HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
Registration valid till
Land, licence & cost
Land area of the project
8.593 acres
Total licensed area
8.593 acres
Licence
LICENSE NO 215 OF 2025 DATED 31.10.2025 VALID UPTO 30.10.2030 ISSUED BY TOWN AND COUNTRY PLANNING DEPARTMENT HARYANA
Estimated project cost
₹ 6.2 Cr
Cost of land
₹ 3.57 Cr
Infrastructure and other structures
₹ 0.69 Cr
EDC, taxes, levies and other costs
₹ 1.94 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
4.425
51.5%
Construction Of Roads
1.388
16.2%
Parks And Playgrounds
0.644
7.5%
Area To Be Left For Transferring To The Government For Community Services
0.859
10%
Any Other
1.05
12.2%
Commercial
0.227
2.6%
Plots 152 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
85.77
103
923
3
88.32
106
951
10
89.65
107
965
1
93.70
112
1,009
4
95.54
114
1,028
19
98.45
118
1,060
4
99.33
119
1,069
1
99.69
119
1,073
1
102.45
123
1,103
1
103.07
123
1,109
8
104.75
125
1,128
1
106.83
128
1,150
8
114.54
137
1,233
10
134.72
161
1,450
28
134.79
161
1,451
32
138.06
165
1,486
2
138.61
166
1,492
18
145.97
175
1,571
1
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
DHBVN
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 20 lakh
As Per Project Report
Water Supply System
₹ 22.5 lakh
As Per Project Report
Storm Water Drainage
₹ 4 lakh
As Per Project Report
Electricity Supply System
₹ 29.5 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 45 lakh
As Per Project Report
Street Lighting
₹ 1 lakh
As Per Project Report
Playgrounds And Parks
₹ 13.5 lakh
As Per Project Report
Boundary Wall
₹ 35 lakh
As Per Project Report
Underground Water Tank
₹ 28 lakh
As Per Project Report
Rain Water Harvesting
₹ 8 lakh
As Per Project Report
Milk And Vegetable Booth
₹ 10 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
License No 215 Of 2025
Already Been Obtained
31 Oct 2025
Zoning Cum Demarcation Plan
Already Been Obtained
1 Jan 2026
Specifications (as filed)
Flooring Details Of Various Parts Of House
Not Applicable
Wall Finishing Details
Not Applicable
Kitchen Details
Not Applicable
Bathroom Fittings
Not Applicable
Wood Work Etc
Not Applicable
Doors And Windos Frames
Not Applicable
Glass Work
Not Applicable
Electric Fittings
Not Applicable
Conducting And Wiring Details
Not Applicable
Cupboard Details
Not Applicable
Water Storage
Not Applicable
Lift Details
Not Applicable
External Glazings
Not Applicable
Windows/Glazings
Not Applicable
Doors
Not Applicable
Main Doors
Not Applicable
Internal Doors
Not Applicable
Air Conditioning
Not Applicable
Electrical Fittings
Not Applicable
Cng Pipe Line
Not Applicable
Provision Of Wifi And Broadband Facility
Not Applicable
External Finishing/Colour Scheme
Not Applicable
Internal Finishing
Not Applicable
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Gokul Dham Phase II?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.