Project ID
RERA-GRG-385-2019
Estimated cost
₹ 207.79 Cr

RERA registration

Registration certificate222 OF 2017, dated 18 Sep 2017
Registration valid till30 Jun 2020
Project IDRERA-GRG-385-2019
AuthorityHRERA Gurugram (Interim Rera)
Project type (as filed)Ongoing
Project nameGurgaon Spectrum Centre (Phase-1) ( Commercial Project)
PromoterBurman Estate Private Limited
Promoter’s registered office4TH Floor, Punjabi Bhawan, 10 Rouse Avenue New Delhi 110002
CINU70109DL2007PTC171515
Site addressSector 82 A Gurugram
SectorSector 82A
Tehsil / DistrictGurgaon / Gurugram
Layout plan approved31 Aug 2015
Building plans approved4 Nov 2015
Application submitted7 Dec 2019

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted 222 OF 2017
  2. Application submitted online
  3. Application received by HRERA Gurugram
  1. Registration valid till

Land, licence & cost

Licence135 of 2008(27-06-2020)
FAR permissible / proposed30129 / 1.75
Estimated project cost₹ 207.79 Cr
Cost of land₹ 47.28 Cr
Cost of construction₹ 120.39 Cr
Infrastructure and other structures₹ 14.4 Cr
EDC, taxes, levies and other costs₹ 25.72 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments5,88032.7%
Construction Of Roads2,00011.1%
Pavements6103.4%
Green Belts1,1006.1%
Vehicle Parkings9885.5%
Electricity Sub-Station4002.2%
Sewage And Solid Waste Treatment Facility1901.1%
Area To Be Left For Transferring To The Government For Community Services6753.8%
Any Other6,11434%

External services

ServiceProvided byApproval taken
RoadsDTCPYes
Water SupplyHUDAYes
ElectricityDHBVNYes
Sewage DisposalHUDAYes
Storm Water DrainageHUDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 2.2 CrAs Per Project Report
Water Supply System₹ 2.6 CrAs Per Project Report
Storm Water Drainage₹ 1.65 CrAs Per Project Report
Electricity Supply System₹ 5.65 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 65 lakhAs Per Project Report
Playgrounds And Parks₹ 1.65 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
Airport AuthorityAlready Been Obtained14 Jan 2016
Development Building PlanAlready Been Obtained4 Nov 2015
Fire Fighting SchemeAlready Been Obtained18 Mar 2016
Environmental Clearence To Establish Consent To OperateAlready Been Obtained23 Aug 2016
Water Load ApprovalAlready Been Obtained19 Feb 2016
Mining ApprovalAlready Been Obtained13 Jul 2016
Load Sanction DemandAlready Been Obtained10 Feb 2016
Plot LicenseAlready Been Obtained
Zioning PlanAlready Been Obtained31 Aug 2015
Building PlanAlready Been Obtained4 Nov 2015

Specifications (as filed)

Flooring Details Of Various Parts Of HouseTiles, Stone, Ips
Wall Finishing DetailsPop, Paint, Stone
Kitchen DetailsKota Stone, Antiskide Tiles
Bathroom FittingsCp Sanitary White Fixture
Wood Work EtcPly, Natural Wood, Polish Mica
Doors And Windos FramesNatural Wood, Flush Doors
Glass WorkToughened Glass
Electric FittingsDown Lights Led, Batten Led, Led Strip
Conducting And Wiring DetailsPvc Conduit, Ms Conduit, Frls Wires
Cupboard DetailsPly Board, Laminate, Drawers
Water StorageRcc Tanks, Overhead Tanks
Lift DetailsPassenger Lifts, Sscage 8 Nos
External GlazingsDgu, Window Openable Aluminium Windows
Windows/GlazingsAluminium Windows, Sgv, Dgv
DoorsFire Doors, Flush Doors
Main Doors55 Mm Flush Doors
Internal Doors42 Mm Flush Doors
Air ConditioningSplit Units, Dsv, Cassette Vrv
Electrical FittingsLed Light, Led Battens
Provision Of Wifi And Broadband FacilityWifi Routers And IT Vendors
External Finishing/Colour SchemeExternal Texture Paint
Internal FinishingPop, Plastic Paint, Dado Tiles, Ceiling Gyp

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Gurgaon Spectrum Centre (Phase-1) ( Commercial Project)?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.