Gls Courtyard
by Gls Infraprojects Pvt. Ltd. · 707, 7TH Floor, Jmd Pacific Square
- RERA registration
- GGM/563/295/2022/38
- Registered on
- 23 May 2022
- Valid till
- 31 Mar 2025
- Project ID
- RERA-GRG-998-2022
- Land area
- 2.956 acres
- Plots
- 34
- Completion (as filed)
- 31 Mar 2025
- Estimated cost
- ₹ 54.87 Cr
(SUPERSEDED BY GGM/815/547/2024/42 DATED 15.04.2024)
RERA registration
| Registration certificate | GGM/563/295/2022/38, dated 23 May 2022 |
|---|---|
| Registration valid till | 31 Mar 2025 |
| Project ID | RERA-GRG-998-2022 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Gls Courtyard |
| Promoter | Gls Infraprojects Pvt. Ltd. |
| Promoter’s registered office | 707, 7RD Floor, Jmd Pacific Square, Sector-15, Part-II, |
| CIN | U70102HR2013PTC051335 |
| Site address | 707, 7TH Floor, Jmd Pacific Square |
| Tehsil / District | Harsaru St / Gurugram |
| Layout plan approved | 9 Dec 2021 |
| Construction start (as filed) | 1 Apr 2022 |
| Completion (as filed) | 31 Mar 2025 |
| Application submitted | 6 Jan 2022 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter By Hand
-
Hearing
Examination By Authority View order
Proceedings
Sh. Ashish Kush, Planning Executive briefed about the facts of the project through video conferencing. By the orders of the authority the promoter is directed to remove the deficit documents as mentioned above. The matter to come up on 07.02.2022.
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush, Planning Executive briefed about the facts of the project through video conferencing. Sh. Ashish Drall (Sr. GM) and Sh. Pankaj Sharma (Legal Manager) are present on behalf of the promoter who apprises that the approval of service plan estimates as well as demarcation plan and standard design stand submitted in the office of DTCP on 27.12.2021 itself and are at advance stage of approval. The corrections in online DPI and a few other deficit documents are also being submitted and request for an adjournment of 15 days for the rectification and submission of all deficit documents. The matter to come up on 21.02.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 21.02.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the project through video conferencing. Sh. Ashish Drall (Senior GM) and Pankaj Sharma (Legal Manager) are present on behalf of the promoter. After scrutiny of the reply, it was found that some deficiencies are remaining which are mentioned below: 1. The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 2. Online DPI needs to be corrected. 3. Approved Service Plan and Estimates needs to be submitted. 4. Demarcation plan and architectural control sheet needs to be submitted. 5. Draft Builder Buyer Agreement needs to be revised. 6. Draft brochure of the project needs to be submitted. The Authority directed the promoter to submit the deficit documents within 15 days. The matter to come up on 07.03.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 07.03.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the project through video conferencing. Sh. Ashish Drall (Sr. GM) is present on behalf of the promoter. The promoter requested for two weeks’ time for the rectification of the deficiencies. The Authority accepts the request and the matter to come up on 28.03.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 31.03.2022
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 02.04.2022
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 02.04.2022 Sh. Ashish Kush (Planning Executive) briefed about the facts of the case. Sh. Ashish Drall (Sr. GM) is present on behalf of the promoter. The corrected form A to H and DPI have been submitted and are to be scrutinized. The AR of the promoter submits that the service plan estimates as well architectural control sheets are in advance stage of approval and seeks 2 weeks’ time for their submission. The matter to come up on 25.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Adjournment View order
Proceedings
Sh. Ashish Kush (Planning Executive) briefed about the facts of the case. Sh. Ashish Drall (Sr. GM) and Sh. Pankaj Sharma (Legal Manager) are present on behalf of the promoter. The AR of the promoter requested for 2 weeks’ time for submitting deficit documents and approvals. The matter is fixed for 09.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 09.05.2022 Sh. Ashish Kush (Planning Executive) briefed about the facts of the case. Sh. Ashish Drall (Sr. GM) is present on behalf of the promoter. The promoter fails to comply with all the deficiencies conveyed earlier. The remaining deficiencies are mentioned below: 1. Approved Service Plan and Estimates needs to be submitted. 2. Demarcation plan and architectural control sheet needs to be submitted. 3. Draft Builder Buyer Agreement needs to be revised. 4. Draft brochure of the project needs to be submitted. The authority directed the promoter to submit the deficit documents. As the architectural control sheet and service plan and estimates are the pre-requisite for the registration. The matter to come up on 16.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Adjournment View order
