Registration period overHRERA Gurugram

Global Heights 88A

by Gcc Infra · P903-905, Sector 48, Jmd Megapolis, Gurugram

RERA registration
GGM/532/264/2022/07
Registered on
1 Feb 2022
Valid till
23 Sep 2026
Project ID
RERA-GRG-992-2021
Land area
6.5 acres
Apartments
1,022 in 33 towers
Completion (as filed)
23 Sep 2026
Estimated cost
₹ 215.83 Cr

RERA registration

Registration certificateGGM/532/264/2022/07, dated 1 Feb 2022
Registration valid till23 Sep 2026
Project IDRERA-GRG-992-2021
AuthorityHRERA Gurugram
Project type (as filed)New
Project nameGlobal Heights 88A
Site addressP903-905, Sector 48, Jmd Megapolis, Gurugram
SectorSector 48
Tehsil / DistrictGurgaon / Gurugram
Construction start (as filed)1 Jun 2022
Completion (as filed)23 Sep 2026
Application submitted3 Jan 2022

Authority, hearings & orders

Current statusApproved And Certificate Uploaded
Initial scrutinyfirst hearing
Next hearingNot Required
  1. Application submitted online
  2. Application received by HRERA Gurugram
  3. Notice sent to the promoter Dispatchd to AR of the promoter
  1. Hearing Approved And Ready For Certificate Issuing Process
    Proceedings

    Proceedings dated 01.02.2022 Sh. Harshit Singla (AR) is present on behalf of the promoter. Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. The promoter has applied for the approval of service plans and estimates and environmental clearance in the concerned departments and the final approvals are still awaited. The application for approval of fire scheme has not been made yet. Corrections in online DPI which have been marked on the hard copy of DPI and conveyed to the promoter are still pending. The authority has decided to grant registration to the promoter subject to the corrections in online DPI and submission of bank guarantee of Rs 10 lakhs on account of approved fire scheme and Rs. 10 lakhs on account of approved service plans and estimates within seven days from the date of grant of registration. This bank guarantee shall be forfeited in case the approved fire scheme and approved service plans and estimates are not submitted in the authority within three months from the date of grant of registration. 

  2. Registration granted GGM/532/264/2022/07
  3. Certificate uploaded RC Uploaded
  1. Registration valid till

Land, licence & cost

Land area of the project6.5 acres
Total licensed area6.5 acres
Licence77 OF 2021
FAR permissible / proposed2.37 / 2.37
Estimated project cost₹ 215.83 Cr
Cost of land₹ 43.2 Cr
Cost of construction₹ 114.24 Cr
Infrastructure and other structures₹ 16 Cr
EDC, taxes, levies and other costs₹ 42.38 Cr

How the land will be used

UseArea (as filed)Share
Land Area To Be Used For Construction Of Apartments1.437716.9%
Construction Of Roads2.0924.6%
Pavements0.9911.6%
Parks And Playgrounds0.97511.5%
Vehicle Parkings1.922.3%
Electricity Sub-Station0.333.9%
Sewage And Solid Waste Treatment Facility0.1051.2%
Any Other0.67738%

Apartments 1,022 units · 33 towers

TypeCarpet area (sq m)Carpet area (sq ft)Units
Apartment/Shops/Other Buildings53,724.49-936
Apartment/Shops/Other Buildings1,606.7317,29586

Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.

External services

ServiceProvided byApproval taken
RoadsGMDA/HUDA (NOT APPLICABLE)No
Water SupplyGMDAYes
ElectricityGMDAYes
Sewage DisposalGMDAYes
Storm Water DrainageGMDAYes

Facilities in the service plan

FacilityEstimated costStatus
Internal Roads And Pavements₹ 1.5 CrSubmitted To Town & Country Planning
Water Supply System₹ 3.53 CrSubmitted To Town & Country Planning
Storm Water Drainage₹ 66.22 lakhSubmitted To Town & Country Planning
Sewage Treatment & Garbage Disposal₹ 1.12 CrSubmitted To Town & Country Planning
Street Lighting₹ 24.94 lakhSubmitted To Town & Country Planning
Playgrounds And Parks₹ 17.88 lakhSubmitted To Town & Country Planning
Any Other₹ 1.94 CrSubmitted To Town & Country Planning

Statutory approvals

ApprovalStatusDate
Storm Water DrainageAlready Been Obtained15 Dec 2021
Water SupplyAlready Been Obtained15 Dec 2021
Sewage DisposalAlready Been Obtained15 Dec 2021
LicenseAlready Been Obtained24 Sep 2021
Map ApprovalAlready Been Obtained18 Jan 2022
RoadsApplied For But Yet To Receive
Electrical Load AvailabilityApplied For But Yet To Receive15 Dec 2021

Specifications (as filed)

Flooring Details Of Various Parts Of HouseTiles
Wall Finishing DetailsObd
Kitchen DetailsCeramic Tiles
Bathroom FittingsModern Elegent
Doors And Windos FramesMild Steel
Glass Work4 Mm Glassasai/Saint Gobain
Electric FittingsIsi Mark For Wiring Switches & Circuts
Conducting And Wiring DetailsConduit-Pvc, Wiring-Copper/Aluminum
Water StorageUnderground Storage Tank & Overheads Storage Tank
Lift DetailsOtis/ Johnson
Windows/GlazingsMild Steel Section
DoorsFlush Doors
Main DoorsFlush Doors
Internal DoorsFlush Doors
Electrical FittingsCopper/Aluminum

Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.

Kamal JaiswalAnkush DwivediNitish MahatoNaveen Kumar
Speak to an advisor

Questions about Global Heights 88A?

An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.

+91 9953537030WhatsApp
Need a shortlist? Answer 4 quick questions and see matching projects.