by Wal Buildcon LLP · Sector 78, Village Naurangpur, Gurugram
RERA registration
Applied, not granted yet
Applied on
14 Sep 2026
Application status
Approved And Ready For Certificate Issuing Process
Project ID
RERA-GRG-2326-2026
Land area
0.988 acres
Apartments
90 in 1 tower
Completion (as filed)
31 Mar 2032
Estimated cost
₹ 113.09 Cr
This project has applied for RERA registration but has not been granted it yet. Under RERA it cannot be advertised, marketed or sold until it is registered.
RERA registration
Registration certificate
Not issued yet: the application is being processed by HRERA Gurugram
Project ID
RERA-GRG-2326-2026
Authority
HRERA Gurugram
Project type (as filed)
New
Project name
Ekantam By Yashika
Site address
Sector 78, Village Naurangpur, Gurugram
Sector
Sector 78
Tehsil / District
Manesar / Gurugram
Building plans approved
11 Sep 2026
Construction start (as filed)
1 Oct 2026
Completion (as filed)
31 Mar 2032
Application submitted
14 Sep 2026
Authority, hearings & orders
Current statusApproved And Ready For Certificate Issuing Process
Initial scrutinyFirst Hearing
Next hearingNot Required
Application submitted online
Notice sent to the promoterDeficiency notice
HearingExamination By AuthorityProceedings
The matter is adjourned to 21.10.2026.
HearingApproved And Ready For Certificate Issuing ProcessProceedings
Approved
Land, licence & cost
Land area of the project
0.988 acres
Total licensed area
0.988 acres
Licence
License No. 71 of 2026 dated 21.04.2026 granted by TCP, Haryana.
FAR permissible / proposed
2.37 / 2.36
Estimated project cost
₹ 113.09 Cr
Cost of land
₹ 10.11 Cr
Cost of construction
₹ 69.04 Cr
Infrastructure and other structures
₹ 2.95 Cr
EDC, taxes, levies and other costs
₹ 30.99 Cr
How the land will be used
Use
Area (as filed)
Share
Land Area To Be Used For Construction Of Apartments
0.1737
38.3%
Green Belts
0.2379
52.4%
Club House
0.042
9.3%
Apartments 90 units · 1 tower
Type
Carpet area (sq m)
Carpet area (sq ft)
Units
Apartment/Shops/Other Buildings
79.00
850
80
Apartment/Shops/Other Buildings
74.88
806
9
Apartment/Shops/Other Buildings
58.19
626
1
Areas are as filed with HRERA.
External services
Service
Provided by
Approval taken
Roads
Yes
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
4.Details of services and facilities which will be provided inside the project area as per service plan estimates and/or the project report:
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
20.00
AS PER PROJECT REPORT
2
Water Supply System
17.00
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
18.00
As Per Project Report
4
ELECTRICITY SUPPLY SYSTEM
40.00
AS PER PROJECT REPORT
5
Sewage Treatment & Garbage Disposal
18.00
AS PER PROJECT REPORT
6
STREET LIGHTING
12.00
As Per Project Report
7
SECURITY AND FIRE FIGHTING
0.00
AS PER PROJECT REPORT
8
Playgrounds And Parks
5.00
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
64.08
As Per Project Report
10
SHOPPING AREA
0.00
AS PER PROJECT REPORT
11
Renewable Energy System
0.00
AS PER PROJECT REPORT
12
SCHOOL
0.00
As Per Project Report
13
HOSPITAL/DISPENSARY
0.00
AS PER PROJECT REPORT
14
Any Other
0.00
AS PER PROJECT REPORT
15
PARKING
25.00
As Per Project Report
16
STP
100.00
AS PER PROJECT REPORT
17
Underground Water Tank
15.00
AS PER PROJECT REPORT
18
RAIN WATER HARVESTING
20.00
As Per Project Report
19
ELECTRICAL SUB STATION
0.00
AS PER PROJECT REPORT
20
Construction Of Circulation Road
5.00
AS PER PROJECT REPORT
5. (a) Date of approval of latest layout plans granted by Town & Country Planning Department on the basis of which the project will be executed.
