HearingExamination By AuthorityView order Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Bijendra (AR) is present on the behalf of the promoter. The promoter has submitted the reply to deficiency notice in the Authority on Friday i.e, 15.09.2023 which needs to be examined by the office. The promoter is directed to submit the remaining deficiencies in the Authority within two weeks. The matter to come up on 09.10.2023.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed about the facts of the case. Sh. Bijendra Pal Singh (AR) and Mohd. Annes (AR) are present on the behalf of the promoter and submits that in the land schedule issued with the license, the name of the company is mentioned against the land owned by them but in the license mistakenly has not been shown as licensee for that part of land but otherwise is a collaborator company for total licensed land. The necessary correction in the license and demarcation is under approval of the authority and shall be submitted within three weeks. Further the approval of zoning plan is also under signatures of DGTCP and shall be submitted before issuance of RC along with 25 lakhs BG for submission of service plans and estimates within three months. In view of the above, the proposal for grant of RC is approved subject to compliance as above and RC shall be issued after compliance as above except for corrected copy of license and demarcation which shall be submitted within three weeks along with GST registration.
Registration grantedGGM/748/480/2023/92
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
12.288 acres
Total licensed area
12.288 acres
Licence
Licence No. 161 of 2023, Valid up to 10.08.2028
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 38.87 Cr
Cost of land
₹ 15.03 Cr
Infrastructure and other structures
₹ 8.98 Cr
EDC, taxes, levies and other costs
₹ 14.85 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
7.0117
57.1%
Construction Of Roads
2.6491
21.6%
Parks And Playgrounds
0.9253
7.5%
Area To Be Left For Transferring To The Government For Community Services
1.2286
10%
Commercial
0.4728
3.8%
Plots 253 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
99.18
119
1,068
23
99.20
119
1,068
43
104.86
125
1,129
1
104.93
125
1,129
2
113.05
135
1,217
153
118.77
142
1,278
3
121.55
145
1,308
1
122.85
147
1,322
1
126.65
151
1,363
1
130.95
157
1,410
1
136.00
163
1,464
7
138.55
166
1,491
2
139.23
167
1,499
1
141.10
169
1,519
11
144.50
173
1,555
2
149.42
179
1,608
1
External services
Service
Provided by
Approval taken
Roads
NHAI
No
Water Supply
HSVP
No
Electricity
DHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 2.03 Cr
Submitted To HUDA
Water Supply System
₹ 1.85 Cr
Submitted To HUDA
Storm Water Drainage
₹ 77.81 lakh
Submitted To HUDA
Electricity Supply System
₹ 50 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 1.48 Cr
Submitted To HUDA
Street Lighting
₹ 47.14 lakh
Submitted To HUDA
Playgrounds And Parks
₹ 5.34 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
Licence
Already Been Obtained
11 Aug 2023
Layout
Already Been Obtained
11 Aug 2023
Zoning
Already Been Obtained
11 Oct 2023
Specifications (as filed)
Flooring Details Of Various Parts Of House
N/A
Wall Finishing Details
N/A
Kitchen Details
N/A
Bathroom Fittings
N/A
Wood Work Etc
N/A
Doors And Windos Frames
N/A
Glass Work
N/A
Electric Fittings
N/A
Conducting And Wiring Details
N/A
Cupboard Details
N/A
Water Storage
N/A
Lift Details
N/A
External Glazings
N/A
Windows/Glazings
N/A
Doors
N/A
Main Doors
N/A
Internal Doors
N/A
Air Conditioning
N/A
Electrical Fittings
N/A
Cng Pipe Line
N/A
Provision Of Wifi And Broadband Facility
N/A
External Finishing/Colour Scheme
N/A
Internal Finishing
N/A
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Golden Gate Residency?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.