Elan The Mark
by Elan Avenue Limited · Situated In Sector 106 In The Revenue Estate Of Village Pawala Khusrupur Tehsil Kadipur District Gurugram, Haryana
- RERA registration
- GGM/702/434/2023/46
- Registered on
- 6 Mar 2023
- Valid till
- 15 Jan 2028
- Project ID
- RERA-GRG-1273-2023
- Land area
- 6.525 acres
- Apartments
- 835 in 1 tower
- Completion (as filed)
- 15 Jan 2028
- Estimated cost
- ₹ 1,221.46 Cr
RERA registration
| Registration certificate | GGM/702/434/2023/46, dated 6 Mar 2023 |
|---|---|
| Registration valid till | 15 Jan 2028 |
| Project ID | RERA-GRG-1273-2023 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Elan The Mark |
| Promoter | Elan Avenue Limited |
| Promoter’s registered office | 15TH Floor ,Two Horizon Centre , DLF Phase-V, Golf Course Road, Gurugram 122002 |
| CIN | U45400HR2007PLC104996 |
| Site address | Situated In Sector 106 In The Revenue Estate Of Village Pawala Khusrupur Tehsil Kadipur District Gurugram, Haryana |
| Sector | Sector 106 |
| Tehsil / District | Kadipur St / Gurugram |
| Building plans approved | 6 Feb 2023 |
| Construction start (as filed) | 25 Apr 2023 |
| Completion (as filed) | 15 Jan 2028 |
| Application submitted | 20 Jan 2023 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter 1st Deficiency Notice
-
Hearing
Adjournment View order
Proceedings
The matter is adjourned to 14.02.2023.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineer Executive cum Planning Coordinator and Ms. Asha, Chartered Accountant briefed about the facts of the case. Ms. Priyanka Aggarwal (AR) is present on behalf of the promoter. The promoter has submitted the reply recently which needs to be scrutinized. The matter to come up on 20.02.2023.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineer Executive cum Planning Coordinator and Ms. Asha, Chartered Accountant briefed about the facts of the case. Ms. Priyanka Aggarwal (AR) is present on behalf of the promoter. The applicant/ promoter has submitted a representation regarding the late fee. The matter to come up on 06.03.2023.
-
Hearing
Adjournment View order
Proceedings
Sh. Sumeet, Engineer Executive cum Planning Coordinator and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Arvinder Dhingra (AS) and Ms. Priyanka Aggarwal (Advocate) are present on behalf of the promoter. The matter is deferred to 06.03.2023.
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
Sh. Sumeet, Engineering Officer cum Planning Coordinator and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Arvinder Dhingra [AS) and Ms. Priyanka Aggarwal are present on behalf of the promoter. The applicant promoter has submitted a representation dated 20.02.2023 regarding late fee along with a copy of the letter issued by interim RERA bearing Memo No. HREM/RD/20L7/35/L049, dated 75.09.2077wherein it has been clarified to the NAREDCO Haryana that promoter may register his Iicensed (unlaunched) projects anytime in future before he intends to advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building as the case may, in any real estate project or part of it, in the planning area. The copy of the above clarification is uploaded and available on official website of T&CP; Department, Haryana. The Authority in such cases sought a clarification from AG, Haryana regarding applicability of late fee. In another such case of M/s DLF Home Developers Ltd. wherein the license has been obtained before 15.09.2017and the building plans have been approved later on, the AG Haryana has already opined that the late fee or penalty is not leviable not only for the project of DLF but the same is advised to be true for a project for which license was taken before 01.05.2017, but no further preparation was done to develop a real estate project. Such a project would not be covered within the ambit of ongoing. In view of the above the Authority decided to grant registration to the project subject to submission of an affidavit from the promoter to the effect that in case any future liability arises on account of late fee, the same shall be deposited on demand without demur. The building plans of the project have been approved on 06.02.2023 wherein Directorate has granted approval to licensee in collaboration with Elan Avenue Ltd (formerly known as Airmid Developers Ltd). In view of this, the change of name of company has already been allowed by DTCP at the time of approving building plans. Accordingly, the promoter is directed to submit the formal letter issued by DTCP for change of name of the company within two months. Further the promoter shall submit the revised affidavit to the effect that the promoter has not done any advertisement, marketing, booking, selling or offer for selling or invited any person to purchase in any manner, any unit in this project prior to getting the project registered in the Authority.