NA
(date)
6. Date of approval of Building Plans
11-09-2026
(date)
7. New projects:
i) Likely date of starting the construction work
01-10-2026
ii) Likely date of completing the project
31-03-2032
iii) Sizes of the plots to be offered in the project
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
iv. Type of apartments to be constructed in the project:
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
79.00
80
1
Apartment/Shops/Other Buildings
74.88
9
1
Apartment/Shops/Other Buildings
58.19
1
1
(vi) Quarterly schedule of development of whole/remaining part of the project:
(c) Apartments/Shops/Other Buildings
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0.00
Shops
0.00
Plots
0.00
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
148.98
Shops
0
Plots
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
148.98
148.98
148.98
148.98
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
148.98
149.40
731.00
731.00
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
986.72
1053.27
455.51
455.51
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
455.51
456.12
199.80
199.80
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
200.53
Shops
0
Plots
0
(d) Infrastructure
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
2.13
Sewerage treatment & garbage disposal
2.25
Electricity Supply System
0
Storm Water Drainage
2.25
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Rain water harvesting
1.43
Parking
1.79
Underground water tank
1.07
Stp
7.14
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
2.13
2.13
2.13
2.13
Sewerage treatment & garbage disposal
2.25
2.25
2.25
2.25
Electricity Supply System
0
0
0
0
Storm Water Drainage
2.25
2.25
2.25
2.25
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Underground water tank
1.07
1.07
1.07
1.07
Rain water harvesting
1.43
1.43
1.43
1.43
Stp
7.14
7.14
7.14
7.14
Parking
1.79
1.79
1.79
1.79
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
2.13
2.13
2.13
0
Sewerage treatment & garbage disposal
2.25
2.25
2.25
0
Electricity Supply System
10.00
10.00
10.00
10.00
Storm Water Drainage
2.25
2.25
2.25
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Underground water tank
1.07
1.07
1.07
1.07
Parking
1.79
1.79
1.79
1.79
STP
7.14
7.14
7.14
7.14
Rain water harvesting
1.43
1.43
1.43
1.43
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
6.67
6.67
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
2.50
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Underground water tank
1.07
1.07
1.07
1.07
Construction of circulation road
1.25
1.25
1.25
Rain water harvesting
1.43
1.43
1.43
1.43
STP
7.14
7.14
7.14
7.14
Parking
1.79
1.79
1.79
1.79
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
6.67
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
2.50
Clubhouse/community centres
0
Shopping area
0
Other
0
Street Lighting
12.00
Rain water harvesting
1.44
Underground water tank
1.08
Stp
7.18
Parking
1.80
Construction of circulation road
1.25
It is hereby stated and declared and the above information is correct and true and nothing has been concealed or misrepresented.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - D
Accounts related information:
1. Annex copy of the balance sheet of last 3 years
Yes
2. In case of on-going projects,cash flow statement since start of the project up-to-date in folder D.
Total receipt of funds, sources of funds and deployment of funds should be stated in tabulated form.
No
3. Bank account to which the deposits received from apartment buyers will be credited
Bank and Branch address
ICICI BANK LIMITED, SUNCITY, GURGAON
Bank Account number
777705009240
IFSC code
ICIC0000399
MICR code
110229008
Branch code
0399
4. Name and address of the person/persons who would ordinarily be operating the account (Change at any time must be intimated to the Authority)
Amit Yadav, Pandwala Kalan, South West Delhi, Delhi-110043
5. Attach certificate issued by a Chartered Accountant that the applicant has not defaulted in its debt liabilities in the past five years in folder D. (In case of default, give details)
Yes
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - E
Details of the statutory approvals:
1. Annex copies of the following in Folder E:
i. Lay out Plan
No
ii. Demarcation Plan
Yes
iii. Zoning Plan
Yes
iv. Building Plan
Yes
Site Plan
Yes
Floor Plan
Yes
Apartment Plans
Yes
Elevation Section
Yes
Detail of Permissible FAR
Yes
Detail of covered area achieved FAR
Yes
2. Annex copies of the following in Folder E:
I. Roads And Pavement Plan
Yes
II. ELECTRICITY SUPPLY PLAN
Yes
III. WATER SUPPLY PLAN
Yes
IV. Sewerage And Garbage Disposal Plan
Yes
V. STROM WATER DRAINAGE
Yes
VI. 10% LAND TO BE TRANSFERRED TO THE GOVT. FOR COMMUNITY FACILITY
No
Vii. Street Lighting Plan
Yes
VIII. PARKING PLAN
Yes
3. Statutory Approvals Status
Statutory Approvals
Statutory Approvals Status
Date
I. LC- V
Already Been Obtained
21-04-2026
II. DEMARCATION CUM ZONING
Already Been Obtained
23-04-2026
III. FOREST NOC
Already Been Obtained
29-01-2026
IV. BR-III
Already Been Obtained
11-09-2026
It is undertaken that the project shall be completed within the time schedule given in Part C and the same will not be delayed on account of non- receipt of any of the statutory approval. The liability for the non-receipt of any of the statutory approval shall be that of the promoter and in case of delay, compensation as per law may be given to the allottees.
