HearingExamination By AuthorityView order Proceedings
The matter to come up on 13.01.2025.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Bijendra Pal Singh (AR) is present on behalf of the promoter. The AR of the promoter states that they have submitted the addendum to the collaboration agreement dated 10.01.2025 along with other deficit documents today itself in the office. Further, The AR seeks three months’ time for submission of the approved service plan & estimates. Approved as proposed subject to submission of BG/DD of Rs. 25 lakh for the submission of the above approval for service plans and estimates within three months. The RC shall be issued after submission of the above-mentioned deficit documents and examination of the reply submitted by the promoter.
Registration grantedGGM/903/635/2025/06
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
5.719 acres
Total licensed area
5.719 acres
Licence
136 of 2024 dated 04.11.2024
FAR permissible / proposed
1 / 1
Estimated project cost
₹ 59.62 Cr
Cost of land
₹ 33.18 Cr
Infrastructure and other structures
₹ 9.11 Cr
EDC, taxes, levies and other costs
₹ 17.33 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
3.4884
61%
Construction Of Roads
0.9962
17.4%
Parks And Playgrounds
0.4333
7.6%
Area To Be Left For Transferring To The Government For Community Services
0.5721
10%
Commercialblock
0.2287
4%
Plots 107 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
95.15
114
1,024
16
114.27
137
1,230
1
118.88
142
1,280
8
124.10
148
1,336
9
132.94
159
1,431
8
140.82
168
1,516
1
141.46
169
1,523
14
142.80
171
1,537
40
144.20
172
1,552
7
150.00
179
1,615
2
873.43
1,045
9,402
1
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
Yes
Electricity
DHBVN
Yes
Sewage Disposal
HSVP
Yes
Storm Water Drainage
HSVP
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 1.4 Cr
Yet To Be Prepared
Water Supply System
₹ 1.82 Cr
Yet To Be Prepared
Storm Water Drainage
₹ 85.56 lakh
Yet To Be Prepared
Electricity Supply System
₹ 2 Cr
Yet To Be Prepared
Street Lighting
₹ 21.94 lakh
Yet To Be Prepared
Playgrounds And Parks
₹ 5.43 lakh
Yet To Be Prepared
Any Other
₹ 1.63 Cr
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
Licence
Already Been Obtained
4 Nov 2024
Layout Plan
Already Been Obtained
6 Nov 2024
Forest Noc
Already Been Obtained
3 May 2024
Zoning
Already Been Obtained
24 Dec 2024
Electric Load Assurance
Already Been Obtained
16 Dec 2024
Service Plan & Estimate
Applied For But Yet To Receive
13 Dec 2024
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Golden Gate Residency- II?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.