Elan Imperial Pvt Ltd (Formerly Known As Ambience Infrastructure Developers Pvt Ltd)
Promoter’s registered office
15TH Floor, Two Horizon Center, DLF Phase 5, Sector-43, Golf Course Road, Gurugram
CIN
U45200DL2008PTC173009
Site address
Village- Nakhnoula, Sector-82, Gurugram
Sector
Sector 82
Tehsil / District
Manesar / Gurugram
Layout plan approved
8 Feb 2024
Building plans approved
8 Feb 2024
Construction start (as filed)
1 Mar 2024
Completion (as filed)
31 Dec 2028
Application submitted
11 Dec 2023
Authority, hearings & orders
Current statusApproved And Certificate Uploaded
Initial scrutinyFirst hearing
Next hearingNot Required
Application submitted online
Application received by HRERA Gurugram
Notice sent to the promoterDeficiency notice
HearingExamination By AuthorityView order Proceedings
Sh. Sumeet, Engineering Officer and Ms. Asha, Chartered Accountant briefed about the facts of the project. No reply has been submitted by the promoter company against the deficiencies conveyed by the authority through deficiency notice dated 28.12.2023. Therefore, in view of the same the matter is adjourned, and the next date of hearing will be conveyed after submission of reply of deficiencies already conveyed. Further, if no response is received from the promoter within next 4 week’s time, in that case the concerned official to put up the matter on file for issuance of show cause notice as to why their application for registration of project may not be rejected following the due procedure under the Act of 2016.
Sh. Sumeet, Engineering Officer and Sh. Ashish, Chartered Accountant briefed about the facts of the case. Shri S. Chaudhary (Head-Business Department) is present on behalf of the promoter. The AR of the promoter requests for one week’s time to submit the remaining documents. Request is allowed. Matter to come up on 19.02.2024.
HearingApproved And Ready For Certificate Issuing ProcessView order Proceedings
Sh. Sumeet Choudhary is present on behalf of the promoter. The AR of the promoter states that they are submitting the deficit fee including late fee and simultaneously request to consider the representation to waive off the late fee as the building plans and other statutory approvals are obtained or being obtained recently except licenses and zoning plan approval. The authority decides that the representation submitted by the promoter be put up on file along with AG opinion obtained in other such cases for taking the decision by the authority regarding applicability of late fee on the project registration application. The AR further states that fire scheme approval and service plan estimate approval is applied and the same will be submitted within 3 months from issuing RC for which the BG amounting Rs 25 lakh each are also being submitted in the authority. The environment clearance has already been recommended by the committee and vide letter dated 23.01.2024, the Member-secretary of SEIAA Haryana has conveyed to consider the approval after appointment of chairperson of SEIAA, Haryana. In view of the same, the authority grants four months’ time for submission of approved Environment Clearance failing which the penal proceedings including freezing of accounts shall be initiated. Further, the site of the project exists on 12 mt service road for which the access permission is not required, and the mining permission will be obtained and submitted before start of excavation/construction. The balance deficit documents will also be submitted within two days after making necessary corrections. In view of the above the Authority decides to grant the registration certificate. The RC shall be issued after submission of deficit documents.
Registration grantedGGM/788/520/2024/15
Certificate uploadedRC Uploaded
Registration valid till
Land, licence & cost
Land area of the project
7.65 acres
Total licensed area
7.65 acres
Licence
60 of 2013 ( 16-07-2013) and61of 2013(16-07-2013
FAR permissible / proposed
312 / 258.31
Estimated project cost
₹ 1,478.22 Cr
Cost of land
₹ 21.2 Cr
Cost of construction
₹ 508.68 Cr
Infrastructure and other structures
₹ 60.57 Cr
EDC, taxes, levies and other costs
₹ 887.77 Cr
How the land will be used
Use
Acres
Share
Land Area To Be Used For Construction Of Apartments
4.0473
52.9%
Construction Of Roads
1.88
24.6%
Parks And Playgrounds
0.554
7.2%
Vehicle Parkings
0.0082
0.1%
Any Other
1.1604
15.2%
Apartments 1,305 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
43,186.13
-
1305
Areas are as filed with HRERA. Some rows show a total built-up area rather than one home’s carpet area, as entered by the promoter.
External services
Service
Provided by
Approval taken
Roads
CONNECTED
Yes
Water Supply
GMDA
Yes
Electricity
DHBVN
Yes
Sewage Disposal
GMDA
Yes
Storm Water Drainage
GMDA
Yes
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 11.48 Cr
As Per Project Report
Water Supply System
₹ 3.18 Cr
As Per Project Report
Storm Water Drainage
₹ 2.7 Cr
As Per Project Report
Electricity Supply System
₹ 14.87 Cr
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 2.27 Cr
As Per Project Report
Street Lighting
₹ 1.71 Cr
As Per Project Report
Security And Fire Fighting
₹ 2.72 Cr
As Per Project Report
Playgrounds And Parks
₹ 71.81 lakh
As Per Project Report
Renewable Energy System
₹ 1.52 Cr
As Per Project Report
Parking
₹ 4.41 Cr
As Per Project Report
Stp
₹ 2.08 Cr
As Per Project Report
Under Ground Water Tank
₹ 3.28 Cr
As Per Project Report
Rain Water Harvesting
₹ 30.79 lakh
As Per Project Report
Electrical Sub Station
₹ 9.33 Cr
As Per Project Report
Statutory approvals
Approval
Status
Date
Aai
Already Been Obtained
12 Sep 2022
Building Plan
Already Been Obtained
8 Feb 2024
Licence 60 Of 2013
Already Been Obtained
16 Jul 2013
Licence 61 Of 2013
Already Been Obtained
16 Jul 2013
Revised Zoning Plan
Already Been Obtained
16 Dec 2013
Specifications (as filed)
Flooring Details Of Various Parts Of House
Stone /Tiles In Common Areas
Wall Finishing Details
Cement Plaster
Bathroom Fittings
Chinaware With Cp Fitting
Doors And Windos Frames
Aluminium/Ms Frame With Glass
Glass Work
6 Mmtoughened Glass And Above
Conducting And Wiring Details
Conduting Pvc Conduting With Wiring As Per Nbc
Water Storage
Yes
Lift Details
Yes
External Glazings
Aluminium/Ms Frame With Glass
Windows/Glazings
Aluminium/Ms Frame With Glass
Doors
Glass Doors Commercial Flush Door Shutters
Main Doors
Glass Doors
Internal Doors
Commercial Flush Door Shutters
Air Conditioning
As Per Dbr In Selected Spaces
Electrical Fittings
As Per Nbc
External Finishing/Colour Scheme
Plaster And Panting And Glazing Acp/Stone Cladding
Internal Finishing
Plaster And Panting And Glazing Acp/Stone Cladding
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Elan Imperial?
An advisor can check this project’s RERA record, approvals and possession timeline with you, and share current prices and availability. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.