W4D, 204/5, Keshav Kunj, Cariappa Marg, Sainik Farms, New Delhi
CIN
U45400DL1990PLC042200
Site address
Sector 14, Sohna, Gurugram
Sector
Sector 14
Tehsil / District
Nuh / Nuh
Layout plan approved
7 Apr 2015
Building plans approved
10 Jun 2015
Application submitted
7 Feb 2020
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Next hearingNot Required
Registration granted21 OF 2017
Application submitted online
Application received by HRERA Panchkula
Registration valid till
Land, licence & cost
Land area of the project
10 acres
Total licensed area
10 acres
Licence
115 of 2014 dated 20.08.2014
FAR permissible / proposed
2.25 / 2.248
Estimated project cost
₹ 211.89 Cr
Cost of land
₹ 37 Cr
Cost of construction
₹ 120.53 Cr
EDC, taxes, levies and other costs
₹ 54.36 Cr
How the land will be used
Use
Area (as filed)
Share
Land Area To Be Used For Construction Of Apartments
7,475.409
12.1%
Construction Of Roads
10,327.112
16.8%
Pavements
12,942.471
21%
Parks And Playgrounds
6,346.921
10.3%
Green Belts
2,215.897
3.6%
Vehicle Parkings
21,410.075
34.7%
Electricity Sub-Station
722
1.2%
Area To Be Left For Transferring To The Government For Community Services
187.84
0.3%
External services
Service
Provided by
Approval taken
Roads
No
WATER SUPPLY
Yes
ELECTRICITY
Yes
Sewage Disposal
No
STORM WATER DRAINAGE
No
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
326.61
Submitted To Town & Country Planning
2
WATER SUPPLY SYSTEM
247.66
SUBMITTED TO TOWN & COUNTRY PLANNING
3
Storm Water Drainage
97.60
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
0
Yet To Be Prepared
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
200
SUBMITTED TO TOWN & COUNTRY PLANNING
6
Street Lighting
38.37
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
12.42
Submitted To Town & Country Planning
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
Club House/Community Centre
0
YET TO BE PREPARED
10
SHOPPING AREA
0
Yet To Be Prepared
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
School
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
Yet To Be Prepared
14
ANY OTHER
0
YET TO BE PREPARED
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
07-04-2015
(date)
6. Date of approval of Building Plans
10-06-2015
(date)
(i) Details of the plots/apartments in the project:
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type 1 BHK TYPE 1
38.496
676
26023.296
579
97
4
2
APARTMENT/SHOPS/OTHER BUILDINGS Type 1 BHK TYPE 2
32.093
264
8472.552
252
12
2
3
APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK TYPE 1
58.608
80
4688.64
77
3
1
4
APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK TYPE 2
59.514
40
2380.56
38
2
1
5
APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK TYPE 3
42.022
584
24540.848
579
5
6
Total
1644
66105.896
1525
119
14
(ii) Apartments/Shops/Other Buildings:-
(a) Status of construction activities in respect of sold/booked apartments.
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
(b) Time schedule of completion of already booked apartments:
Start Date
15-11-2015
Earlier date of completion
31-07-2019
Revised date of completion
09-03-2020
(c) Time schedule for development of infrastructure:
Start Date
15-11-2015
Percentage completion Upto the
date of application
0
Projected date of completion
09-03-2020
(d) Provide further details in the proforma REP-I Part-C-X.
(e) Plan of action for completing the Project along with requisite infrastructure.
(iii) Status in respect of plotted colony:-
(a)
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
(b) Schedule for development of Infrastructure:
Start Date
15-11-2015
Percentage completion
0
Projected date of completion
09-03-2020
(c) Provide further details in the proforma REP-I Part-C-X.
(d) Schedule of completing the project and handing over possession of the plots.
(iv) Vehicle parkings details of the project-
a) Underground parking
0
b) Stilt parking
389
c) Covered parking
0
d) Open parking
454
e) Independent garages
0
(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
6804
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (
)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - C-X
1.Financial information:
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
1644
ii. No. of Flats/ Apartments booked
1525
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
25435.50 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
13020.74 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
12414.75 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
1820.37 Lakhs
vii. Amount invested in the project upto the date of application
6804 Lakhs
Land cost (If any)
2809 Lakhs
Apartments
2618 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
1377 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
14385 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
5500 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
900 Lakhs
2.Additional information:
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. Internal Roads And Pavements
326.61
0
II. Water Supply System
247.66
0
III. Storm Water Drainage
97.60
0
IV. Electricity Supply System
0
0
V. Sewage Treatment & Garbage Disposal
334.9
0
Vi. Club House/Community Centre
0
0
Vii. School
0
0
Viii. Any Other
0
0
Ix. Solid Waste Collection & Mgmt System
200
0
X. Clubhouse
0
0
Xi. Neighbourhood Shopping
0
0
Xii. Green Areas,Parks,Playgrounds Etc.
0
0
Xiii. Covered Parking
0
0
Xiv. Open Parking
0
0
Xv. Garages
0
0
Xvi. Security System
12.42
0
Xvii. Other Facilities As Per Project Report
0
0
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
Yes
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
Yes Bank Limited, Chanakyapuri, New Delhi
Bank Account number
000380200010108
IFSC code
YESB0000003
MICR code
110532002
Branch code
000003
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 3.27 Cr
Submitted To Town & Country Planning
Water Supply System
₹ 2.48 Cr
Submitted To Town & Country Planning
Storm Water Drainage
₹ 97.6 lakh
Submitted To Town & Country Planning
Sewage Treatment & Garbage Disposal
₹ 2 Cr
Submitted To Town & Country Planning
Street Lighting
₹ 38.37 lakh
Submitted To Town & Country Planning
Security And Fire Fighting
₹ 12.42 lakh
Submitted To Town & Country Planning
Statutory approvals
Approval
Status
Date
License No. 115 Of 2014
Already Been Obtained
20 Aug 2014
Building Plan
Already Been Obtained
10 Jun 2015
Environmental Clearance
Already Been Obtained
9 Mar 2015
Consent To Establish
Already Been Obtained
29 Aug 2017
Airport Height Clearance Noc
Already Been Obtained
15 Oct 2014
HUDA Construction Noc
Already Been Obtained
4 Nov 2014
Power Assurance
Already Been Obtained
27 Oct 2014
HUDA Water Noc
Already Been Obtained
7 Oct 2014
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Krishana Housing Scheme?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.