Signature _____________
Seal _____________
Date _____________
Form Rep-I
Part - F
1. A copy of the draft allotment letter by which the apartment shall be allotted/ booked in favour of the apartment buyers.
Yes
2. A copy of the Draft Agreement which shall be made before seeking any deposit exceeding 10% of the cost of the apartment. (Based on the model agreement prescribed in the Rules)
(Annex a copy in Folder F)
Yes
3. Gist of the important provisions of the Draft Agreement
(Annex a copy in Folder F)
Yes
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Form Rep-I
Part - G
Projects launched by the promoter in last five years: (No Projects)
I hereby declare that the above information and particulars are based on record and are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
FORM REP-I
Part - H
Specification Of Construction
Specification of apartments and other buildings including the following:
1
Flooring Details Of Various Parts Of House
LIVING/DRAWING ROOM-ISI VETRIFIED TILE,
BEDROOM- LAMINATED WOODEN FLOORING,
Kitchen- Anti Skid Tiles.
2
WALL FINISHING DETAILS
Internal Wall-Obd & Plastic Emulsion/ Isi Marked,
EXTERNAL WALL- TEXTURE.
3
Kitchen Details
AVAILABLE
4
Bathroom Fittings
WASH BASIN, TAPS AND FITTINGS.
5
Wood Work Etc
DOORS
6
Doors And Windos Frames
DOORS- PAINTED FLUSH DOOR,
WINDOWS- ALUMINIUM WITH 6MM TOUGHENED GLASS / AS PER WIND PRESSURE
7
GLASS WORK
TOUGHENED GLASS AS PER WIND PRESSURE.
8
ELECTRIC FITTINGS
ONLY PROVISIONS
9
CONDUCTING AND WIRING DETAILS
FRLS- HAVELLS OR EQUIVALENT
10
CUPBOARD DETAILS
N/A
11
WATER STORAGE
N/A
12
LIFT DETAILS
4 NO'S UNITS PER FLOOR, 2 PASSENGER LIFT, 1 SERVICE LIFT
13
EXTERNAL GLAZINGS
ALUMINIUM WITH 6MM TOUGHENED GLASS / AS PER WIND PRESSURE
13.1
WINDOWS/GLAZINGS
ALUMINIUM WITH 6MM TOUGHENED GLASS / AS PER WIND PRESSURE
14
DOORS
PAINTED FLUSH DOOR
14.1
MAIN DOORS
PAINTED FLUSH DOOR
14.2
INTERNAL DOORS
PAINTED FLUSH DOOR
15
AIR CONDITIONING
N/A
16
ELECTRICAL FITTINGS
PROVISIONS
17
CNG PIPE LINE
N/A
18
PROVISION OF WIFI AND BROADBAND FACILITY
AVAILABLE
19
EXTERNAL FINISHING/COLOUR SCHEME
TEXTURE
20
INTERNAL FINISHING
OBD & PLASTIC EMULSION/ ISI MARKED
Specification Unit Wise
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
Floor
ISI MARKED VETRIFIED TILE
1 . 2
Walls
PLASTIC EMULSION
1 . 3
Ceiling
OIL BOND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
LAMINATED WOODEN FLOORING
2 . 2
WALLS
PLASTIC EMULSION
2 . 3
CEILING
OIL BOND DISTEMPER
2 . 4
MODULAR WARDROBES
N/A
3 . Master Toilet
3 . 1
FLOOR
Anti Skid Tiles
3 . 2
WALLS
Ceramic Tiles
3 . 3
CEILING
Oil Bond Distemper
3 . 4
COUNTERS
Counters
3 . 5
SANITARY WARE/CP FITTINGS
Wash Basin, Taps And Fittings
3 . 6
FITTING/FIXTURES
Fittings
4 . BED ROOMS
4 . 1
Floor
LAMINATED WOODEN FLOORING
4 . 2
Walls
PLASTIC EMULSION
4 . 3
Ceiling
OIL BOND DISTEMPER
4 . 4
Wardrobes
N/A
5 . TOILET
5 . 1
FLOOR
ANTI SKID TILES
5 . 2
WALLS
CERAMIC TILES
5 . 3
CEILING
OIL BOND DISTEMPER
5 . 4
COUNTERS
COUNTERS
5 . 5
SANITARY WARE/CP FITTINGS
WASH BASIN, TAPS AND FITTINGS
5 . 6
FIXTURES
FITTINGS
6 . Kitchen
6 . 1
FLOOR
Anti Skid Tiles
6 . 2
WALLS
Ceramic Tiles/ Paint
6 . 3
CEILING
Oil Bond Distemper
6 . 4
COUNTERS
