H-38,Gf, M2K White House Sector Gurgaon Gurgaon Hr 122001
CIN
U45400HR2008PTC038509
Site address
Sector- 73
Sector
Sector 73
Tehsil / District
Badshahpur St / Gurugram
Construction start (as filed)
15 Jun 2022
Completion (as filed)
15 Dec 2026
Application submitted
15 Apr 2022
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyThe hearing is fixed for 09.05.2022.
Next hearingNot Required
Application submitted online
Application received by HRERA Gurugram
Notice sent to the promoterBy Hand
HearingExamination By AuthorityView order Proceedings
Proceedings dated: 09.05.2022 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Sunil Kumar (AR), Sh. Shrikant Kumar (Legal- Head) and Sh.Puneet Satija (Chartered Accountant) are present on behalf of the promoter. The authority directed the promoter to submit the Bank guarantee of Rs 25 lakhs within a week for the submission of service plan and estimates within 3 months from the issuance of registration certificate. The authority decided to grant the in-principle registration and at the same, the authority directed the promoter to submit three binded DPI along with the documents mentioned below: 1. The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 2. Online DPI needs to be corrected. 3. Latest Jamabandi duly certified by revenue officer six months prior to date of application needs to be submitted – It is submitted by the promoter that latest jamabandi is of year 2003-04 for which certificate from the revenue officer will be submitted. 4. Approvals / NOC’s from concerned agency for connecting roads needs to be submitted. 5. Escrow agreement with the bank submitted but needs to be signed and stamp by the banker. 6. Bank undertaking needs to be submitted. 7. Annual report for the financial year 2020-21 needs to be submitted. 8. Promoter affidavit keeping in view of section 4(2)(l)(D) needs to be revised as all three account numbers are not mentioned. In case of failure to submit the approved service plans and estimates within three months from the date of issuance of registration certificate, then the amount collected from the allottees is liable to be refunded with interest at the prescribed rate and the registration certificate shall be treated as deemed cancelled. The matter to come up for compliance on 16.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Proceedings dated: 16.05.2022 Sh. Ashish Kush, Planning Executive briefed the facts about the project.Sh. Sunil Kumar (AR) and Sh. Puneet Satija (CA) are present on behalf of the promoter. The promoter stated that the service plans and estimates are got approved today only vide no. LC-4446/JE(VA)/2022/13147 dated 16.05.2022 which will be submitted tomorrow alongwith the plans. The authority decided to grant the registration certificate on the condition that the promoter shall submit the service plan and estimates, corrected online (A-H) form and corrected Online DPI alongwith three sets of binder within a week..Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
Registration grantedGGM/560/292/2022/35
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
2.169 acres
Total licensed area
2.169 acres
Licence
107 OF 2021 DATED 17.12.2021
FAR permissible / proposed
1.5 / 1.49
Estimated project cost
₹ 55.44 Cr
Cost of land
₹ 11.67 Cr
Infrastructure and other structures
₹ 3.41 Cr
EDC, taxes, levies and other costs
₹ 40.36 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
0.7584
35%
Construction Of Roads
1.1495
53%
Parks And Playgrounds
0.108
5%
Electricity Sub-Station
0.0494
2.3%
Sewage And Solid Waste Treatment Facility
0.02
0.9%
Open Parking Area
0.051
2.4%
Toilet Block
0.0124
0.6%
Ugt
0.02
0.9%
Plots 28 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
100.65
120
1,083
5
102.30
122
1,101
12
121.67
146
1,310
11
External services
Service
Provided by
Approval taken
Roads
ALREADY CONNECTED
No
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 85.84 lakh
As Per Project Report
Water Supply System
₹ 79.51 lakh
As Per Project Report
Storm Water Drainage
₹ 30.89 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 30.41 lakh
As Per Project Report
Street Lighting
₹ 8.32 lakh
As Per Project Report
Playgrounds And Parks
₹ 2.07 lakh
As Per Project Report
Construction Of Circulation Road As Per Conditions Of License
₹ 1.04 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
License
Already Been Obtained
17 Dec 2021
Layout Plan Approval
Already Been Obtained
4 Jan 2022
Demarcation
Already Been Obtained
4 Jan 2022
Electricity Load Availability
Already Been Obtained
3 Jan 2022
Water Supply Assurance
Already Been Obtained
7 Jan 2022
Assurance For Sewarage Disposal
Already Been Obtained
30 Dec 2021
Forest Noc
Already Been Obtained
7 Dec 2021
Standard Design
Already Been Obtained
26 Apr 2022
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Grand Vista?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.