Registration period overHRERA GurugramInterim ReraOC / CC on record

Group Housing Colony Of 10.925 Acres

by St. Patricks Realty Pvt.ltd. · Sector-32, Sohna Gurugram

RERA registration
150 OF 2017
Registered on
28 Aug 2017
Valid till
31 Jan 2026
Project ID
RERA-GRG-665-2020
Land area
148.683 acres
Estimated cost
₹ 1,202.34 Cr

RERA registration

Registration certificate150 OF 2017, dated 28 Aug 2017
Registration valid till31 Jan 2026
Project IDRERA-GRG-665-2020
AuthorityHRERA Gurugram (Interim Rera)
Project type (as filed)Ongoing
Project nameGroup Housing Colony Of 10.925 Acres
PromoterSt Patricks Realty Pvt Ltd
Promoter’s registered officeTower-D, 3RD Floor, Global Business Park, M.g Road, Gurgaon, Gurgaon, Haryana, 122002
CINU45200HR2008PTC037964
Site addressSector 29, 30, 32 & 33, Sohna, Dist Gurugram
SectorSector 32
Tehsil / DistrictSohna / Gurugram
Layout plan approved13 Dec 2019
Application submitted18 Mar 2020

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Next hearingNot Required
  1. Registration granted 150 OF 2017
  2. Application submitted online
  3. Application received by HRERA Gurugram
  1. Registration valid till

Land, licence & cost

Land area of the project148.683 acres
Total licensed area148.683 acres
Licence54 of 2014 (19-06-2024), 28 of 2016 (22-12-2021), 07 of 2020 (28-01-2025)
FAR permissible / proposed0 / 0
Estimated project cost₹ 1,202.34 Cr
Cost of land₹ 82.76 Cr
Cost of construction₹ 268.03 Cr
Infrastructure and other structures₹ 135.19 Cr
EDC, taxes, levies and other costs₹ 716.36 Cr

How the land will be used

UseAcresShare
Plots To Be Sold55.6937.5%
Land Area To Be Used For Construction Of Apartments14.119.5%
Construction Of Roads20.6713.9%
Pavements20.6713.9%
Parks And Playgrounds11.6657.8%
Green Belts7.1464.8%
Electricity Sub-Station0.470.3%
Club House21.3%
Sewage And Solid Waste Treatment Facility0.630.4%
Any Other3.522.4%
Commercial4.112.8%
Community6.454.3%
Undetermined1.5521%