Proceedings
Proceedings dated: 16.05.2022 Sh. Ashish Kush (Planning Executive) briefed about the facts of the case.Sh. Ashish Drall (Sr. GM) is present on behalf of the promoter. The promoter stated that the service plans and estimates are got approved today only vide no. LC-4200(A+B)/JE(DS)-2022/13222 dated 16.05.2022 which will be submitted tomorrow alongwith the plans. The authority the promoter to submit the service plan and estimates, corrected online (A-H) form and corrected Online DPI alongwith three sets of binder within a week. The matter to come up on 23.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Proceedings dated: 23.05.2022 Sh. Ashish Kush (Planning Executive) briefed about the facts of the case.Sh. Ashish Drall (Sr. GM) is present on behalf of the promoter. In view of the examination and confirmation by the Office for promoter having complied with all the pre-requisites, the authority decides to grant the registration certificate.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal)
- Registration granted GGM/563/295/2022/38
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 2.956 acres |
|---|---|
| Total licensed area | 2.956 acres |
| Licence | 103 of 2021(08-12-2021) |
| FAR permissible / proposed | 1.5 / 1.5 |
| Estimated project cost | ₹ 54.87 Cr |
| Cost of land | ₹ 23.95 Cr |
| Infrastructure and other structures | ₹ 6.51 Cr |
| EDC, taxes, levies and other costs | ₹ 24.41 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Plots To Be Sold | 1.035 | 40.6% |
| Construction Of Roads | 1.006 | 39.4% |
| Parks And Playgrounds | 0.095 | 3.7% |
| Vehicle Parkings | 0.246 | 9.6% |
| Electricity Sub-Station | 0.049 | 1.9% |
| Sewage And Solid Waste Treatment Facility | 0.062 | 2.4% |
| Ugt | 0.049 | 1.9% |
| Toilet | 0.009 | 0.4% |
Plots 34 plots
| Plot size (sq m) | Sq yd | Sq ft | Plots |
|---|---|---|---|
| 74.02 | 89 | 797 | 1 |
| 82.05 | 98 | 883 | 1 |
| 84.80 | 101 | 913 | 1 |
| 94.26 | 113 | 1,015 | 1 |
| 97.50 | 117 | 1,049 | 1 |
| 97.97 | 117 | 1,055 | 1 |
| 99.00 | 118 | 1,066 | 5 |
| 99.00 | 118 | 1,066 | 5 |
| 110.22 | 132 | 1,186 | 1 |
| 138.85 | 166 | 1,495 | 2 |
| 138.85 | 166 | 1,495 | 2 |
| 148.06 | 177 | 1,594 | 12 |
| 255.94 | 306 | 2,755 | 1 |
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | DULB/ HSVP/ GMDA | Yes |
| Water Supply | DULB/ HSVP/ GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | DULB/ HSVP/ GMDA | Yes |
| Storm Water Drainage | DULB/ HSVP/ GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 1.29 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 72.13 lakh | Yet To Be Prepared |
| Storm Water Drainage | ₹ 32.38 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 1.65 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 35.29 lakh | Yet To Be Prepared |
| Street Lighting | ₹ 11.34 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 96.32 lakh | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 8.54 lakh | Yet To Be Prepared |
| Parking | ₹ 22.31 lakh | Yet To Be Prepared |
| Stp | ₹ 78.09 lakh | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| License | Already Been Obtained | 3 Dec 2021 |
| Layout Plan Approval | Already Been Obtained | 9 Dec 2021 |
| Non-Encumbrance | Already Been Obtained | 16 Jan 2022 |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | N/A |
|---|---|
| Wall Finishing Details | N/A |
| Kitchen Details | N/A |
| Bathroom Fittings | N/A |
| Wood Work Etc | N/A |
| Doors And Windos Frames | N/A |
| Glass Work | N/A |
| Electric Fittings | N/A |
| Conducting And Wiring Details | N/A |
| Cupboard Details | N/A |
| Water Storage | N/A |
| Lift Details | N/A |
| External Glazings | N/A |
| Windows/Glazings | N/A |
| Doors | N/A |
| Main Doors | N/A |
| Internal Doors | N/A |
| Air Conditioning | N/A |
| Electrical Fittings | N/A |
| Cng Pipe Line | N/A |
| Provision Of Wifi And Broadband Facility | N/A |
| External Finishing/Colour Scheme | N/A |
| Internal Finishing | N/A |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.