Elan Paradise
by Elan Limited · Revenue Estate Of Village Adampur, Sub Tehsil- Wazirabad, Sector-50, District Gurugram, Haryana
- RERA registration
- GGM/447/179/2021/15
- Registered on
- 22 Mar 2021
- Valid till
- 30 Sep 2025
- Project ID
- RERA-GRG-813-2021
- Land area
- 2 acres
- Apartments
- 247 in 1 tower
- Completion (as filed)
- 30 Sep 2025
- Estimated cost
- ₹ 199.43 Cr
(SUPERSEDED BY GGM/584/316/2022/59 DATED 04.07.2022)
RERA registration
| Registration certificate | GGM/447/179/2021/15, dated 22 Mar 2021 |
|---|---|
| Registration valid till | 30 Sep 2025 |
| Project ID | RERA-GRG-813-2021 |
| Authority | HRERA Gurugram |
| Project type (as filed) | New |
| Project name | Elan Paradise |
| Promoter | Elan Limited |
| Promoter’s registered office | 3RD Floor, Golf View Corporate Tower, Golf Course Road, Sector 42 , Gurugram , Haryana 122002 |
| CIN | U70200DL2013PLC250600 |
| Site address | Revenue Estate Of Village Adampur, Sub Tehsil- Wazirabad, Sector-50, District Gurugram, Haryana |
| Sector | Sector 50 |
| Tehsil / District | Wazirabad St / Gurugram |
| Layout plan approved | 10 Feb 2021 |
| Building plans approved | 10 Feb 2021 |
| Construction start (as filed) | 30 Sep 2021 |
| Completion (as filed) | 30 Sep 2025 |
| Application submitted | 12 Feb 2021 |
Authority, hearings & orders
- Application submitted online
- Application received by HRERA Gurugram
- Notice sent to the promoter By Mail
-
Hearing
Examination By Authority View order
Proceedings
Hearing adjourned and fixed for 22.02.2021
-
Hearing
Approved And Ready For Certificate Issuing Process View order
Proceedings
During personal hearing, the Authority has discussed the project in detail. After detailed scrutiny, it was found that all the deficiencies have been fulfilled by the promoter and the registration fee, processing fee is duly paid by the promoter. The documents which are still pending are copy of environment clearance, fire scheme approval and approved service estimates and plans, however, applications already filed in the concerned department for these approvals. An affidavit was given by the promoter declaring that he will submit these deficit approvals within 3 months. Therefore, the authority has decided to grant provisional registration certificate and direct the promoter to submit these deficit documents within 3 months from the date of grant of registration certificate. Also, the promoter shall submit the bank guarantee of Rs 10,00,000,00/- within seven days from the date of issuance of registration certificate. This bank guarantee shall be forfeited in case the conditions are not fulfilled by the promoter within 3 months of issuance of this registration certificate. The master account (100%) (50200055952382) shall be attached. No amount shall be withdrawn from this account till the submission of deficit documents in the authority. It is the responsibility of the concerned bank to freeze the master account till the conditions are not fulfilled by the promoter and the account will be defreeze as intimated by the authority. In case of failure to submit the approved environment clearance, fire scheme approval and approved service estimates and plans within three months from the date of issuance of registration certificate, then the amount collected from the allottees will be refunded with interest at the prescribed rate within one month thereafter and the registration certificate shall be treated as demand cancelled.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K Khandelwal (Chairman)
- Registration granted GGM/447/179/2021/15
- Certificate uploaded RC Approved and Certificate Uploaded
- Registration valid till
Land, licence & cost
| Land area of the project | 2 acres |
|---|---|
| Total licensed area | 2 acres |
| Licence | 32 of 2020 dated 31/10/2020 by TCP |
| FAR permissible / proposed | 1.87 / 1.87 |
| Estimated project cost | ₹ 199.43 Cr |
| Cost of land | ₹ 43.96 Cr |
| Cost of construction | ₹ 86.61 Cr |
| Infrastructure and other structures | ₹ 11.61 Cr |
| EDC, taxes, levies and other costs | ₹ 57.26 Cr |
How the land will be used
| Use | Acres | Share |
|---|---|---|
| Land Area To Be Used For Construction Of Apartments | 1.07 | 51.4% |
| Construction Of Roads | 0.7731 | 37.1% |
| Parks And Playgrounds | 0.227 | 10.9% |
| Vehicle Parkings | 0.0123 | 0.6% |
Apartments 247 units · 1 tower
| Type | Carpet area (sq m) | Carpet area (sq ft) | Units |
|---|---|---|---|
| Apartment/Shops/Other Buildings | 8,603.32 | - | 247 |
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
| Service | Provided by | Approval taken |
|---|---|---|
| Roads | HUDA | Yes |
| Water Supply | GMDA | Yes |
| Electricity | DHBVN | Yes |
| Sewage Disposal | GMDA | Yes |
| Storm Water Drainage | GMDA | Yes |
Facilities in the service plan
| Facility | Estimated cost | Status |
|---|---|---|
| Internal Roads And Pavements | ₹ 2.66 Cr | Yet To Be Prepared |
| Water Supply System | ₹ 56.02 lakh | Yet To Be Prepared |
| Storm Water Drainage | ₹ 52 lakh | Yet To Be Prepared |
| Electricity Supply System | ₹ 2.5 Cr | Yet To Be Prepared |
| Sewage Treatment & Garbage Disposal | ₹ 42.78 lakh | Yet To Be Prepared |
| Street Lighting | ₹ 23.75 lakh | Yet To Be Prepared |
| Security And Fire Fighting | ₹ 59.55 lakh | Yet To Be Prepared |
| Playgrounds And Parks | ₹ 16.13 lakh | Yet To Be Prepared |
| Renewable Energy System | ₹ 32.23 lakh | Yet To Be Prepared |
| Parking | ₹ 52 lakh | Yet To Be Prepared |
| Stp | ₹ 38.67 lakh | Yet To Be Prepared |
| Under Oh Water Tank | ₹ 62.88 lakh | Yet To Be Prepared |
| Rain Water Harvesting | ₹ 6.77 lakh | Yet To Be Prepared |
| Electrical Sub Station | ₹ 2.03 Cr | Yet To Be Prepared |
Statutory approvals
| Approval | Status | Date |
|---|---|---|
| Forest Noc | Already Been Obtained | 1 Mar 2021 |
| Zoning Plan Drg No. Dtcp 7581 | Already Been Obtained | 2 Nov 2020 |
| Water Noc Memo 68 | Already Been Obtained | 28 Jan 2021 |
| Electrical Load Availablity Memo No. Ch. /Dgr-26B Dated 4/2/2021 | Already Been Obtained | 4 Feb 2021 |
| Building Plan Memo No. 2P-1452/Ad(Ra)/20213372 | Already Been Obtained | 10 Feb 2021 |
| License 32 Of 2020, | Already Been Obtained | 10 Oct 2020 |
| Sewage Disposal Memo No. Gmdascw/2021/218 | Already Been Obtained | 23 Feb 2021 |
| Environment Clearance | Applied For But Yet To Receive | 23 Feb 2021 |
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.




Questions about Elan Paradise?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.