- Registration granted GGM/702/434/2023/46
- Certificate uploaded RC Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 6.525 acres |
|---|---|
| Total licensed area | 6.525 acres |
| Licence | 79of 2012 dated 17/08/2012 valid till 16/08/2024 And 11 of 2013 dated 12/03/2013 vaild till 11/032024 |
| FAR permissible / proposed | 187 / 186.95 |
| Estimated project cost | ₹ 1,221.46 Cr |
| Cost of land | ₹ 63.03 Cr |
| Cost of construction | ₹ 433.79 Cr |
| Infrastructure and other structures | ₹ 46.32 Cr |
| EDC, taxes, levies and other costs | ₹ 678.32 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 1.975 | 30.3% |
| Construction Of Roads | 1.048 | 16.1% |
| Parks And Playgrounds | 0.2 | 3.1% |
| Any Other | 3.301 | 50.6% |
Apartments 835 units · 1 tower
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 29,140.39 | - | 835 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | GMDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 8.78 Cr | As Per Project Report |
| Water Supply System | ₹ 2.43 Cr | As Per Project Report |
| Storm Water Drainage | ₹ 2.07 Cr | As Per Project Report |
| Electricity Supply System | ₹ 11.37 Cr | As Per Project Report |
| Sewage Treatment & Garbage Disposal | ₹ 1.73 Cr | As Per Project Report |
| Street Lighting | ₹ 1.31 Cr | As Per Project Report |
| Security And Fire Fighting | ₹ 2.08 Cr | As Per Project Report |
| Playgrounds And Parks | ₹ 54.92 lakh | As Per Project Report |
| Renewable Energy System | ₹ 1.16 Cr | As Per Project Report |
| Parking | ₹ 3.37 Cr | As Per Project Report |
| Stp | ₹ 1.59 Cr | As Per Project Report |
| Underground Watertank | ₹ 2.51 Cr | As Per Project Report |
| Rain Water Harvesting | ₹ 23.54 lakh | As Per Project Report |
| Electric Sub Station | ₹ 7.13 Cr | As Per Project Report |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Forest Noc | Already Been Obtained | 18 Nov 2021 |
| Building Plan | Already Been Obtained | 6 Feb 2023 |
| Environment Clearance | Already Been Obtained | 25 Sep 2022 |
| Noc Form Airport Authority | Already Been Obtained | 5 May 2022 |
| Electrical Load Availability | Already Been Obtained | 21 Sep 2022 |
| Service Estimates Plan | Yet To File For Approval | |
| Fire Scheme Approval | Yet To File For Approval |
Specifications (as filed)
| Flooring Details Of Various Parts Of House | Stone/Tile Flooring In Common Areas |
|---|---|
| Wall Finishing Details | Cement Plaster |
| Bathroom Fittings | White Chinaware With Cp Fittings |
| Doors And Windos Frames | Aluminum Frames With Glass |
| Glass Work | Toughened Glass 6MM Thick And Above |
| Electric Fittings | Electrical Fittings & Fixtures Not Provided |
| Conducting And Wiring Details | Pvc Conducting With Copper Wiring |
| Water Storage | 300KL Fire Tank, 150KL Domestic Tank, 150KL Raw Water Tank, 310KL Recycled |
| Lift Details | 6 Nos |
| External Glazings | Isi Marked |
| Windows/Glazings | Aluminum Frames With Glass |
| Doors | Commercial Flush Door Shutters Glass Doors |
| Main Doors | Commercial Flush Door Shutters |
| Internal Doors | Commercial Flush Door Shutters |
| Air Conditioning | As Per Dbr In Select Spaces |
| Electrical Fittings | Electrical Provided Fittings Not |
| Provision Of Wifi And Broadband Facility | Yes Provision Is There |
| External Finishing/Colour Scheme | Plaster & Paint, Glazing, Acp/ Stone Cladding |
| Internal Finishing | Cement/ Gypsum Plaster |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.