Klj Greens - Tower B-8, B-9 & B-10
by M/S Klj Developers Pvt. Ltd. · Klj Greens, Pocket B, Klj Group Housing Colony, Village Neemka, Sector-77
- RERA registration
- Applied, not granted yet
- Applied on
- 17 Oct 2023
- Application status
- Withdrawn/Rejected
- Project ID
- RERA-PKL-1353-2023
- Apartments
- 162 in 3 towers
- Completion (as filed)
- 31 Dec 2033
- Estimated cost
- ₹ 106.9 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
| Registration certificate | Not issued yet: the application is being processed by HRERA Panchkula |
|---|---|
| Project ID | RERA-PKL-1353-2023 |
| Authority | HRERA Panchkula |
| Project type (as filed) | New |
| Project name | Klj Greens - Tower B-8, B-9 & B-10 |
| Promoter | M/S Klj Developers Pvt. Ltd. |
| Promoter’s registered office | Klj House, 5TH Floor, 8A Shivaji Marg, Najafgarh Road, New Delhi - 110015 |
| CIN | U45201DL2006PTC145296 |
| Site address | Klj Greens, Pocket B, Klj Group Housing Colony, Village Neemka, Sector-77 |
| Sector | Sector 77 |
| Tehsil / District | Tigaon St / Faridabad |
| Layout plan approved | 4 Dec 2013 |
| Building plans approved | 30 Mar 2021 |
| Construction start (as filed) | 1 Nov 2023 |
| Completion (as filed) | 31 Dec 2033 |
| Application submitted | 17 Oct 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Panchkula
-
Hearing
Examination By Authority View order
Proceedings
ADJOURNED TO 08.01.2024
-
Hearing
Adjournment View order
Proceedings
Adjourned to 22.01.2024
-
Hearing
Adjournment View order
Proceedings
LISTED FOR 21-02-2024
-
Hearing
Adjournment View order
Proceedings
Adjourned to 13-03-2024
-
Hearing
Withdrawn/Rejected View order
Proceedings
DIS[POSED OF AS WITHDRAWN. The Authority accepts the request of the promoter to withdraw the present application with the directions to apply afresh application as per the approved phasing plan.
Land, licence & cost
| Licence | LICENSE NO. 3-9 OF 2007 DATED 02.01.2007 VALID UPTO 01.01.2025 AND LICENSE NO 157 OF 2008 DATED 08.08.2008 VALID UPTO 08.08.2025 |
|---|---|
| FAR permissible / proposed | 1.75 / 1.74 |
| Estimated project cost | ₹ 106.9 Cr |
| Cost of land | ₹ 2.61 Cr |
| Cost of construction | ₹ 75.88 Cr |
| Infrastructure and other structures | ₹ 0.51 Cr |
| EDC, taxes, levies and other costs | ₹ 6.69 Cr |
How the land will be used
| Use | Area (as filed) | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 1,804.08 | 28.7% |
| Construction Of Roads | 3,052.36 | 48.5% |
| Pavements | 1,434.47 | 22.8% |
Apartments 162 units · 3 towers
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 89.74 | 966 | 78 |
| Apartment/Shops/Other Buildings | 88.72 | 955 | 84 |
Areas are as filed with HRERA.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HSVP | Yes |
| Water Supply | HSVP | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | HSVP | Yes |
| Storm Water Drainage | HSVP | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 23.31 lakh | As Per Project Report |
| Water Supply System | ₹ 4.24 lakh | As Per Project Report |
| Electricity Supply System | ₹ 9.79 lakh | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 11.97 lakh | As Per Project Report |
| Renewable Energy System | ₹ 1.44 lakh | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License No 3-9 Of 2007 | Already Been Obtained | 2 Jan 2007 |
| License No 157 Of 2008 | Already Been Obtained | 8 Aug 2008 |
| Forest Noc | Already Been Obtained | 17 Jan 2013 |
| Airports Authority Of India | Already Been Obtained | 9 Apr 2018 |
| Environmental Clearance | Already Been Obtained | 12 Sep 2023 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Drg/Dining - Vitrified Tiles |
|---|
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Klj Greens - Tower B-8, B-9 & B-10?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.