Land Area To Be Used For Construction Of Apartments
3,649.02
12%
Construction Of Roads
6,661.32
22%
Pavements
3,137.78
10.3%
Parks And Playgrounds
8,160.75
26.9%
Club House
846.02
2.8%
Sewage And Solid Waste Treatment Facility
100
0.3%
Area To Be Left For Transferring To The Government For Community Services
3,022.49
10%
Area For Open Carparks
3,262.38
10.8%
Area For Maintenance
48.29
0.2%
Area For Commercial
150.86
0.5%
Open Area
1,286
4.2%
Apartments 457 units · 4 towers
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
43,015.10
-
384
Apartment/Shops/Other Buildings
73.30
789
5
Apartment/Shops/Other Buildings
1,251.88
13,475
68
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
HUDA
No
Water Supply
HUDA
No
Electricity
HUDA
No
Sewage Disposal
HUDA
No
Storm Water Drainage
HUDA
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 72.54 lakh
Yet To Be Prepared
Water Supply System
₹ 14.3 lakh
Yet To Be Prepared
Storm Water Drainage
₹ 37.6 lakh
Yet To Be Prepared
Electricity Supply System
₹ 2.4 Cr
Yet To Be Prepared
Sewage Treatment & Garbage Disposal
₹ 55.94 lakh
Yet To Be Prepared
Street Lighting
₹ 57.2 lakh
Yet To Be Prepared
Security And Fire Fighting
₹ 1.5 Cr
Yet To Be Prepared
Playgrounds And Parks
₹ 25 lakh
Yet To Be Prepared
Club House/Community Centre
₹ 6.43 Cr
Yet To Be Prepared
Renewable Energy System
₹ 28 lakh
Yet To Be Prepared
Statutory approvals
Approval
Status
Date
HUDA Construction Water Noc
Already Been Obtained
30 Oct 2018
Electrical Load Availability
Already Been Obtained
15 Oct 2018
Airport Height Clearance Noc
Already Been Obtained
22 Oct 2018
License
Already Been Obtained
25 Feb 2018
Environmental Clearance
Already Been Obtained
7 Feb 2019
Forest Noc
Already Been Obtained
26 Jul 2018
Tree Cutting Permission
Applied For But Yet To Receive
23 Oct 2018
Consent To Establish
Applied For But Yet To Receive
12 Feb 2019
Consent To Operate Noc
Yet To File For Approval
Deed Of Declaration
Yet To File For Approval
Execution Of Sale Deed
Yet To File For Approval
Mining Permission
Yet To File For Approval
1 Sep 2019
Fire Scheme Approval
Yet To File For Approval
28 Feb 2019
Services Estimates And Plans
Yet To File For Approval
28 Feb 2019
Occupation Permission Including Fire Noc, HSVP Internal And External Services Noc, Lift Noc, Chief Electrical Engineer Noc And Any Other Required Approval
Yet To File For Approval
GMDA/ HUDA/ Mcg Services Connection Permission
Yet To File For Approval
Electrical Load Connection/ Energization
Yet To File For Approval
Hsd Storage Noc
Yet To File For Approval
Specifications (as filed)
Flooring Details Of Various Parts Of House
Vitrified Tile Or Eqv. In Living/Dining, Wooden Flooring Or Eqv. In Bedrooms, Anti-Skid Tiles Or Eqv. In Toilets, Kitchen, Balcony & Utility
Wall Finishing Details
Acrylic Emulsion Or Eqv. In Intenal Walls, Oil Bound Distemper Or Eqv. In Ceiling, Weather Proof Or Eqv. In External
Kitchen Details
Granite Counter With Sink And Cp Fittings
Bathroom Fittings
Yes Cp/ Sanitary
Wood Work Etc
Yes
Doors And Windos Frames
Teak Frame In Main Door, Aluminium Frame With Glass For Windows & Sliding Door Windows, Red Merandi In Internal Doors
Glass Work
Yes, Windows
Electric Fittings
Only Switches
Conducting And Wiring Details
Yes
Cupboard Details
No Wardrobe
Water Storage
Underground Water Tank
Lift Details
Yes
External Glazings
Yes - Windows
Windows/Glazings
Aluminium
Doors
Yes
Main Doors
Teak Wood Frame With Veneer Shutter
Internal Doors
Red Merandi With Laminate Shutter & Skin Door In Toilets
Electrical Fittings
Only Switches
External Finishing/Colour Scheme
Weather Proof Or Equivalent
Internal Finishing
Acrylic Emulsion Or Eqv.
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Godrej Habitat?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.