External services

ServiceProvided byApproval taken
RoadsNoWATER SUPPLY
NoELECTRICITYNo
Sewage DisposalNoSTORM WATER DRAINAGE
No4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:Sr. No.
Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS1157
As Per Project Report2WATER SUPPLY SYSTEM
567AS PER PROJECT REPORT3
Storm Water Drainage324AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM1736
As Per Project Report5SEWAGE TREATMENT & GARBAGE DISPOSAL
463AS PER PROJECT REPORT6
Street Lighting174AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING23
As Per Project Report8PLAYGROUNDS AND PARKS
694AS PER PROJECT REPORT9
Club House/Community Centre1500AS PER PROJECT REPORT
10SHOPPING AREA0
Yet To Be Prepared11RENEWABLE ENERGY SYSTEM
25AS PER PROJECT REPORT12
School3476AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY1509
As Per Project Report14ANY OTHER
0AS PER PROJECT REPORT5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
13-12-2019(date)6. Date of approval of Building Plans
Na(date)(i) Details of the plots/apartments in the project:
Sr. No.Plot/ apartment typeSize of the plot/carpet area of the apartments
Total number of plots/apartments in the projectTotal size of the plots/carpet area of the apartmentsPlots/apartments booked/ sold upto the date of application
Yet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments1
PLOT Type BLOCK A041
0911
02PLOT Type BLOCK B
0300
1820
3PLOT Type BLOCK C0
115054
804
PLOT Type BLOCK D0176
0751
05PLOT Type BLOCK E
01580
000
6PLOT Type BLOCK F0
207050
1207
PLOT Type BLOCK G0105
04658
08PLOT Type BLOCK H
0480
0480
9PLOT Type BLOCK I0
10400
104010
PLOT Type BLOCK J0103
0060
011PLOT Type BLOCK K
0620
0240
Total11490
2523280
(ii) Apartments/Shops/Other Buildings:-(a) Status of construction activities in respect of sold/booked apartments.Type
Number of apartments booked/ soldWrite or Annex the stage of construction of the booked/ sold apartments in folder CFLAMINGO FLOORS
563STRUCTURE & PLASTER DONE, FLOORING & FINISHING IN PROGRESSCERISE FLOOR
139SUPERSTRUCTURE NEARING COMPLETIONCLOVER FLOORS
12STRUCTURE IN PROGRESSFLEUR VILLAS
61STRUCTURE, PLASTER AND FLOORING DONE, FINISHING IN PROGRESS(b) Time schedule of completion of already booked apartments:
Start Date01-08-2014Earlier date of completion
31-07-2022Revised date of completion31-12-2024
(c) Time schedule for development of infrastructure:Start Date01-08-2014
Percentage completion Upto the   date of application47
Projected date of completion31-12-2024(d) Provide further details in the proforma REP-I Part-C-X.
(e) Plan of action for completing the Project along with requisite infrastructure.(iii) Status in respect of plotted colony:-(a)
PlotsBooked/soldStage of handing over the possession (Write or Annex details)
Plot252LEVELING AND DEMARCATION DONE, SEWERAGE, DRAINAGE AND ELECTRIFICATION WORK IN PROGRESS
(b) Schedule for development of Infrastructure:Start Date01-08-2014
Percentage completion47Projected date of completion
31-12-2024(c) Provide further details in the proforma REP-I Part-C-X.(d) Schedule of completing the project and handing over possession of the plots.
(iv) Vehicle parkings details of the project-a) Underground parking0
b) Stilt parking482c) Covered parking
0d) Open parking709
e) Independent garages0(v) Quarterly schedule of development of whole/remaining part of the project:
(a) Apartments/Shops/Other BuildingsExpenditure incurred till the date of application (In Lakhs)Particulars
ExpenditureApartments11282.76
Shops0Plots
0Expenditure to be made in each quarter (In Lakhs)Particulars
Year-2020Jan-MarApr-June
July-SepOct-DecApartments
922.03910.12890.63
850.30Shops0
000
Plots00
00Particulars
Year-2021Jan-MarApr-June
July-SepOct-DecApartments
1269.011269.011269.01
1269.01Shops0
000
Plots00
00Particulars
Year-2022Jan-MarApr-June
July-SepOct-DecApartments
888.84888.84888.84
888.84Shops0
000
Plots00
00Particulars
Year-2023Jan-MarApr-June
July-SepOct-DecApartments
1113.591113.59543.93
543.93Shops0
000
Plots00
00(b) Infrastructure
Expenditure incurred till the date of application (In Lakhs)ParticularsExpenditure
Roads & Pavements534Water Supply System
285Sewerage treatment & garbage disposal191
Electricity Supply System519Storm Water Drainage
232Parks and Playgrounds559
Clubhouse/community centres495Shopping area
0Other764
Expenditure to be made in each quarter (In Lakhs)ParticularsYear-2020
Jan-MarApr-JuneJuly-Sep
Oct-DecRoads & Pavements18.72
18.7218.7218.72
Water Supply System8.468.46
8.468.46Sewerage treatment & garbage disposal
3.983.983.98
3.98Electricity Supply System36.53
36.5336.5336.53
Storm Water Drainage6.926.92
6.926.92Parks and Playgrounds

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 11.57 CrAs Per Project Report
Water Supply System₹ 5.67 CrAs Per Project Report
Storm Water Drainage₹ 3.24 CrAs Per Project Report
Electricity Supply System₹ 17.36 CrAs Per Project Report
Sewage Treatment & Garbage Disposal₹ 4.63 CrAs Per Project Report
Street Lighting₹ 1.74 CrAs Per Project Report
Security And Fire Fighting₹ 23 lakhAs Per Project Report
Playgrounds And Parks₹ 6.94 CrAs Per Project Report
Club House/Community Centre₹ 15 CrAs Per Project Report
Renewable Energy System₹ 25 lakhAs Per Project Report
School₹ 34.76 CrAs Per Project Report
Hospital/Dispensary₹ 15.09 CrAs Per Project Report

Statutory approvals

ApprovalStatusDate
Forest And Aravali NocAlready Been Obtained
Layout ApprovalAlready Been Obtained
Builtup Building PlansAlready Been Obtained
LicenseAlready Been Obtained
Environmental ApprovalApplied For But Yet To Receive
Demarcation & ZoningApplied For But Yet To Receive
Service Plan EstimatesApplied For But Yet To Receive

Specifications (as filed)

Flooring Details Of Various Parts Of HouseFor Flamingo Floors:

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Group Housing Colony Of 10.925 Acres?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.