Land area
8.974 acres
Estimated cost
₹ 393.07 Cr

RERA registration

Registration certificate97 OF 2017, dated 24 Aug 2017
Registration valid till30 Jun 2021
Project IDRERA-GRG-486-2019
AuthorityHRERA Gurugram (Interim Rera)
Project type (as filed)Ongoing
Project nameHill View Project (Tower 1 To 8)
PromoterSupertech Limited
Promoter’s registered office1114, Hemkunt Chamber 89, Nehru Place, New Delhi-110019
CINU74899DL1995PLC074422
Site addressSector-2, Sohna
SectorSector 2
Tehsil / DistrictSohna / Gurugram
Layout plan approved23 Jan 2015
Building plans approved23 Jan 2015
Application submitted30 Dec 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted 97 OF 2017
  2. Application submitted online
  3. Application received by HRERA Gurugram
  1. Registration valid till

Land, licence & cost

Land area of the project8.974 acres
Total licensed area100.369 acres
Licence124 of 2014
FAR permissible / proposed1.75 / 1.75
Estimated project cost₹ 393.07 Cr
Cost of land₹ 44.77 Cr
Cost of construction₹ 156.36 Cr
Infrastructure and other structures₹ 8.3 Cr
EDC, taxes, levies and other costs₹ 183.64 Cr

How the land will be used

UseAcresShare
Land Area To Be Used For Construction Of Apartments2.78231%
Construction Of Roads2.83231.6%
Parks And Playgrounds1.07712%
Vehicle Parkings1.13112.6%
Club House0.1141.3%
Any Other1.03811.6%

External services

ServiceProvided byApproval taken
RoadsGMDANo
Water SupplyGMDAYes
ElectricityDHBVNYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.25 CrAs Per Project Report
Water Supply System₹ 66 lakhAs Per Project Report
Storm Water Drainage₹ 25 lakhAs Per Project Report
Electricity Supply System₹ 2.08 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 2.08 CrAs Per Project Report
Street Lighting₹ 17 lakhAs Per Project Report
Security And Fire Fighting₹ 42 lakhAs Per Project Report
Playgrounds And Parks₹ 25 lakhAs Per Project Report
Any Other₹ 1.14 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
License ApprovalAlready Been Obtained23 Aug 2014
Zoning PlanAlready Been Obtained18 Dec 2014
Building PlanAlready Been Obtained1 Jan 2015
Environment ClearanceAlready Been Obtained15 Mar 2016
Height ClearanceAlready Been Obtained17 Feb 2016
Fire SchemeAlready Been Obtained11 Mar 2016

Specifications (as filed)

Flooring Details Of Various Parts Of HouseAs Per Sales Browser
Wall Finishing DetailsCement Plastic With Pop With Plastic Emulsion Paint Or Texture

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Hill View Project (Tower 1 To 8)?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.