Village Naggal & Alipur Sector 19 Kot Behla Urban Complex
Sector
Sector 19
Tehsil / District
Panchkula / Panchkula
Layout plan approved
13 Feb 2026
Construction start (as filed)
1 May 2026
Completion (as filed)
12 Feb 2031
Application submitted
24 Apr 2026
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyListed for hearing on 13-05-2026
Next hearingNot Required
Application submitted online
Application received by HRERA Panchkula
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS
Registration valid till
Land, licence & cost
Land area of the project
9.99 acres
Total licensed area
9.99 acres
Licence
LICENCE NO. 26 OF 2025 GRANTED BY DTCP HARYANA ON DATED 13.02.2026 IS VALID UPTO 12.02.2031
Estimated project cost
₹ 34.11 Cr
Cost of land
₹ 27.17 Cr
Infrastructure and other structures
₹ 5 Cr
EDC, taxes, levies and other costs
₹ 1.94 Cr
How the land will be used
Use
Acres
Share
Plots To Be Sold
4.9077
49.1%
Construction Of Roads
2.6942
27%
Parks And Playgrounds
0.7567
7.6%
Green Belts
0.451
4.5%
Area To Be Left For Transferring To The Government For Community Services
0.99
9.9%
Area Under Commercial
0.1907
1.9%
Plots 172 plots
Plot size (sq m)
Sq yd
Sq ft
Plots
73.33
88
789
1
74.85
90
806
1
74.90
90
806
21
97.69
117
1,052
2
102.49
123
1,103
54
115.12
138
1,239
1
118.68
142
1,277
2
119.27
143
1,284
2
123.82
148
1,333
1
126.53
151
1,362
30
129.64
155
1,395
1
132.26
158
1,424
1
133.43
160
1,436
21
137.16
164
1,476
12
140.09
168
1,508
1
142.50
170
1,534
8
147.49
176
1,588
1
147.87
177
1,592
9
149.03
178
1,604
1
149.92
179
1,614
2
External services
Service
Provided by
Approval taken
Roads
HSVP
No
Water Supply
HSVP
No
Electricity
DHBVNL
No
Sewage Disposal
HSVP
No
Storm Water Drainage
HSVP
No
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 1.36 Cr
As Per Project Report
Water Supply System
₹ 78.89 lakh
As Per Project Report
Storm Water Drainage
₹ 57.97 lakh
As Per Project Report
Electricity Supply System
₹ 66.76 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 75.85 lakh
As Per Project Report
Street Lighting
₹ 24.36 lakh
As Per Project Report
Playgrounds And Parks
₹ 21.52 lakh
As Per Project Report
Boundary Wall
₹ 37.58 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Layout Plan
Already Been Obtained
13 Feb 2026
Demarcation Cum Zoning Plan
Already Been Obtained
21 Apr 2026
Source: HRERA Panchkula, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Five Greens?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.