Counters
6 . 5
FIXTURES
Sink, Taps & Fittings
6 . 6
KITCHEN APPLIANCES
N/A
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
Floor
ANTI SKID TILES
7 . 2
Walls & Ceiling
WALLS- TEXTURE, CEILING- OIL BOND DISTEMPER
7 . 3
Toilet
N/A
7 . 4
Balcony
AVAILABLE
8 . SIT-OUTS
8 . 1
FLOOR
N/A
8 . 2
WALLS & CEILING
N/A
8 . 3
RAILINGS
N/A
8 . 4
FIXTURES
N/A
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
List of Uploaded Documents
Sr. No.
Document Description
Date of Document Upload
View Document
1
COPY OF LICENSE ALONG WITH SCHEDULE OF LAND
02-09-2026
View Document
2
Zoning Plan
02-09-2026
View Document
3
DEMARCATION PLAN
02-09-2026
View Document
4
IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN
13-09-2026
View Document
5
Non Default Certificate From A Chartered Accountant
12-09-2026
View Document
6
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.
12-09-2026
View Document
7
IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN
13-09-2026
View Document
8
Documents Relating To The Entry Of License And Collaboration Agreement In The Revenue Record
14-09-2026
View Document
I hereby declare that the above information and particulars are based on record and are true to the
best of my knowledge and belief and nothing has been concealed.
Signature of the Applicant / Authorised Representative
Stamp _____________
Date _____________
Print
Facilities in the service plan
Facility
Estimated cost
Status
Internal Roads And Pavements
₹ 20 lakh
As Per Project Report
Water Supply System
₹ 17 lakh
As Per Project Report
Storm Water Drainage
₹ 18 lakh
As Per Project Report
Electricity Supply System
₹ 40 lakh
As Per Project Report
Sewage Treatment & Garbage Disposal
₹ 18 lakh
As Per Project Report
Street Lighting
₹ 12 lakh
As Per Project Report
Playgrounds And Parks
₹ 5 lakh
As Per Project Report
Club House/Community Centre
₹ 64.08 lakh
As Per Project Report
Parking
₹ 25 lakh
As Per Project Report
Stp
₹ 1 Cr
As Per Project Report
Underground Water Tank
₹ 15 lakh
As Per Project Report
Rain Water Harvesting
₹ 20 lakh
As Per Project Report
Construction Of Circulation Road
₹ 5 lakh
As Per Project Report
Statutory approvals
Approval
Status
Date
Lc- V
Already Been Obtained
21 Apr 2026
Demarcation Cum Zoning
Already Been Obtained
23 Apr 2026
Forest Noc
Already Been Obtained
29 Jan 2026
Br-III
Already Been Obtained
11 Sep 2026
Specifications (as filed)
Flooring Details Of Various Parts Of House
Living/Drawing Room-Isi Vetrified Tile,
Source: HRERA Gurugram, Form REP-I, read on 23 Oct 2026. Figures are as filed by the promoter with HRERA. Always check the latest record on haryanarera.gov.in before you pay any money.
Speak to an advisor
Questions about Ekantam By Yashika?
This project has applied for RERA but is not registered yet. An advisor can tell you what that means for booking, and suggest registered alternatives nearby. No obligation.
We use cookies only to run this site and remember your shortlist, compare list and preferences. Visits are counted anonymously. No advertising cookies. Privacy policy
Private advisory
Speak to a Triverse advisor
Share your details and a senior advisor will call you back shortly.