrastructure and other structures₹ 42.95 Cr
EDC, taxes, levies and other costs₹ 207.8 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments1.192414.3%
Construction Of Roads112%
Parks And Playgrounds2.091325%
Vehicle Parkings0.56%
Club House0.39064.7%
Sewage And Solid Waste Treatment Facility1.474817.7%
Watersupplysystem0.56%
Stormwaterdrainage0.56%
Electricitysupplysystem0.22.4%
Securityandfirefighting0.22.4%
Sportsblock0.33.6%

External services

ServiceProvided byApproval taken
RoadsGMDAYes
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 3.54 CrAs Per Project Report
Water Supply System₹ 59.94 lakhAs Per Project Report
Storm Water Drainage₹ 1.11 CrAs Per Project Report
Electricity Supply System₹ 1.68 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 60.23 lakhAs Per Project Report
Street Lighting₹ 41.68 lakhAs Per Project Report
Security And Fire Fighting₹ 11.55 lakhAs Per Project Report
Playgrounds And Parks₹ 1.54 CrAs Per Project Report
Club House/Community Centre₹ 17.7 CrAs Per Project Report
Parking₹ 10.97 lakhAs Per Project Report
Stp₹ 3.18 CrAs Per Project Report
Underground Water Tank₹ 1.96 CrAs Per Project Report
Rain Water Harvesting₹ 34.64 lakhAs Per Project Report
Electric Substation₹ 2.39 CrAs Per Project Report
Cnstruction Of Circulation Road₹ 6.16 CrAs Per Project Report
Electrification₹ 1.5 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
LicenseAlready Been Obtained11 Nov 2011
ZoningAlready Been Obtained11 Nov 2011

Specifications (as filed)

Flooring Details Of Various Parts Of HouseMarble, Laminated Flooring And Wooden Floor/Tiles As Applicable
Wall Finishing DetailsEmulsion Paint
Kitchen DetailsGranite Counter And Modular Kitchen
Bathroom FittingsStandard Make
Doors And Windos FramesLaminated Flush Doors
Electric FittingsIsi Standard
Conducting And Wiring DetailsIsi Standard
Water StorageIf Applicable
Lift DetailsAs Per Applicable Norms
External GlazingsAluminium Frames With Toughned Glass
Windows/GlazingsAluminium Frames With Toughned Glass
DoorsLaminated Flush Doors
Main DoorsLaminated Flush Doors
Internal DoorsLaminated Flush Doors
Electrical FittingsIsi Standards
External Finishing/Colour SchemePaint Finish
Internal FinishingPaint Finish

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Lushlands?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.