RERA applied, not grantedHRERA Panchkula

Landways Delnia Villas Phase II

by Landways Developers India LLP · Sector 36

RERA registration
Applied, not granted yet
Applied on
16 Mar 2025
Application status
In process
Project ID
RERA-PKL-1584-2024
Land area
3.268 acres
Plots
56
Completion (as filed)
10 Apr 2027
Estimated cost
₹ 7 Cr

This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.

RERA registration

Registration certificateNot issued yet: the application is being processed by HRERA Panchkula
Project IDRERA-PKL-1584-2024
AuthorityHRERA Panchkula
Project type (as filed)New
Project nameLandways Delnia Villas Phase II
PromoterLandways Developers India LLP
Promoter’s registered officeR3 First Floor Ruhil Residency Sector 3 Bahadurgarh
Site addressSector 36
SectorSector 36
Tehsil / DistrictBahadurgarh / Jhajjar
Layout plan approved6 Dec 2024
Building plans approved6 Dec 2024
Construction start (as filed)15 Apr 2025
Completion (as filed)10 Apr 2027
Application submitted16 Mar 2025

Authority, hearings & orders

Current statusStatus not given
Next hearingNot Required
  1. Application submitted online

Land, licence & cost

Land area of the project3.268 acres
Total licensed area8.588 acres
Licence176of2024
Estimated project cost₹ 7 Cr
Cost of land₹ 6.5 Cr
Infrastructure and other structures₹ 6.5 Cr
EDC, taxes, levies and other costs₹ 1.83 Cr

How the land will be used

UseArea (as filed)Share
Plots To Be Sold5696.6%
Construction Of Roads0.591%
Pavements0.0920.2%
Parks And Playgrounds0.2540.4%
Electricity Sub-Station0.0010%
Club House0.8581.5%
Sewage And Solid Waste Treatment Facility0.1480.3%

Plots 56 plots

Plot size (sq m)Sq ydSq ftPlots
5,314.006,35557,19956

External services

ServiceProvided byApproval taken
RoadsSELFNo
Water SupplyHUDANo
ElectricityDHBVNNo
Sewage DisposalHUDANo
Storm Water DrainageHUDANo

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.25 CrYet To Be Prepared
Water Supply System₹ 40 lakhYet To Be Prepared
Storm Water Drainage₹ 25 lakhYet To Be Prepared
Electricity Supply System₹ 70 lakhYet To Be Prepared
Sewage Treatment & Garbage Disposal₹ 70 lakhYet To Be Prepared
Street Lighting₹ 40 lakhYet To Be Prepared
Security And Fire Fighting₹ 25 lakhYet To Be Prepared
Playgrounds And Parks₹ 30 lakhYet To Be Prepared
Club House/Community Centre₹ 50 lakhYet To Be Prepared
Shopping Area₹ 25 lakhYet To Be Prepared
Any Other₹ 50 lakhYet To Be Prepared

Statutory approvals

ApprovalStatusDate
NoYet To File For Approval1 Mar 2024

Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Landways Delnia Villas Phase II?

This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.